ITEM NO ITEM DESCRIPTION/ ACTIVITIES QUANTITY

I. EARTHWORKS
1.EXCAVATION 10
2.BACKFILL 2
II. CONCRETE WORKS
2.1. CONCRETING OF COLUMN FOOTING 6.00
2.2. CONCRETING OF COLUMN 8.10
2.3.CONCRETING OF TIE BEAM 2.50
2.4. CONCRETING OF SECOND FLOOR BEAM 5.00
2.5. CONCRETING OF ROOF BEAM-1 AND 2 4.20
2.6.CONCRETING OF GROUND FLOOR AND SECOND FLOOR SLAB 9.00
III. FORMWORKS AND SCAFFOLDINGS 1.00
3.1 PREPARATION OF FORMS
3.2. INSTALLATION OF FORMS
3.3 REMOVING OF FORMS
3.4 INSTALLATION OF SCAFFOLDING
3.5 REMOVING OF SCAFFOLDING
IV. MASONRY WORKS 265.000
4.1. LAYING OF CHB
4.2 PLASTERING
V. STEEL WORKS 1.00
1.PREPARATION OF RSB
2. INSTALLATION OF RSB IN COLUMN FOOTING
3.INSTALLATION OF RSB IN COLUMN
4. INSTALLATION OF RSB IN ROOF BEAM
5. INSTALLATION OF RSB IN WALL FOOTING
6.INSTALLATION OF RSB IN GROUND SLAB AND SECOND FLOOR SLAB
VI. ROOFING WORKS 62.00
VII. CEILING WORKS 1.00
VIII. TILE WORKS AND PLASTER FINISH 370.00
IX. DOORS AND WINDOWS 1.00
X. ELECTRICAL WORKS 1.00
XI. PLUMBING WORKS 1.00
XII. PAINTING WORKS 1.00
UNIT AMOUNT % NUMBER OF DAYS WEEK 1
1 2 3
cu.m 6,000.00 4.92 3 4.92%
cu.m 11,244.00 1.64 1

cu.m 39,630.00 3.28 2


cu.m 90,492.71 8.19 5
cu.m 24,788.75 3.28 2
cu.m 53287.50 6.56 4
cu.m 40755.50 4.92 3
cu.m 58,327.47 4.92 3
l.s 40355.00 4.92
0.5 0.82%
1
0.5
0.5
0.5
sq.m 75,156.65 4.92
2
1
l.s 47,188.25 6.56
0.5 0.82%
0.5
0.5
1
0.5
1
sq.m 62,649.76 4.92 3
l.s 30000.00 8.19 5
sq.m 72,750.00 8.19 5
l.s 40,000.00 6.56 4
l.s 39,613.02 4.92 3
l.s 36,875.00 4.92 3
l.s 25,000.00 8.19 5
100 61
WEEK 1 WEEK 2
3 4 5 6 1 2 3 4

1.64% 1.64%
8.00%
3.28% 3.28%
4.10% 3.28%

0.82%
1.64%
0.82%

0.82% 0.82%
0.82% 0.82% 0.82%
0.82%

1.64%
EEK 2 WEEK 3
5 6 1 2 3 4 5 6 1

4.10% 4.10%
3.28%
6.56% 6.56%
4.92% 4.92%
WEEK 4 WEEK 5
2 3 4 5 6 1 2 3 4

2.46% 2.46% 2.46%


WEEK 5 WEEK 6
4 5 6

2.46%
WEEK 7 W
WEEK 8 WEEK 9
WEEK 10
WEEK 11
ITEM NO ITEM DESCRIPTION/ ACTIVITIES QUANTITY UNIT

I. EARTHWORKS
1.EXCAVATION 10 cu.m
2.BACKFILL 2 cu.m
II. CONCRETE WORKS
2.1. CONCRETING OF COLUMN FOOTING 6.00 cu.m
2.2. CONCRETING OF COLUMN 8.10 cu.m
2.3.CONCRETING OF TIE BEAM 2.50 cu.m
2.4. CONCRETING OF SECOND FLOOR BEAM 5.00 cu.m
2.5. CONCRETING OF ROOF BEAM-1 AND 2 4.20 cu.m
2.6.CONCRETING OF GROUND FLOOR AND SECOND FLOOR SLAB 9.00 cu.m
III. FORMWORKS AND SCAFFOLDINGS 1.00 l.s
3.1 PREPARATION OF FORMS
3.2. INSTALLATION OF FORMS
3.3 REMOVING OF FORMS
3.4 INSTALLATION OF SCAFFOLDING
3.5 REMOVING OF SCAFFOLDING
IV. MASONRY WORKS 265.000 sq.m
4.1. LAYING OF CHB
4.2 PLASTERING
V. STEEL WORKS 1.00 l.s
1.PREPARATION OF RSB
2. INSTALLATION OF RSB IN COLUMN FOOTING
3.INSTALLATION OF RSB IN COLUMN
4. INSTALLATION OF RSB IN ROOF BEAM
5. INSTALLATION OF RSB IN WALL FOOTING
6.INSTALLATION OF RSB IN GROUND SLAB AND SECOND FLOOR SLAB
VI. ROOFING WORKS 62.00 sq.m
6.1 FABRICATION OF TRUSS
6.2 INSTALLATION OF TRUSS
VII. CEILING WORKS 1.00 l.s
7.1 INSTALLATION OF CEILING JOIST
7.2 INSTALLATION OF CEILING
VIII. TILE WORKS AND PLASTER FINISH 370.00 sq.m
IX. DOORS AND WINDOWS 1.00 l.s
X. ELECTRICAL WORKS 1.00 l.s
XI. PLUMBING WORKS 1.00 l.s
XII. PAINTING WORKS 1.00 l.s
AMOUNT % NUMBER OF DAYS WEEK 1
1 2 3 4 5
###
6,000.00 4.92 3
11,244.00 1.64 1 4.92%

39,630.00 3.28 2
90,492.71 8.19 5
24,788.75 3.28 2
53287.50 6.56 4
40755.50 4.92 3
58,327.47 4.92 3
40355.00 4.92 3
0.5 0.82%
1 1.64%
0.5
0.5
0.5
75,156.65 4.92 3
2
1
47,188.25 6.56 4
0.5 0.82% 0.82%
0.5 0.82% 0.82%
0.5 0.82% 0.82%
1
0.5
1
62,649.76 4.92 3
1
2
30000.00 8.19 5
2

72,750.00 8.19 5
40,000.00 6.56 4
39,613.02 4.92 3
36,875.00 4.92 3
25,000.00 8.19 5
WEEK 2
5 6 1 2 3 4 5 6

1.64%
1.64%
3.28%
3.28% 4.10%
3.28%

1.64%
0.82%

0.82%
WEEK 3 WEEK
1 2 3 4 5 6 1 2

4.10%
3.28%
### 6.56%

3.28%

1.69%
### 1.69%
WEEK 4 WEEK 5
3 4 5 6 1 2 3 4

6.56%
4.92% 4.92% 4.92%
4.92%

0.82%

### 1.69% ###

### 1.69% 1.69%


WEEK 5 WEEK 6
4 5 6 1 2 3

4.92% 4.92%%

0.82%
0.82%

1.64%

1.69%
WEEK 6
4 5 6 1 2

0.82% 0.82%

1.64%
1.64%
3.28%
WEEK 7
3 4 5 6 1

1.64%

1.64%
WEEK 8
2 3 4 5 6
WEEK 9
1 2 3 4 5
WEEK 10
6 1 2 3 4
WEEK 10
5 6 1 2 3
WEEK 10
4 5 6