Company office

Darwaza city {3}

Construction weekly Report


Prepared by: [ENG. Mohammed Tahseen]
Date: [ 17/12/2022]
⁄ ⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄

JOB DETAILS

Project Name: Building Office


Job Type: construction Job Number: 1

⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
WEATHER

Overall Conditions:

❏ Sunny ❏ Raining ❏ Fog


❏ Cloudy ❏ Thunderstorm ❏ Frost
❏ Partially cloudy ❏ Snow ❏ Wind

Wind speed: 13 mph


⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄

WORK ACCOMPLISHED
TASK STATUS
1- {17/12/2022} wooding board for last On work
10 columns, had been started
2- {17/12/2020} receiving 17 ballets
Ponza block, also transferring the
10x20 block and sand to first story
Done
and transferring the rest of
outside blocks to inside with the
sand and cements
3- {18/12/2022} 10 columns becoming
ready to concrete, and staircase
wall blocking started., and On work
excavators filling side of the
building
4- {19/12/2022} Preparing for stair
case steels and plywood, wall
Done
blocking floor one completed

CONSTRUCTION WEEKLY REPORT


5- {20/12/2022} concreting the
columns and the stair case, and
the building sides around 4 hours Done
three mixers (11m-35mpa-18m-
15mpa),
6- {21/12/2022} watering the
concrete and the columns,
on work
preparing the wooding frame at
the side of the building
7- {22/12/2022} wooding frame box
finished and sending the concrete
Done
cube boxes to lab, covering the
materials from been wet

⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
CREW LIST
CREW TYPE CREW NAME CREW NUMBER
SUPERVISOR KANYAW KARWAN 1
Asst. engineer MOHAMMED TAHSEEN 2

⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
MATERIAL QUANTITIES
# USED
MATERIAL TYPE # REMAINING

Cement 9 21 (50kg)
Steel #12mm 55,175 kg
Steel #10mm 16,155 kg
Steel #16mm 42,440 kg
Blocks (10x40) 1200

Concreting till first floor 214,16 𝑚3

Ponza block 200 4100


Blocks(20x40) 2500

CONSTRUCTION WEEKLY REPORT


⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
MATERIAL DELIVERIES
TYPE # SCHEDULED ARRIVAL
Ponza block 17 ballets 17/12/2022-monday-afternoon
block 2500 20/12/2022-Tuesday-afternoon

SIGNIFICANT EVENTS

EVENT TYPE DESCRIPTION POTENTIAL DELAY

Concreting all the columns in


Concreting
this week and the staircase [no]

⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄

SAFETY

Was a site inspection performed today?


❏ Yes
❏ No
Were there any safety incidents?

Mohammed Tahseen 17/12/2022

I, [Mohammed Tahseen], certify that I have completed this daily construction report and the information
herein is accurate and up-to-date to the best of my knowledge

____________________________________
[17/12/2022]

CONSTRUCTION WEEKLY REPORT