You are on page 1of 6

Planning and Phasing of Detailed Geotechnical

Investigations for Underground Structures


R. C. Bhandari

Abstract

Geo-technical Investigations plays a dominant role in deciding design param eters, construction
methodology including cost assessment for underground structures such as tunnels, power house
cavern during preparation o f Detailed Project Report (DPR). As every project has got unique
engineering components, a detailed understanding o f Geological and Geomorphological features
including stress field conditions o f the area surrounding the proposed project site are o f utmost
importance rather than adopting a cook book approach.
It is experienced in past that geological surprises encountered during construction, causes delays
and disputes during and after construction.
A well-planned exploration, if undertaken at investigation and design stage is always helpful in
evaluating feasibility, safety, design and economics of the project in more system atic and reliable
manner.
In the engineering project areas located in complex geological set up like Himalayas the cost and
feasibility param eters are being dominated by Geological factors. To overcome this challenge a
comprehensive knowledge o f regional geology Including structural geology o f the area and its
inter-relationship with cavern axis must be known. There must be adequate Geological / Geo­
technical inform ation including "Stress Field Conditions” to support the preparation o f the “Geo­
technical Design Summary Report (GDSR) forming the part o f Contract Document.
In order to forecast anticipated geological problems a detailed sub-surface exploration programme
including drillin g o f boreholes and G eo-physical survey is to be worked out on the basis of
detailed Geological walk over survey and maps prepared with help o f satellite imageries.
On the basis o f the results obtained from surface / sub-surface explorations, the Rock f\/lass
Q uality (RMO) is determined. Based on this a suitable geological model is prepared depicting
distribution of reach wise Rock Mass Quality (RMQ) of anticipated rock types, ground water conditions
and proposed method o f excavations including ground support system. The final Geo-technical
report that supports the Contract document has received considerable attention in recent past
because o f its legal significance to construction contract document. This is due to the fact the
sudden occurrence o f fa u lt/ shear zones requiring complete change in excavation method, support
system, results in delay in project schedule and cost escalation, leading to legal complications on
later date.

In tro d u c tio n thoroughly investigated during early phase


^ . ... . . . . , has lesser cost and lesser disputes.
Geology plays a significant role in choice of
alignment, design and deciding construction The most fundamental aspect of the Geo­
methodology of tunnels and other technical Investigation for tunnels/
underground structures. The unanticipated underground cavities is that, earlier the
geological problems always create delays, explorations made, the owner and designer
escalation of cost and disputes between has flexibility for optimization of alignment
construction agency and client. It is and deciding the construction methodology,
experienced in the past that the tunnels

Highway Division, Intercontinental Consultants and Technocrats Pvt. Ltd.. A-8, Green Park,
New D e lh i- 110016, INDIA
The experience shows it is not advisable to holes and tests should have the specific
go for design and construction before certain purpose of obtaining information of direct
levels of explorations are completed. In fact relevance to the design and construction of
it is also experienced in past that it is better tunnel scheme.
to have no data or knowledge rather than to
The stages and methods of acquisition of
have misleading data.
Geo-technical information for tunnels can be
summarized as:
C h a lle n g e s fa ce d in g e o -te c h n ic a l
investigations for underground works Route Corridor Identification
The challenges faced for Geo-technical Desk Study
Investigations required for underground Site Reconnaissance
projects located in the area having complex
geological set up are due to the following Preliminary Ground Investigations (if
facts: required)
• The Cost and Feasibility of the project Main Ground Investigation Field Work
is dominated by Geology. including Detailed Geological Mapping
and drilling of exploratory boreholes.
• Every feature like drilling and
Geophysical investigations of Geological Main Ground Investigation Laboratory
Investigation is more demanding than Work
traditional foundation engineering Interpretation of Main Ground
projects. Investigation findings
• There may be variation in regional Supplementary Ground Investigations (if
geology and tectonic set up of the area. required)
• Change in engineering properties of Interpretation of Supplementary Ground
rocks conditions, such as time, rate and Investigations
direction of loading etc. These properties
some time changes drastically. Establishment of Geo-technical Design
/Parameter values
• Ground water is most critical parameters
to predict as it creates problem during Preparation of Reference Ground
construction, requiring provision of Condition Report
additional elaborate drainage Review of Geotechnical Interpretive
arrangement before advancement. Report during construction
• Change in in-situ structural conditions
depending upon the tectonic setup of the Desl( s tu d y and s ite reconnaissance
area. A desk study of available literature maps,
aerial photograph, utility plans, existing
P lanning o f in ve s tig a tio n ground investigations etc. should be carried
The Geo-technical/Geological data collection out for all schemes. The existing information
and evaluation should begin early conceptual can be made available from the published
planning stage of any project and should literature about the area from national agency
continue through out construction and even like Geological Survey of India, National
after construction to document as built Remote Sensing Agency and concerned
behavior of tunnel. The governing principle in State Govt, departments. These studies attain
setting scopes of phased field and laboratory more importance where the project is
investigations should be that all exploratory proposed to be located in difficult terrain area.
Although recent technology advances have boreholes can be utilized for installation of
led to the availability of Satellite Imageries, piezometers.
which are updated frequently, there is no Although each project site is unique, there
substitute for conducting a site are no rigid rules which can be applied for
reconnaissance along proposed corridor to every project, but following aspects must be
get the best feel for final corridor selection considered for planning the detailed Geo­
and identification of locations of potential technical Investigations.
working for adits / shafts and work sites.
Character and Variability of ground
Normally this activity takes the form of a walk
over survey, which also provides the Nature of the Project.
opportunity to examine exposures of the Need for and scope of a Preliminary
ground and to confirm the reliability desk Investigations.
study data.
Location and Spacing of Exploratory
Field in v e s tig a tio n s holes.
Depth of Exploration s.
Selection o f method o f investigations
and scope of woric Purpose of exploratory hole.
There are number of field and laboratory Type of field in-situ and Laboratory tests.
investigations and testing methods of direct It is important to take boreholes to an
relevance to tunnel schemes, the method and adequate depth below proposed invert level,
scope of investigations applicable to any both because subsequent design changes
particular scheme will be governed by many could cause lowering of alignment, and
factors related to specific project. Qlossop secondly the zone of influence of the tunnel
(1968) has expressed valuable principle. may be extended by nature of the ground at
“If you do not know what you should be a greater depth.
looking for in a site investigation, you are not
likely to find much of value”. G ro u n d a p p re c ia tio n lin l( betw een
This is the important principle for strategy of in v e stig a tio n and design
site investigations, defining a specific purpose The ground appreciation, in other words, the
for every single exploratory hole collection interpretation of investigation data, forms
or soil sample, or rock core, samples, field essential link between factual information
test and laboratory test. This should ensure derived from desk studies, field and
that optimum value for money has been laboratory investigations and commencement
obtained from Sound Engineering of tunnel lining design process itself.
consideration. Interpretation involves the definition,
A phased Geo-technical Investigation description and quantification of the ground
programme is of great benefit in following conditions in a form that is relevant and
these principles. The findings of preliminary readily available for tunnel lining design team.
investigation enable the main investigations This imperative report may contain following:-
to be better tailored to suit the expected Brief about Scheme.
surface and sub-surface conditions, while a
supplementary investigation can be planned Description of Route Corridor.
to sweep up remaining doubts and knowledge Finding of Desk Study and Site
gaps left after assessing the results of main reconnaissance.
investigations. On the other hand, early
boreholes may, with economy, serve the Identification of route and alignment
purposes of a later phase, for example some options.
Summary of Ground Investigation another, depending upon the geological setup
Works. of the area.
Hydrology including discussions on The degree of detail study will also be guided
ground water by nature of design analysis. Establishing,
the Geo-technical properties of some
Interpretation of ground conditions in
Geological strata can be undertaken with
relation to Design and proposed
confidence, arising either from previous
construction methodology
tunneling experience within same strata or
Recommendations for design, from the fact that these strata are established
construction and further ground to be relatively uniform. For example when
investigations the Geological mapping indicates uniformity
The required Geo-technical design of the strata fewer number of boreholes will
be required, on the contrary the area having
parameters should be worked out in Geo-
complex geology will require more detailed
technical Interpretive Report, dealing with
explorations and number of boreholes may
interpretation of ground conditions in relation
be increased. The success of even a carefully
to design and construction. These are based
planned boring programme also depends
on the description of rock including their
greatly on quality of, on site inspection during
structural conditions, and results of In-situ
drilling operation.
and laboratory tests.
It is not uncommon for Geo-technical
The following table shows Geo-technical
Investigations even one investigation
parameters that are normally required to be
programme based on the most rigorous and
applied to tunnel lining design.
comprehensive survey, fails to reveal actual
For design of tunneling and selecting method ground conditions. In many cases,
of excavation, it is necessary to obtain remarkable departure is observed within
sufficient information on Geo-technical actual excavation conditions during
Design parameters. The amount of construction, than the interpreted data based
information required will vary from one site to on exploratory holes. The interpretative report
SI. No Type of T est Parameters Obtained Tunnel Design Applicability
1. Bulk Density Unit Weight Over burden pressure
2. Maximum and Minimum Density Maximum and Minimum Density Over burden pressure of ground
3. Moisture Content Moisture Content Type and State of Ground
4. Specific Gravity Specific Gravity Over burden pressure
Liquid and Plastic limits. Plasticity Liquid /
5. Plasticity Type and State of Ground
Index
6. Particle, Size Distribution Properties of Soil Composition Type of Ground
1. Unconfmed Compression Unconfmed Compressive Strength (UCS) Rock Strength
Point Load Index Strength, Unconlined
8. Point Load Strength Rock Strength
Compressive Strength
Undtained/ drained triaxial Soil / Rock Strength
9. Undrained Shear Strength
compression
Consolidated Undrained/ drained
10 . triaxial compression
Effective Stress Shear Strength Soil Strength
Frictional strength of soil grains
11. Shear Box Angle of shearing resistance and rock joints
Odometer / one dimensional Co-efficient of compressibility vertical drains
12. Soil stiffness
consolidation deformation
13. Laboratory Permeability Co-efficient of Permeability Soil Permeability
14. Poisson's ratio Poisson's ratio Ground stiffness
15. Chemical analysis PH Value Sulphate and Chloride Contents Lining Durability
16. Abrasion Abrasion Excavatability
must endeavour to consider as thoroughly as C ost o f e x p lo ra tio n s
possible a clear picture of ground conditions
as a whole. On the basis of experience it U.S.National Committee on Tunnelling
may be concluded that variation in interpreted Technology in 1984, has recommended
data and actual strata encountered during (a) The site exploration budget should
tunnel operations is controlled by following average 3.0% of Estimated Project Cost.
geological factors like:-
(b) Boring footage should average 1.5 linear
• Presence of ground water bearing or feet of borehole per route feet of tunnel.
layers of granular material within
cohesive strata. These recommendations were made on the
basis of experiences that sometimes even
• Cavities in rocks, solution features in 2 % for Geo-explorations was obviously too
limestone, sometimes partly or fully in low, as compared with average %1 2

filled with gravels, sands, silts and clays. expenditure incurred in project cost, that
• Sudden appearance of artesian were for payment against variation clause.
conditions not intercepted in boreholes This is usually due to unexpected adverse
during investigations. Geological condition causing higher cost and
delay in completion of project.
• The presence of sudden aquifers in
limestone was experienced way back in C o n s t r a in ts /e r r o r s m ade fo r
1970, in Sundernagar, Satluj (SST) part
g e ote chn ica l in v e s tig a tio n s
of Beas Satluj link project in Himachal
Pradesh. This problem was tackled by Detailed studies not taken up well in
making pre-drainage arrangement. time. This leads in proper location of
• Deviation in interpreted location of weak boreholes hence information collected
zones such as fault zones, shear zones sometimes is not useful.
at tunnel grade. This is attributed mainly Detailed Surface Geological Mapping and
due to folded nature of strata in Structural Analysis not undertaken
geologically complex area. timely.
• Sudden occurrence of methane / other Not enough time is given (usually
hazardous gas bearing strata. administrative pressure) for detailed
• Variation of rock stress conditions as per exploration as per site specific
rock cover. requirement.
Not enough money but more will be paid
Need o f e x p lo ra tio n s v is -a -v is size later. This is a casual approach and
o f cavern ultimately leads to collection of limited
The need of Geo-technical explorations data for design creating problem in later
varies with dimensions of underground date.
excavation. The larger the cavity more the Tendering of construction works before
additional explorations, as the cavities / the Site Investigation is completed. This
tunnels of larger dimensions may experience approach sometimes to disastrous and
more construction difficulties. Frequently leads to tremendous problem and even
method of construction changes with causes change in route/alignment.
increase in size of cavern and risks during
construction stage are greater so different The tender finalisation of documents and
Geo-technical field as well as laboratory tests award of contract of construction of tunnels
may be required to support increasingly more in Railway line project linking Katra and
detailed Geotechnical Synthesis. Srinagar, has resulted to design of tunnel
portals without adequate supports. This discussions held with Sri S.K. Mathur
resulted collapse in tunnel portals at nnany Consultant, during writing this paper.
places and forced the project authorities to
take a decision to change the alignment. R efe ren ce s
John O.BIckel, Thomas R.Kuesel, Elwyn H.King,
A cknow ledgem ent
(2004) : Tunnel Engineering Hand Book.
The author is thankful to Shri K. K. Kapila Second Edition.
Chaimnan and Managing Director ICT Pvt. Ltd. British Tunneling Society (2004): Tunnel Lining
for giving his consent to publish this paper. Design Guide, Thomas Telford London
The author also acknowledges the valuable 2004

You might also like