You are on page 1of 34

Day : Tuesday

Date : 24-Nov-20
Hari
Daily Report Weeks : 102

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 5 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 5 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 9 0 0


b.1.1 Casting concrete for column GF and tie beam PoP ToC -0.050 ### s/d ### 6 2 9 0 0 m3 start working for cleaning and shifting materiel
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 12 4 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 10 0 4 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 5 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 11 8 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 8 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 13 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 6 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 5 5 0 0


d.1.1 Fabrication Rebar ### s/d ### 12 5 1 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 12 0 0 0 0 kg
d.1.4 Erection and install rebar column GF PoP ### s/d ### 10 0 4 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 5 0 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg
d.2.2 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 12 5 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 15 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar beam and slab first floor PoP ToC +5.250 (zone 2 ### s/d ### 10 0 7 0 0 kg sims
d.3.3 Install rebar slab first floor PoP ToC +5.250 (zone 4a) ### s/d ### 15 0 8 0 0 kg sims

E. Masonry 4 47 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 11 0 0 m2 sirius
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 20 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 12 4 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 12 0 10 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 0 4 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 0 0 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 10 0 3 0 0 m2 sirius
f.4 Plastering for paraphet roof PoP ToC +10.800 ### s/d ### 10 0 1 0 0 m2 wala group
f.5 ### s/d ### 0 0 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 36 18 0 0 ls
k.1 Storing ### s/d ### -7 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 6 3 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 9 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 10 3 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
75 120
ENG 7 HC / GA 7
23 - 36° C 10 0 195 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Sunday
Date : 1-Nov-20
Hari
Daily Report Weeks : 98

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 5 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area corridor on zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area beam PoP ### s/d ### 10 0 5 0 0 m3 levelliing until below slab on ground and castin
a.4 Levelling land for lc tie beam HoS ### s/d ### 0 0 0 0 0

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 2 8 0 0


b.2.1 Casting concrete for column GF PoP ### s/d ### 2 2 8 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 6 6 0 0


c.1.1 Workshop ### s/d ### 10 1 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 1 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 10 0 6 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP ### s/d ### 10 4 0 0 0 m2
c.1.5 ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 11 0 0 0


c.2.1 Dishutter formwork beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Install formwork for beam and slab corridor on zone 1 ToC -0 ### s/d ### 0 0 0 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ### s/d ### 10 11 0 0 0 m2
c.2.4 Install formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.5 ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 3 0 0


c.3.1 Dishutter formwork ring beam and slab first floor PoP ### s/d ### 10 0 3 0 0 m2
c.3.2 ### s/d ### 0 0 0 0 0 m2
c.3.3 ### s/d ### 0 0 0 0 0 m2
c.3.4 ### s/d ### 0 0 0 0 0 m2
c.3.5 ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 5 0 0 0


d.1.1 Fabrication Rebar ### s/d ### 0 0 0 0 0 kg
d.1.2 Prefabrication and erection rebar for column PoP ### s/d ### 10 5 0 0 0 kg
d.1.3 ### s/d ### 0 0 0 0 0 kg
d.1.4 ### s/d ### 0 0 0 0 0 kg
d.1.5 ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 0 8 0 0


d.2.1 Install rebar beam FF PoP ToC +5.250 ### s/d ### 0 0 0 0 0 kg
d.2.2 Install rebar beam FF PoP ToC +5.250 ### s/d ### 10 0 8 0 0 kg sims
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab corridor on zone 1 ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 14 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.2 Install brick for window and corridor area ballroom ### s/d ### 9 0 8 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 0 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 2 0 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 10 2 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering wall for post control type 1 unit 1 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 14 8 0 0 ls
k.1 Storing ### s/d ### 10 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 3 5 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 0 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 10 0 2 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 0 0 0 0 0 ls
k.10 Equipment assistant ### s/d ### 10 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 0 0 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Repair and made a new pallet ### s/d ### 0 0 0 0 0 m2
k.19 Install rebar and formwork for column pratice and lintel beam ### s/d ### 0 0 0 0 0 m2
k.20 Grouting a column metal structure of a roof ballroom ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure for foor balrrom ### s/d ### 10 3 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
40 52
ENG 7 HC / GA 7
26 - 35° C 10 0 92 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Monday
Date : 2-Nov-20
Hari
Daily Report Weeks : 99

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 4 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area tie beam on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 12 0 4 0 0 m3 5 person finish at 17.00 ; 2 person cleaning roof
a.4 ### s/d ### 0 0 0 0 0

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 2 9 0 0


b.3.1 Casting concrete for ring beam and slab roof PoP ### s/d ### 8 2 9 0 0 m3 start working for dishutter formwork, cleaning a
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 10 0 0


c.1.1 Workshop ### s/d ### 12 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 12 0 8 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP ### s/d ### 10 6 2 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 12 2 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 10 0 2 0 0 m2 sims
c.2.2 Install formwork for beam HoS ToC -2.200 ### s/d ### 0 0 0 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 12 12 0 0 0 m2
c.2.4 Install formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 10 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 11 4 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 6 0 0 0 kg
d.1.2 Prefabrication and erection rebar for column PoP ### s/d ### 12 5 0 0 0 kg
d.1.3 Manual erection for rebar column corridor on zone 1 ### s/d ### 0 0 0 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 1 0 0 0


d.2.1 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 1 0 0 0 kg
d.2.2 Install rebar for tie beam HoS ToC -2.200 ### s/d ### 0 0 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 12 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab FF PoP ToC +5.250 ### s/d ### 10 0 12 0 0 kg sims

E. Masonry 0 36 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 10 0 9 0 0 m2 wala group
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 18 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 2 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 10 0 2 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 10 4 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering wall for post control type 1 unit 1 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 33 26 0 0 ls
k.1 Storing ### s/d ### 12 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 2 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 15 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 0 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 3 7 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 0 0 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 6 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Ansembling mockarabieh ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 10 0 1 0 0 m3
k.21 Install metal roof for ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 10 1 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 110
ENG 7 HC / GA 7
23 - 37° C 10 0 186 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Tuesday
Date : 3-Nov-20
Hari
Daily Report Weeks : 99

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 4 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area tie beam on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 10 0 4 0 0 m3
a.4 ### s/d ### 0 0 0 0 0

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 1 9 0 0


b.3.1 Casting concrete for column GF and slab PoP ToC -0.050 ### s/d ### 6 1 9 0 0 m3 start working for dishutter formwork, cleaning a
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 12 8 0 0


c.1.1 Workshop ### s/d ### 12 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 3 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 12 0 8 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP ### s/d ### 10 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 2 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 10 0 2 0 0 m2 sims
c.2.2 Install formwork for beam HoS ToC -2.200 ### s/d ### 0 0 0 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 12 13 0 0 0 m2
c.2.4 Install formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 10 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 11 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 6 0 0 0 kg
d.1.2 Prefabrication and erection rebar for column PoP ### s/d ### 12 5 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 12 0 2 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 2 6 0 0


d.2.1 Install rebar for beam roof PoP ToC +10.800 ### s/d ### 10 2 6 0 0 kg sims
d.2.2 Install rebar for tie beam HoS ToC -2.200 ### s/d ### 0 0 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 6 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 10 0 6 0 0 kg sims

E. Masonry 0 37 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 10 0 9 0 0 m2 wala group
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 19 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 6 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 10 0 6 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 10 4 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering wall for post control type 1 unit 1 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 33 25 0 0 ls
k.1 Storing ### s/d ### 12 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 2 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 15 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 2 7 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 6 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Ansembling mockarabieh ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal roof for ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 114
ENG 7 HC / GA 7
23 - 37° C 10 0 190 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Wednesday
Date : 4-Nov-20
Hari
Daily Report Weeks : 99

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 6 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area tie beam on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 12 0 6 0 0 m3
a.4 ### s/d ### 0 0 0 0 0

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 1 9 0 0


b.3.1 Casting concrete for column GF and beam and slab PoP ToC + ### s/d ### 7 1 9 0 0 m3 start working for dishutter formwork, cleaning a
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 8 0 0


c.1.1 Workshop ### s/d ### 12 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 12 0 8 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP ### s/d ### 10 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 2 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 10 0 2 0 0 m2 sims
c.2.2 Install formwork for beam HoS ToC -2.200 ### s/d ### 0 0 0 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 12 4 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 12 9 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 10 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 11 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 6 0 0 0 kg
d.1.2 Prefabrication and erection rebar for column PoP ### s/d ### 12 5 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 12 0 2 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 2 6 0 0


d.2.1 Install rebar for beam roof PoP ToC +10.800 ### s/d ### 10 2 6 0 0 kg sims
d.2.2 Install rebar for tie beam HoS ToC -2.200 ### s/d ### 0 0 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 6 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 10 0 6 0 0 kg sims

E. Masonry 0 43 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 10 0 9 0 0 m2 wala group
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 25 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 6 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 10 0 6 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 10 4 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering wall for post control type 1 unit 1 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 32 23 0 0 ls
k.1 Storing ### s/d ### 12 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 2 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 15 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 1 5 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 6 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Ansembling mockarabieh ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal roof for ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 120
ENG 7 HC / GA 7
23 - 38° C 10 0 196 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Thursday
Date : 5-Nov-20
Hari
Daily Report Weeks : 99

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 2 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area tie beam on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 12 0 2 0 0 m3
a.4 ### s/d ### 0 0 0 0 0

B.1 CONCRETE FOR COLUMN 2 8 0 0


b.1.1 Casting concrete for column GF ### s/d ### 4 2 8 0 0 m3 start working for dishutter formwork, cleaning a
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 8 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 12 0 8 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP ### s/d ### 10 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 0 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Install formwork for beam HoS ToC -2.200 ### s/d ### 0 0 0 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 10 4 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 9 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 10 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 11 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 6 0 0 0 kg
d.1.2 Prefabrication and erection rebar for column PoP ### s/d ### 10 5 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 2 6 0 0


d.2.1 Install rebar for beam roof PoP ToC +10.800 ### s/d ### 10 2 6 0 0 kg sims
d.2.2 Install rebar for tie beam HoS ToC -2.200 ### s/d ### 0 0 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 7 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 10 0 7 0 0 kg sims

E. Masonry 0 41 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 10 0 8 0 0 m2 wala group
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 24 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 7 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 10 0 7 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 10 4 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering wall for post control type 1 unit 1 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 31 21 0 0 ls
k.1 Storing ### s/d ### 12 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 2 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 0 7 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 2 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Ansembling mockarabieh ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal roof for ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 111
ENG 7 HC / GA 7
23 - 38° C 10 0 187 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Friday
Date : 6-Nov-20
Hari
Daily Report Weeks : 99

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 2 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area tie beam on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 12 0 2 0 0 m3
a.4 ### s/d ### 0 0 0 0 0

B.1 CONCRETE FOR COLUMN 2 8 0 0


b.1.1 Casting concrete for column GF PoP and screed roof HoS ToC ### s/d ### -16 2 8 0 0 m3 Preparing for working with night shift 15.00 - 0
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 11 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 13 0 11 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP ### s/d ### 10 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 0 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Install formwork for beam HoS ToC -2.200 ### s/d ### 0 0 0 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 10 4 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 9 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 10 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 11 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 6 0 0 0 kg
d.1.2 Prefabrication and erection rebar for column PoP ### s/d ### 10 5 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 2 6 0 0


d.2.1 Install rebar for beam roof PoP ToC +10.800 ### s/d ### 10 2 6 0 0 kg sims
d.2.2 Install rebar for tie beam HoS ToC -2.200 ### s/d ### 0 0 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 7 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 10 0 7 0 0 kg sims

E. Masonry 0 41 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 10 0 8 0 0 m2 wala group
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 24 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 6 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 10 0 6 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 10 4 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering wall for post control type 1 unit 1 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 31 21 0 0 ls
k.1 Storing ### s/d ### 12 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 2 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 0 7 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 2 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Repair and installing doors in SVB and HoS ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure for roof of ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 113
ENG 7 HC / GA 7
23 - 38° C 10 0 189 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Saturday
Date : 7-Nov-20
Hari
Daily Report Weeks : 99

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 2 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area tie beam on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 12 0 2 0 0 m3
a.4 ### s/d ### 0 0 0 0 0

B.1 CONCRETE FOR COLUMN 2 8 0 0


b.1.1 Casting concrete for column GF, lc tie beam and footing, rin ### s/d ### -6 2 8 0 0 m3 concrete team working for night shift 15.00 - 00
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 10 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 16 0 10 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP ### s/d ### 10 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 0 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Install formwork for beam HoS ToC -2.200 ### s/d ### 0 0 0 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 10 4 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 9 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 10 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 11 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 6 0 0 0 kg
d.1.2 Prefabrication and erection rebar for column PoP ### s/d ### 10 5 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 2 3 0 0


d.2.1 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 2 3 0 0 kg sims
d.2.2 Install rebar for tie beam HoS ToC -2.200 ### s/d ### 0 0 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 41 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 10 0 8 0 0 m2 wala group
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 24 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 6 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 10 0 6 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 10 4 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering wall for post control type 1 unit 1 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 31 21 0 0 ls
k.1 Storing ### s/d ### 12 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 2 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 0 7 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 2 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Repair and installing doors in SVB and HoS ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure for roof of ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 102
ENG 7 HC / GA 7
23 - 38° C 10 0 178 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Sunday
Date : 8-Nov-20
Hari
Daily Report Weeks : 99

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 0 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area corridor on zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area beam PoP ### s/d ### 0 0 0 0 0 m3
a.4 Levelling land for lc tie beam HoS ### s/d ### 0 0 0 0 0

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 6 4 0 0


c.1.1 Workshop ### s/d ### 0 0 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 2 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 10 0 4 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP ### s/d ### 10 4 0 0 0 m2
c.1.5 ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 6 0 0 0


c.2.1 Dishutter formwork beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Install formwork for beam and slab corridor on zone 1 ToC -0 ### s/d ### 0 0 0 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ### s/d ### 10 6 0 0 0 m2
c.2.4 Install formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.5 ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 5 3 0 0


c.3.1 Dishutter formwork ring beam and slab first floor PoP ### s/d ### 10 0 3 0 0 m2
c.3.2 Install formwork slab FF PoP ### s/d ### 10 5 0 0 0 m2
c.3.3 ### s/d ### 0 0 0 0 0 m2
c.3.4 ### s/d ### 0 0 0 0 0 m2
c.3.5 ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 11 0 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 5 0 0 0 kg
d.1.2 Install rebar footing and pedestal column PoP ### s/d ### 10 6 0 0 0 kg
d.1.3 ### s/d ### 0 0 0 0 0 kg
d.1.4 ### s/d ### 0 0 0 0 0 kg
d.1.5 ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 0 8 0 0


d.2.1 Install rebar tie beam GF PoP ToC -0.050 ### s/d ### 10 0 3 0 0 kg sims
d.2.2 Install rebar beam FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 kg sims
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab corridor on zone 1 ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 22 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 10 0 8 0 0 m2 wala group
e.2 Install brick for window and corridor area ballroom ### s/d ### 9 0 8 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 0 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 0 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 10 4 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering wall for post control type 1 unit 1 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 15 8 0 0 ls
k.1 Storing ### s/d ### 10 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 3 5 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 0 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 10 0 2 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 0 0 0 0 0 ls
k.10 Equipment assistant ### s/d ### 10 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 0 0 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Repair and made a new pallet ### s/d ### 0 0 0 0 0 m2
k.19 Install rebar and formwork for column pratice and lintel beam ### s/d ### 0 0 0 0 0 m2
k.20 Grouting a column metal structure of a roof ballroom ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure for foor balrrom ### s/d ### 10 3 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 10 1 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
47 45
ENG 7 HC / GA 7
25 - 36° C 10 0 92 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Monday
Date : 9-Nov-20
Hari
Daily Report Weeks : 100

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 0 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area tie beam on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 10 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 8 0 0


b.1.1 Casting concrete for column GF, footing PoP, screed roof HoS ### s/d ### -13 2 8 0 0 m3 concrete team working for night shift 15.00 - 00
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 4 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 12 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 16 0 4 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP ### s/d ### 12 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 12 7 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 7 0 0 m2 sims
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 12 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 7 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 10 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 11 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 12 6 0 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 10 5 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 2 17 0 0


d.2.1 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 2 5 0 0 kg sims
d.2.2 Install rebar for tie beam GF PoP ToC -0.050 ### s/d ### 10 0 12 0 0 kg sims
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 41 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 10 0 8 0 0 m2 wala group
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 24 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 3 6 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 10 0 6 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 12 3 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering wall for post control type 1 unit 1 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 33 23 0 0 ls
k.1 Storing ### s/d ### 12 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 2 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 2 6 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 5 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Repair and installing doors in SVB and HoS ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure for roof of ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 117
ENG 7 HC / GA 7
23 - 38° C 10 0 193 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Tuesday
Date : 10-Nov-20
Hari
Daily Report Weeks : 100

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 0 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area tie beam on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 10 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 8 0 0


b.1.1 Casting concrete for column GF, footing PoP, screed roof HoS ### s/d ### -16 2 8 0 0 m3 concrete team working for night shift 15.00 - 00
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 4 0 0


c.1.1 Workshop ### s/d ### 15 3 0 0 0 m2 closed a guardrail of project 18.00 - 22.00
c.1.2 Fabrication on site ### s/d ### 12 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 16 0 4 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 7 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 7 0 0 m2 sims
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 12 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 12 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 11 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 6 0 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 10 5 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 2 15 0 0


d.2.1 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 2 5 0 0 kg sims
d.2.2 Install rebar for tie beam GF PoP ToC -0.050 ### s/d ### 10 0 10 0 0 kg sims
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 41 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 10 0 7 0 0 m2 wala group
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 25 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 3 0 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 10 3 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering wall for post control type 1 unit 1 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 32 23 0 0 ls
k.1 Storing ### s/d ### 12 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 2 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 1 5 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 6 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Repair and installing doors in SVB and HoS ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure for roof of ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 109
ENG 7 HC / GA 7
23 - 38° C 10 0 185 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Wednesday
Date : 11-Nov-20
Hari
Daily Report Weeks : 100

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 0 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area tie beam on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 8 0 0


b.1.1 Casting concrete for column GF, Pedestal column PoP, Tie be ### s/d ### 6 2 8 0 0 m3 concrete team working for night shift 15.00 - 00
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 4 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 12 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 16 0 4 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 11 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 11 0 0 m2 sims (7 person finish at 22.00)
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 12 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 12 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 10 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 5 0 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 10 5 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 2 15 0 0


d.2.1 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 2 5 0 0 kg sims
d.2.2 Install rebar for tie beam GF PoP ToC -0.050 ### s/d ### 10 0 10 0 0 kg sims
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 37 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 10 0 2 0 0 m2 wala group
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 26 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 11 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 2 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 12 4 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering a wall paraphet of a roof ballroom ToC +9.600 ### s/d ### 10 0 9 0 0 m' wala group

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 32 23 0 0 ls
k.1 Storing ### s/d ### 12 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 2 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 1 5 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 6 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Repair and installing doors in SVB and HoS ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure for roof of ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 120
ENG 7 HC / GA 7
23 - 38° C 10 0 196 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Thursday
Date : 12-Nov-20
Hari
Daily Report Weeks : 100

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 0 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area tie beam on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 8 0 0


b.1.1 Casting concrete for column GF, Pedestal column PoP, Tie be ### s/d ### 7 2 8 0 0 m3 concrete team working for night shift 15.00 - 00
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 0 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 10 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 11 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 11 0 0 m2 sims (7 person finish at 22.00)
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 10 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 10 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 5 0 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 10 5 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 2 5 0 0


d.2.1 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 2 5 0 0 kg sims
d.2.2 Install rebar for tie beam GF PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 33 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 24 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 13 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 2 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 10 4 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering a wall paraphet of a roof ballroom ToC +9.600 ### s/d ### 10 0 11 0 0 m' wala group

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 32 23 0 0 ls
k.1 Storing ### s/d ### 18 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 2 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 1 5 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 6 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Repair and installing doors in SVB and HoS ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure for roof of ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 104
ENG 7 HC / GA 7
23 - 37° C 10 0 180 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Friday
Date : 13-Nov-20
Hari
Daily Report Weeks : 100

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 0 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area tie beam on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 8 0 0


b.1.1 Casting concrete for screed roof HoS, tie beam GF PoP ### s/d ### 6 2 8 0 0 m3 concrete team working for night shift 15.00 - 00
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 0 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 12 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 11 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 11 0 0 m2 sims (7 person finish at 22.00)
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 12 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 12 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 11 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 6 0 0 0 kg
d.1.2 Install rebar retaining wall corridor PoP ### s/d ### 12 5 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 2 5 0 0


d.2.1 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 2 5 0 0 kg sims
d.2.2 Install rebar for tie beam GF PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 33 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 24 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 17 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 2 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 12 4 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 9 0 4 0 0 m2 sirius
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering a wall paraphet of a roof ballroom ToC +9.600 ### s/d ### 10 0 11 0 0 m' wala group

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 31 23 0 0 ls
k.1 Storing ### s/d ### 18 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 0 5 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 6 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Repair and installing doors in SVB and HoS ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure for roof of ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 108
ENG 7 HC / GA 7
23 - 37° C 10 0 184 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Saturday
Date : 14-Nov-20
Hari
Daily Report Weeks : 100

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 0 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area tie beam on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 8 0 0


b.1.1 Casting concrete for beam and slab FF PoP ### s/d ### 6 2 8 0 0 m3 concrete team working for night shift 15.00 - 00
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 0 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 12 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 11 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 11 0 0 m2 sims (7 person finish at 22.00)
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 12 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 12 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 12 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 6 0 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 10 6 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 1 5 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 10 1 5 0 0 kg sims
d.2.2 Install rebar for tie beam GF PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 39 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 22 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 12 0 8 0 0 m2 wala group
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 12 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 2 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 12 4 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 9 0 7 0 0 m2 sirius
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering a wall paraphet of a roof ballroom ToC +9.600 ### s/d ### 10 0 3 0 0 m' wala group

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 31 23 0 0 ls
k.1 Storing ### s/d ### 18 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 0 5 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 6 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Repair and installing doors in SVB and HoS ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure for roof of ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 109
ENG 7 HC / GA 7
23 - 37° C 10 0 185 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Sunday
Date : 15-Nov-20
Hari
Daily Report Weeks : 100

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 0 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Backfilling area corridor on zone 1 ### s/d ### 0 0 0 0 0 m3
a.3 Backfilling area beam PoP ### s/d ### 0 0 0 0 0 m3
a.4 Levelling land for lc tie beam HoS ### s/d ### 0 0 0 0 0

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 9 4 0 0


c.1.1 Workshop ### s/d ### 0 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 3 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 10 0 4 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP ### s/d ### 10 3 0 0 0 m2
c.1.5 ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 14 0 0 0


c.2.1 Dishutter formwork beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Install formwork for beam and slab FF PoP ToC +5.250 ### s/d ### 10 5 0 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ToC 10.800 ### s/d ### 10 9 0 0 0 m2
c.2.4 Install formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.5 ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 6 3 0 0


c.3.1 Dishutter formwork beam and slab FF PoP ToC +5.250 ### s/d ### 10 2 0 0 0 m2
c.3.2 Dishutter formwork beam and slab Roof PoP ToC +10.800 ### s/d ### 10 4 3 0 0 m2
c.3.3 ### s/d ### 0 0 0 0 0 m2
c.3.4 ### s/d ### 0 0 0 0 0 m2
c.3.5 ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 5 0 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 5 0 0 0 kg
d.1.2 Install rebar footing and pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 ### s/d ### 0 0 0 0 0 kg
d.1.4 ### s/d ### 0 0 0 0 0 kg
d.1.5 ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 1 5 0 0


d.2.1 Install rebar tie beam GF PoP ToC -0.050 ### s/d ### 10 0 0 0 0 kg
d.2.2 Install rebar beam Roof PoP ToC +10.800 ### s/d ### 10 1 5 0 0 kg sims
d.2.3 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab corridor on zone 1 ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 20 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 10 0 6 0 0 m2 wala group
e.2 Install brick for window and corridor area ballroom ### s/d ### 9 0 8 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 0 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 2 4 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 10 2 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 9 0 4 0 0 m2 sirius
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering wall for post control type 1 unit 1 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 18 8 0 0 ls
k.1 Storing ### s/d ### 10 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 3 5 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 0 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 10 0 2 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 0 0 0 0 0 ls
k.10 Equipment assistant ### s/d ### 10 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 0 0 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Repair and made a new pallet ### s/d ### 0 0 0 0 0 m2
k.19 Install rebar and formwork for column pratice and lintel beam ### s/d ### 0 0 0 0 0 m2
k.20 Install mockarabieh in Ballroom ### s/d ### 3 4 0 0 0 pcs valasindo
k.21 Install metal structure for foor balrrom ### s/d ### 10 0 0 0 0 kg
k.22 Finishing and expose column and beam ### s/d ### 10 3 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
55 44
ENG 7 HC / GA 7
25 - 36° C 10 0 99 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Monday
Date : 16-Nov-20
Hari
Daily Report Weeks : 101

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 6 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 7 0 3 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 7 0 3 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 8 0 0


b.1.1 Casting concrete for footing and column PoP ### s/d ### 28 2 8 0 0 m3 casting concrete with indonesian only (10 person)
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 0 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 12 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 11 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 11 0 0 m2 sims (5 person finish at 22.00)
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 12 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 12 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 12 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 6 0 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 10 6 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 10 0 4 0 0 kg sims

D.2 REBAR FOR BEAM 1 9 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 10 1 5 0 0 kg sims
d.2.2 Install rebar for tie beam GF PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.2.3 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 0 4 0 0 kg sims

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 43 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 24 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 12 0 10 0 0 m2 wala group
e.5 Shifting brique ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 8 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 3 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 12 4 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 9 0 5 0 0 m2 sirius
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering a wall paraphet of a roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 31 17 0 0 ls
k.1 Storing ### s/d ### 39 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 0 5 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Repair and installing doors in SVB and HoS ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure for roof of ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 113
ENG 7 HC / GA 7
23 - 37° C 10 0 189 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Tuesday
Date : 17-Nov-20
Hari
Daily Report Weeks : 101

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 4 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 4 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 8 0 0


b.1.1 Casting concrete for pedestal, ring beam and slab roof PoP T ### s/d ### 6 2 8 0 0 m3 start working for cleaning and shifting materiel
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 0 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 12 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 11 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 11 0 0 m2 sims (5 person finish at 22.00)
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 12 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 12 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 11 1 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 5 1 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 10 6 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 0 0 0 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 1 14 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 12 1 6 0 0 kg sims
d.2.2 Install rebar for tie beam GF PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.2.3 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 0 8 0 0 kg sims

D.3 REBAR FOR SLAB 0 6 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 12 0 6 0 0 kg sims
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 4 38 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 5 0 0 m2 sirius
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 24 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 12 0 0 0 0 m2 wala group
e.5 Install brick for expose stair PoP ### s/d ### 12 4 0 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 0 17 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 4 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 0 0 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 9 0 5 0 0 m2 sirius
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
f.5 Plastering a wall paraphet of a roof ballroom ToC +9.600 ### s/d ### 12 0 8 0 0 m2 wala group

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 32 20 0 0 ls
k.1 Storing ### s/d ### 18 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 6 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 1 7 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Repair and installing doors in SVB and HoS ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 124
ENG 7 HC / GA 7
23 - 36° C 10 0 200 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Wednesday
Date : 18-Nov-20
Hari
Daily Report Weeks : 101

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 4 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 4 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 0 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 12 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 11 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 11 0 0 m2 sims (5 person finish at 22.00)
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 12 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 12 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 10 2 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 4 2 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 10 6 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 0 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 1 6 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 12 1 6 0 0 kg sims
d.2.2 Install rebar for tie beam GF PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.2.3 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 0 0 0 0 0 kg sims

D.3 REBAR FOR SLAB 0 14 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 14 0 14 0 0 kg sims (6 person continued until 21.00)
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 4 44 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 5 0 0 m2 sirius
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 20 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 12 4 0 0 0 m2
e.6 Install brick outside basement ballroom ### s/d ### 12 0 10 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 0 9 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 4 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 0 0 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 9 0 5 0 0 m2 sirius
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
f.5 Plastering a wall paraphet of a roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 35 27 0 0 ls
k.1 Storing ### s/d ### 12 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 2 7 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 2 8 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Repair and installing doors in SVB and HoS ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 122
ENG 7 HC / GA 7
23 - 36° C 10 0 198 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Thursday
Date : 19-Nov-20
Hari
Daily Report Weeks : 101

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 4 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 4 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 2 8 0 0


b.3.1 Casting concrete for slab on ground PoP, LC tie beam PoP ### s/d ### 7 2 8 0 0 m3 start working for cleaning, install retaining wall
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 12 0 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 3 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 11 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 11 0 0 m2 sims (5 person finish at 22.00)
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 10 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 10 2 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 4 2 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 10 6 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 0 0 0 kg
d.1.4 Install rebar for pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 1 6 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 12 1 6 0 0 kg sims
d.2.2 Install rebar for tie beam GF PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.2.3 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 0 0 0 0 0 kg sims

D.3 REBAR FOR SLAB 0 8 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 11 0 8 0 0 kg sims
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 4 40 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 5 0 0 m2 sirius
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 23 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 9 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 12 4 0 0 0 m2
e.6 Install brick roof PoP ToC +10.800 ### s/d ### 12 0 3 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 0 17 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 4 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 0 0 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 9 0 5 0 0 m2 sirius
f.4 Plastering for wall outside basement ballroom ### s/d ### 12 0 8 0 0 m2 wala group
f.5 ### s/d ### 0 0 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 34 19 0 0 ls
k.1 Storing ### s/d ### 17 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 3 7 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Fabrication and install window alumunium ### s/d ### 9 0 2 0 0 m2 aigle royal
k.19 Repair and installing doors in SVB and HoS ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 120
ENG 7 HC / GA 7
23 - 36° C 10 0 196 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Friday
Date : 20-Nov-20
Hari
Daily Report Weeks : 101

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 3 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 3 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 9 0 0


b.1.1 Casting concrete for column GF and pedestal PoP and retainin ### s/d ### 0 2 9 0 0 m3 shift 2 start working from 15.00 for cleaning and
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 3 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 7 0 3 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 8 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 8 0 0 m2 sims (5 person finish at 22.00)
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 12 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 12 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 4 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 12 4 2 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 0 0 0 0 0 kg
d.1.4 Erection and install rebar column GF PoP ### s/d ### 10 0 4 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 7 6 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 12 1 6 0 0 kg sims
d.2.2 Install rebar for tie beam GF PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.2.3 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 12 6 0 0 0 kg

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 4 40 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 5 0 0 m2 sirius
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 24 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 12 4 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 12 0 5 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 0 11 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 0 0 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 9 0 5 0 0 m2 sirius
f.4 Plastering for wall outside basement ballroom ### s/d ### 12 0 6 0 0 m2 wala group
f.5 ### s/d ### 0 0 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 33 22 0 0 ls
k.1 Storing ### s/d ### -7 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 2 7 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 9 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 113
ENG 7 HC / GA 7
23 - 36° C 10 0 189 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Saturday
Date : 21-Nov-20
Hari
Daily Report Weeks : 101

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 3 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 3 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 9 0 0


b.1.1 Casting concrete for column GF and ring beam and slab PoP ### s/d ### 11 2 9 0 0 m3 shift 2 start working from 15.00 for cleaning and
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 3 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 7 0 3 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 12 8 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 8 0 0 m2 sims (5 person finish at 22.00)
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 13 5 0 0 0 m2 2 person finish at 06.00
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 7 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 5 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 5 2 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 0 0 0 0 0 kg
d.1.4 Erection and install rebar column GF PoP ### s/d ### 10 0 4 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 6 13 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 12 1 6 0 0 kg sims
d.2.2 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 5 0 0 0 kg
d.2.3 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 0 7 0 0 kg sims

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab ground floor PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 4 40 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 5 0 0 m2 sirius
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 24 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 12 4 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 12 0 5 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 0 11 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 0 0 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 9 0 5 0 0 m2 sirius
f.4 Plastering for wall outside basement ballroom ### s/d ### 12 0 6 0 0 m2 wala group
f.5 ### s/d ### 0 0 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 34 22 0 0 ls
k.1 Storing ### s/d ### -7 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 3 7 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 9 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 120
ENG 7 HC / GA 7
23 - 36° C 10 0 196 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Sunday
Date : 22-Nov-20
Hari
Daily Report Weeks : 101

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 3 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 3 0 0 m3
a.3 Backfilling area beam PoP ### s/d ### 0 0 0 0 0 m3
a.4 Levelling land for lc tie beam HoS ### s/d ### 0 0 0 0 0

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 3 4 0 0


c.1.1 Workshop ### s/d ### 0 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 0 0 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 10 0 4 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP ### s/d ### 0 0 0 0 0 m2
c.1.5 ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 0 0 0 0


c.2.1 Dishutter formwork beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Install formwork for beam and slab FF PoP ToC +5.250 ### s/d ### 0 0 0 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ToC 10.800 ### s/d ### 0 0 0 0 0 m2
c.2.4 Install formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.5 ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 4 0 0


c.3.1 Dishutter formwork beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 0 0 0 m2
c.3.2 Dishutter formwork beam and slab Roof PoP ToC +10.800 ### s/d ### 10 0 4 0 0 m2
c.3.3 ### s/d ### 0 0 0 0 0 m2
c.3.4 ### s/d ### 0 0 0 0 0 m2
c.3.5 ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 4 0 0 0


d.1.1 Fabrication Rebar ### s/d ### 10 4 0 0 0 kg
d.1.2 Install rebar footing and pedestal column PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 ### s/d ### 0 0 0 0 0 kg
d.1.4 ### s/d ### 0 0 0 0 0 kg
d.1.5 ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 0 16 0 0


d.2.1 Install rebar tie beam GF PoP ToC -0.050 ### s/d ### 10 0 0 0 0 kg
d.2.2 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 0 7 0 0 kg sims
d.2.3 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 10 0 9 0 0 kg sims

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab corridor on zone 1 ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 22 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.2 Install brick for window and corridor area ballroom ### s/d ### 9 0 12 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 0 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install retaining wall (stone wall) in HoS ### s/d ### 10 0 4 0 0 m2
e.6 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 0 0 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 0 0 0 0 0 m2
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Plastering wall for post control type 1 unit 1 ### s/d ### 0 0 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 12 6 0 0 ls
k.1 Storing ### s/d ### 10 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 3 5 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 0 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 10 0 1 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 0 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 0 0 0 0 0 ls
k.10 Equipment assistant ### s/d ### 10 0 0 0 0 ls
k.11 Foreman ### s/d ### 10 0 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 0 0 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Repair and made a new pallet ### s/d ### 0 0 0 0 0 m2
k.19 Install rebar and formwork for column pratice and lintel beam ### s/d ### 0 0 0 0 0 m2
k.20 Install mockarabieh in Ballroom ### s/d ### 3 0 0 0 0 pcs
k.21 Install metal structure for foor balrrom ### s/d ### 10 3 0 0 0 kg valasindo
k.22 Finishing and expose column and beam ### s/d ### 10 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
19 55
ENG 7 HC / GA 7
25 - 36° C 10 0 74 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Monday
Date : 23-Nov-20
Hari
Daily Report Weeks : 102

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 5 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 5 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 9 0 0


b.1.1 Casting concrete for column GF and pedestal PoP and retainin ### s/d ### 3 2 9 0 0 m3 start working for cleaning and shifting materiel
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 4 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 10 0 4 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 8 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 8 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 13 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 6 6 0 0


d.1.1 Fabrication Rebar ### s/d ### 12 6 0 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 12 0 2 0 0 kg
d.1.4 Erection and install rebar column GF PoP ### s/d ### 10 0 4 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 7 8 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg sims
d.2.2 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 12 6 0 0 0 kg sims
d.2.3 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 12 1 8 0 0 kg sims

D.3 REBAR FOR SLAB 0 9 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab first floor PoP ToC +5.250 ### s/d ### 10 0 9 0 0 kg
d.3.3 Install rebar for slab roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg

E. Masonry 4 37 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 5 0 0 m2 sirius
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 20 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 12 4 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 12 0 6 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 0 5 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 0 0 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Plastering for paraphet roof PoP ToC +10.800 ### s/d ### 12 0 5 0 0 m2 wala group
f.5 ### s/d ### 0 0 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 31 20 0 0 ls
k.1 Storing ### s/d ### -7 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 0 5 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 9 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 116
ENG 7 HC / GA 7
23 - 36° C 10 0 192 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Tuesday
Date : 24-Nov-20
Hari
Daily Report Weeks : 102

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 5 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 5 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 9 0 0


b.1.1 Casting concrete for column GF and tie beam PoP ToC -0.050 ### s/d ### 6 2 9 0 0 m3 start working for cleaning and shifting materiel
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 12 4 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 10 0 4 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 5 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 11 8 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 8 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 13 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 6 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 5 5 0 0


d.1.1 Fabrication Rebar ### s/d ### 12 5 1 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 12 0 0 0 0 kg
d.1.4 Erection and install rebar column GF PoP ### s/d ### 10 0 4 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 5 0 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg
d.2.2 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 12 5 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 15 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar beam and slab first floor PoP ToC +5.250 (zone 2 ### s/d ### 10 0 7 0 0 kg sims
d.3.3 Install rebar slab first floor PoP ToC +5.250 (zone 4a) ### s/d ### 15 0 8 0 0 kg sims

E. Masonry 4 47 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 11 0 0 m2 sirius
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 20 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 12 4 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 12 0 10 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 0 4 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 0 0 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 10 0 3 0 0 m2 sirius
f.4 Plastering for paraphet roof PoP ToC +10.800 ### s/d ### 10 0 1 0 0 m2 wala group
f.5 ### s/d ### 0 0 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 36 18 0 0 ls
k.1 Storing ### s/d ### -7 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 6 3 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 9 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 10 3 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
75 120
ENG 7 HC / GA 7
23 - 36° C 10 0 195 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Wednesday
Date : 25-Nov-20
Hari
Daily Report Weeks : 102

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 5 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 5 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 9 0 0


b.1.1 Casting concrete for column GF and tie beam PoP ToC -0.050 ### s/d ### 11 2 9 0 0 m3 start working for cleaning and shifting materiel
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 12 4 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 10 0 4 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 5 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 8 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 15 0 8 0 0 m2
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 13 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 5 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 5 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 6 5 0 0


d.1.1 Fabrication Rebar ### s/d ### 12 6 1 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 12 0 0 0 0 kg
d.1.4 Erection and install rebar column GF PoP ### s/d ### 10 0 4 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 6 0 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg
d.2.2 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 12 6 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 15 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar beam and slab first floor PoP ToC +5.250 (zone 2 ### s/d ### 10 0 7 0 0 kg sims
d.3.3 Install rebar slab first floor PoP ToC +5.250 (zone 4a) ### s/d ### 15 0 8 0 0 kg sims

E. Masonry 0 43 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 10 0 0 m2 sirius
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 16 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 12 0 11 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 7 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 9 0 3 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 12 4 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 10 0 4 0 0 m2 sirius
f.4 Plastering for paraphet roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 m2
f.5 ### s/d ### 0 0 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 33 18 0 0 ls
k.1 Storing ### s/d ### -7 1 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 3 3 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 2 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 9 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 10 3 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 8 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 119
ENG 7 HC / GA 7
23 - 36° C 10 0 195 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Thursday
Date : 26-Nov-20
Hari
Daily Report Weeks : 102

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 5 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 7 0 5 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 2 9 0 0


b.1.1 Casting concrete column GF and beam and slab FF PoP ToC +5 ### s/d ### 7 2 9 0 0 m3 shift 2 start working from 15.00
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 4 0 0


c.1.1 Workshop ### s/d ### 7 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 7 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 7 0 4 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 7 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 13 13 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 9 0 13 0 0 m2 sims
c.2.3 Install formwork for beam and slab Roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 7 13 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 0 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 0 0 0 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 6 7 0 0


d.1.1 Fabrication Rebar ### s/d ### 7 6 1 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 7 0 2 0 0 kg
d.1.4 Erection and install rebar column GF PoP ### s/d ### 7 0 4 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 5 0 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg
d.2.2 Install rebar for tie beam PoP ToC -0.050 ### s/d ### 7 5 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 15 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar beam and slab first floor PoP ToC +5.250 (zone 2 ### s/d ### 7 0 7 0 0 kg sims
d.3.3 Install rebar slab first floor PoP ToC +5.250 (zone 4a) ### s/d ### 12 0 8 0 0 kg sims

E. Masonry 0 29 0 0
e.1 Install brick for GF PoP ### s/d ### 7 0 10 0 0 m2 sirius
e.2 Install brick for window and corridor area ballroom ### s/d ### 7 0 13 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 7 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 0 0 0 0 0 m2
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 11 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 7 0 7 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 7 4 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 7 0 4 0 0 m2 sirius
f.4 Plastering for paraphet roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 m2
f.5 ### s/d ### 0 0 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 33 16 0 0 ls
k.1 Storing ### s/d ### -10 1 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 7 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 7 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 7 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 7 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 13 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 7 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 7 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 9 0 1 0 0 ls
k.11 Foreman ### s/d ### 7 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 3 1 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 7 2 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 7 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 7 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 7 7 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 7 1 0
l.2 Trailler Truck ### s/d ### 0 0 0
l.3 Compactor ### s/d ### 7 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 7 2 0
l.6 Rough Terrain Crane ### s/d ### 7 1 0
l.7 Concrete Vibrator ### s/d ### 7 3 0
l.8 Bar Bending ### s/d ### 7 1 0
l.9 Bar Cutter ### s/d ### 7 1 0
l.10 Flat Bed Truck ### s/d ### 7 1 0
l.11 Circle Cutter ### s/d ### 7 4 0
l.12 Welding Machine ### s/d ### 7 4 0
l.13 Stamper ### s/d ### 7 1 0
l.14 Compressor ### s/d ### 7 1 0
l.15 Tile Cutter ### s/d ### 7 2 0
l.16 Seaming Roofing Machine ### s/d ### 7 2 0
l.17 Hand Bor ### s/d ### 7 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 109
ENG 7 HC / GA 7
23 - 36° C 10 0 185 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,


07.00 - 10.00 Tribute for the body of the former president niger

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Friday
Date : 27-Nov-20
Hari
Daily Report Weeks : 102

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 9 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 5 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 15 0 4 0 0 m3 19.00 - 22.00 moving excavator
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 1 9 0 0


b.1.1 Casting concrete for column GF and beam and slab FF PoP To ### s/d ### 10 1 9 0 0 m3 Shift 2 (15.00 - finish) start working for cleanin
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 12 0 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 12 5 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 11 11 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 12 0 11 0 0 m2 sims
c.2.3 Install formwork for tie beam PoP ToC -0.050 ### s/d ### 10 4 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 7 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 2 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 2 0 0 m2 sims
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 6 7 0 0


d.1.1 Fabrication Rebar ### s/d ### 12 6 0 0 0 kg
d.1.2 Install rebar footing and pedestal PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 12 0 2 0 0 kg
d.1.4 Prefabrication rebar for column FF PoP ### s/d ### 10 0 5 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 6 0 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg
d.2.2 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 12 6 0 0 0 kg
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 15 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar beam and slab first floor PoP ToC +5.250 (zone 2 ### s/d ### 10 0 7 0 0 kg sims
d.3.3 Install rebar slab first floor PoP ToC +5.250 (zone 4a) ### s/d ### 15 0 8 0 0 kg sims

E. Masonry 0 40 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 10 0 0 m2 sirius
e.2 Install brick for window and corridor area ballroom ### s/d ### 11 0 13 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 12 0 11 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 10 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 9 0 7 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 12 4 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 10 0 3 0 0 m2 sirius
f.4 Plastering for paraphet roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 m2
f.5 ### s/d ### 0 0 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 36 18 0 0 ls
k.1 Storing ### s/d ### -7 1 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 6 3 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 2 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 9 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 7 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 121
ENG 7 HC / GA 7
22 - 38° C 10 0 197 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Saturday
Date : 28-Nov-20
Hari
Daily Report Weeks : 102

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 9 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 5 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 10 0 4 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 2 9 0 0


b.2.1 Casting concrete for beam and slab GF PoP ToC -0.050 ### s/d ### 6 2 9 0 0 m3 Shift 2 (15.00 - finish) start working for cleanin
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 0 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 10 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 12 11 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 12 0 11 0 0 m2 sims
c.2.3 Install formwork for tie beam PoP ToC -0.050 ### s/d ### 10 4 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 2 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 2 0 0 m2 sims
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 11 8 0 0


d.1.1 Fabrication Rebar ### s/d ### 12 6 1 0 0 kg
d.1.2 Prefab and erection rebar column FF PoP ### s/d ### 15 5 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Prefabrication rebar for column FF PoP ### s/d ### 10 0 5 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 1 8 0 0


d.2.1 Install rebar for ring beam and slab PoP ToC +10.800 ### s/d ### 0 0 0 0 0 kg
d.2.2 Install rebar for beam GF, retaining wall and footing PoP ### s/d ### 12 1 8 0 0 kg sims
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 4 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 11 0 4 0 0 kg sims
d.3.2 Install rebar beam and slab first floor PoP ToC +5.250 (zone 2 ### s/d ### 10 0 0 0 0 kg
d.3.3 Install rebar slab first floor PoP ToC +5.250 (zone 4a) ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 40 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 10 0 0 m2 sirius
e.2 Install brick for window and corridor area ballroom ### s/d ### 9 0 13 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 6 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 10 0 11 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 8 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 9 0 4 0 0 m2 sirius
f.2 Install head of plaster on ballroom ### s/d ### 12 4 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 10 0 4 0 0 m2 sirius
f.4 Plastering for paraphet roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 m2
f.5 ### s/d ### 0 0 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 33 16 0 0 ls
k.1 Storing ### s/d ### -7 1 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 3 1 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 2 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 9 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 7 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 115
ENG 7 HC / GA 7
22 - 38° C 10 0 191 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Sunday
Date : 29-Nov-20
Hari
Daily Report Weeks : 101

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 1 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 1 0 0 m3
a.3 Backfilling area beam PoP ### s/d ### 0 0 0 0 0 m3
a.4 Levelling land for lc tie beam HoS ### s/d ### 0 0 0 0 0

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 10 0 0 0


c.1.1 Workshop ### s/d ### 10 2 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 2 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP ### s/d ### 10 6 0 0 0 m2
c.1.5 ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 4 8 0 0


c.2.1 Dishutter formwork beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Install formwork for beam and slab FF PoP ToC +5.250 (zone 4 ### s/d ### 10 0 3 0 0 m2 sims
c.2.3 Install formwork for beam and slab Roof PoP ToC 10.800 ### s/d ### 0 0 0 0 0 m2
c.2.4 Install formwork for beam PoP ToC -0.050 ### s/d ### 10 4 0 0 0 m2
c.2.5 Dishutter scaffolding and formwork beam and slab FF and Roo ### s/d ### 10 0 5 0 0 m2

C.3 FORMWORK FOR SLAB 0 0 0 0


c.3.1 Dishutter formwork beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 0 0 0 m2
c.3.2 Dishutter formwork beam and slab Roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 m2
c.3.3 ### s/d ### 0 0 0 0 0 m2
c.3.4 ### s/d ### 0 0 0 0 0 m2
c.3.5 ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 3 3 0 0


d.1.1 Fabrication Rebar ### s/d ### 0 0 0 0 0 kg
d.1.2 Install rebar footing and pedestal column PoP ### s/d ### 10 3 0 0 0 kg
d.1.3 Erection rebar column FF PoP ### s/d ### 4 0 3 0 0 kg sims
d.1.4 ### s/d ### 0 0 0 0 0 kg
d.1.5 ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 0 0 0 0


d.2.1 Install rebar tie beam GF PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.2.2 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 0 0 0 0 0 kg
d.2.3 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 0 0 0


d.3.1 Install rebar for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 kg
d.3.2 Install rebar slab corridor on zone 1 ToC -0.050 ### s/d ### 0 0 0 0 0 kg
d.3.3 Install rebar slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 19 0 0
e.1 Install brick for window and corridor area ballroom ### s/d ### 0 0 0 0 0 m2
e.2 Install brick for HoS and ballroom ### s/d ### 9 0 12 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 0 0 3 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install retaining wall (stone wall) in HoS ### s/d ### 10 0 4 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 0 0 0 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 6 0 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 10 4 0 0 0 m2
f.3 Plastering wall of HoS and ballroom ### s/d ### 0 0 0 0 0 m2
f.4 Install head of screed roof HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m'
f.5 Grouting and finishing wall of mockarabieh ### s/d ### 10 2 0 0 0 m'

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 6 7 0 0 ls
k.1 Storing ### s/d ### 10 1 0 0 0 ls
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 0 3 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 0 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 10 0 1 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 0 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 0 0 0 0 0 ls
k.10 Equipment assistant ### s/d ### 10 0 0 0 0 ls
k.11 Foreman ### s/d ### 10 0 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 0 0 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 3 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 0 0 0 0 0 m2
k.19 Install rebar and formwork for column pratice and lintel beam ### s/d ### 0 0 0 0 0 m2
k.20 Install mockarabieh in Ballroom ### s/d ### 0 0 0 0 0 pcs
k.21 Install metal structure for foor balrrom ### s/d ### 0 0 0 0 0 kg
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 10 1 0
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
29 38
ENG 7 HC / GA 7
25 - 36° C 10 0 67 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Monday
Date : 30-Nov-20
Hari
Daily Report Weeks : 103

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 9 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 5 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 10 0 4 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 2 9 0 0


b.2.1 Casting concrete for beam and slab GF PoP ToC -0.050 ### s/d ### 3 2 9 0 0 m3 start working for cleaning and shifting material
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 12 0 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 3 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 10 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 10 11 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 12 0 11 0 0 m2 sims
c.2.3 Install formwork for tie beam PoP ToC -0.050 ### s/d ### 10 4 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 6 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 2 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 2 0 0 m2 sims
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 6 7 0 0


d.1.1 Fabrication Rebar ### s/d ### 12 6 1 0 0 kg
d.1.2 Prefab and erection rebar column FF PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Install rebar for footing and pedestal column PoP ### s/d ### 10 0 4 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 7 8 0 0


d.2.1 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 12 6 0 0 0 kg
d.2.2 Install rebar for beam ans slab GF PoP ### s/d ### 12 1 8 0 0 kg sims
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 4 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 11 0 4 0 0 kg sims
d.3.2 Install rebar beam and slab first floor PoP ToC +5.250 (zone 2 ### s/d ### 10 0 0 0 0 kg
d.3.3 Install rebar slab first floor PoP ToC +5.250 (zone 4a) ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 23 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 6 0 0 m2 sirius
e.2 Install brick for HoS and ballroom ### s/d ### 9 0 4 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 3 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 10 0 10 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 6 6 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 12 4 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 10 0 6 0 0 m2 sirius
f.4 Plastering for paraphet roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 m2
f.5 Grouting and finishing wall of mockarabieh ### s/d ### 12 2 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 33 16 0 0 ls
k.1 Storing ### s/d ### -7 1 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 4 1 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 9 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 7 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 95
ENG 7 HC / GA 7
22 - 38° C 10 0 171 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Tuesday
Date : 1-Dec-20
Hari
Daily Report Weeks : 103

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 3 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 3 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 2 9 0 0


b.2.1 Casting concrete for beam and footing PoP, LC ballroom ToC ### s/d ### 12 2 9 0 0 m3 start working for cleaning and shifting material
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 13 2 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Instal formwork column FF PoP ### s/d ### 10 0 2 0 0 m2 sims
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 10 6 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 10 10 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 12 0 10 0 0 m2 sims
c.2.3 Install formwork for tie beam PoP ToC -0.050 ### s/d ### 10 5 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 5 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 7 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 10 0 7 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 6 7 0 0


d.1.1 Fabrication Rebar ### s/d ### 12 6 1 0 0 kg
d.1.2 Prefab and erection rebar column FF PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 10 0 2 0 0 kg
d.1.4 Install rebar for footing and pedestal column PoP ### s/d ### 10 0 4 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 7 8 0 0


d.2.1 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 12 6 0 0 0 kg
d.2.2 Install rebar for beam ans slab GF PoP ### s/d ### 12 1 8 0 0 kg sims
d.2.3 ### s/d ### 0 0 0 0 0 kg

D.3 REBAR FOR SLAB 0 4 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 11 0 4 0 0 kg sims
d.3.2 Install rebar beam and slab first floor PoP ToC +5.250 (zone 2 ### s/d ### 10 0 0 0 0 kg
d.3.3 Install rebar slab first floor PoP ToC +5.250 (zone 4a) ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 31 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 8 0 0 m2 sirius
e.2 Install brick for HoS and ballroom ### s/d ### 9 0 9 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 3 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 10 0 11 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 5 4 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 12 3 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 10 0 4 0 0 m2 sirius
f.4 Plastering for paraphet roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 m2
f.5 Grouting and finishing wall of mockarabieh ### s/d ### 12 2 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 33 21 0 0 ls
k.1 Storing ### s/d ### 15 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 5 0 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 0 6 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 9 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 5 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 106
ENG 7 HC / GA 7
22 - 38° C 10 0 182 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Wednesday
Date : 2-Dec-20
Hari
Daily Report Weeks : 103

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 5 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 5 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 2 9 0 0


b.2.1 casting concrete for beam and slab GF PoP Toc -0.050 ### s/d ### 4 2 9 0 0 m3 start working for cleaning and shifting material
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 10 0 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 10 3 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 0 0 0 0 0 m2

C.2 FORMWORK FOR BEAM 14 11 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 12 0 11 0 0 m2 sims
c.2.3 Install formwork for tie beam PoP ToC -0.050 ### s/d ### 10 6 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 14 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 12 0 14 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 5 3 0 0


d.1.1 Fabrication Rebar ### s/d ### 12 5 1 0 0 kg
d.1.2 Prefab and erection rebar column FF PoP ### s/d ### 0 0 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 0 0 0 0 0 kg
d.1.4 Install rebar for footing and pedestal column PoP ### s/d ### 10 0 2 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 6 8 0 0


d.2.1 Install rebar for beam FF PoP ToC +5.250 ### s/d ### 12 6 0 0 0 kg
d.2.2 Install rebar for beam first floor PoP ToC +5.250 (zone 4a) ### s/d ### 10 0 3 0 0 kg sims
d.2.3 Install rebar for beam FF PoP ToC +5.250 (zone 4a) ### s/d ### 10 0 5 0 0 kg sims

D.3 REBAR FOR SLAB 1 12 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 11 0 4 0 0 kg sims
d.3.2 Install rebar for slab first floor PoP ToC +5.250 (zone 2 & 4b) ### s/d ### 12 1 8 0 0 kg sims
d.3.3 Install rebar slab first floor PoP ToC +5.250 (zone 4a) ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 32 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 9 0 0 m2 sirius
e.2 Install brick for HoS and ballroom ### s/d ### 9 0 9 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 3 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 10 0 11 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 4 5 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 12 3 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 10 0 5 0 0 m2 sirius
f.4 Plastering for paraphet roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 m2
f.5 Grouting and finishing wall of mockarabieh ### s/d ### 10 1 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 34 15 0 0 ls
k.1 Storing ### s/d ### 15 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 6 0 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 0 0 0 0 0 ls
k.18 Install a frame celling in SVB ### s/d ### 9 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 5 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 114
ENG 7 HC / GA 7
22 - 38° C 10 0 190 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.
Day : Thursday
Date : 3-Dec-20
Hari
Daily Report Weeks : 103

Tanggal

RÉHABILITATION DU PALAIS PRÉSIDENTIEL DU RÉPUBLIQUE DU NIGER


Minggu Ke
Work Durations number of workers Volume
NO Job Description Working Hours Unit Material / Information Material
(Hours) Ind WorkersLocal Workers Tools Ind Workers
Local Workers Tools
A. EARTHWORK 0 5 0 0
a.1 Shifting and backfilling on corridor zone 1 ### s/d ### 0 0 0 0 0 m3
a.2 Manual excavation for footing corridor PoP ### s/d ### 10 0 5 0 0 m3
a.3 Backfilling area tie beam and slab on ground PoP ### s/d ### 0 0 0 0 0 m3
a.4 Excavation for footing PoP ### s/d ### 0 0 0 0 0 m3

B.1 CONCRETE FOR COLUMN 0 0 0 0


b.1.1 ### s/d ### 0 0 0 0 0 m3
b.1.2 ### s/d ### 0 0 0 0 0
b.1.3 ### s/d ### 0 0 0 0 0

B.2 CONCRETE FOR BEAM 0 0 0 0


b.2.1 ### s/d ### 0 0 0 0 0 m3
b.2.2 ### s/d ### 0 0 0 0 0
b.2.3 ### s/d ### 0 0 0 0 0

B.3 CONCRETE FOR SLAB/FLOOR PLATE 0 0 0 0


b.3.1 ### s/d ### 0 0 0 0 0 m3
b.3.2 ### s/d ### 0 0 0 0 0
b.3.3 ### s/d ### 0 0 0 0 0

C.1 FORMWORK FOR COLUMN 10 3 0 0


c.1.1 Workshop ### s/d ### 10 3 0 0 0 m2
c.1.2 Fabrication on site ### s/d ### 10 4 0 0 0 m2
c.1.3 Install and dihutter formwork for column GF PoP ### s/d ### 0 0 0 0 0 m2
c.1.4 Install and dishutter formwork column GF and FF PoP, pedest ### s/d ### 10 3 0 0 0 m2
c.1.5 Install formwork for pedestal column PoP ### s/d ### 13 0 3 0 0 m2 sims

C.2 FORMWORK FOR BEAM 14 10 0 0


c.2.1 Install and dishutter formwork for beam PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.2.2 Instal formwork beam and slab PoP ToC +5.250 (zone 4A) ### s/d ### 13 0 10 0 0 m2 sims
c.2.3 Install formwork for tie beam PoP ToC -0.050 ### s/d ### 10 6 0 0 0 m2
c.2.4 Instal formwork beam and slab PoP ToC +5.250 ### s/d ### 10 8 0 0 0 m2
c.2.5 Dishutter formwork beam and slab corridor on zone 1 ToC -0. ### s/d ### 0 0 0 0 0 m2

C.3 FORMWORK FOR SLAB 0 14 0 0


c.3.1 Install formwork slab on ground PoP ToC -0.050 ### s/d ### 0 0 0 0 0 m2
c.3.2 Joint and setting formwork for doom HoS ToC +6.350 ### s/d ### 0 0 0 0 0 m2
c.3.3 Dishutter formwork ring beam and slab FF PoP ToC +5.250 ### s/d ### 12 0 14 0 0 m2
c.3.4 Dishutter formwork ring beam and slab post control type 1 on ### s/d ### 0 0 0 0 0 m2
c.3.5 Install formwork for beam and slab HoS ToC -0.050 (garden a ### s/d ### 0 0 0 0 0 m2

D.1 REBAR FOR COLUMN 9 3 0 0


d.1.1 Fabrication Rebar ### s/d ### 12 6 1 0 0 kg
d.1.2 Prefab and erection rebar column GF and FF PoP ### s/d ### 10 3 0 0 0 kg
d.1.3 Prefabrication rebar for column and lintel beam ### s/d ### 0 0 0 0 0 kg
d.1.4 Install rebar for footing and pedestal column PoP ### s/d ### 10 0 2 0 0 kg sims
d.1.5 Install rebar for column GF PoP (prefab) ### s/d ### 0 0 0 0 0 kg

D.2 REBAR FOR BEAM 3 7 0 0


d.2.1 Install rebar for tie beam PoP ToC -2.200 ### s/d ### 10 3 0 0 0 kg
d.2.2 Install rebar for beam ans slab GF PoP ### s/d ### 0 0 0 0 0 kg
d.2.3 Install rebar for beam FF PoP ToC +5.250 (zone 4a) ### s/d ### 10 0 7 0 0 kg sims

D.3 REBAR FOR SLAB 1 10 0 0


d.3.1 Install rebar for slab on ground PoP ### s/d ### 11 0 4 0 0 kg sims
d.3.2 Install rebar beam and slab first floor PoP ToC +5.250 (zone 2 ### s/d ### 11 1 6 0 0 kg sims
d.3.3 Install rebar slab first floor PoP ToC +5.250 (zone 4a) ### s/d ### 0 0 0 0 0 kg

E. Masonry 0 32 0 0
e.1 Install brick for GF PoP ### s/d ### 9 0 9 0 0 m2 sirius
e.2 Install brick for HoS and ballroom ### s/d ### 9 0 9 0 0 m2 sirius
e.3 Fabrication brique ### s/d ### 9 0 3 0 0 pcs sirius
e.4 Install brick for paraphet roof ballroom ToC +9.600 ### s/d ### 0 0 0 0 0 m2
e.5 Install brick for expose stair PoP ### s/d ### 0 0 0 0 0 m2
e.6 Install brick for GF PoP ### s/d ### 10 0 11 0 0 m2 wala group
e.7 Install brick for paraphet roof post control type 2 unit 1 ### s/d ### 0 0 0 0 0 m'

F. Plastering 5 5 0 0
f.1 Finishing wall with stuccofiller on HoS ### s/d ### 0 0 0 0 0 m2
f.2 Install head of plaster on ballroom ### s/d ### 12 3 0 0 0 m'
f.3 Plastering wall of ballroom ### s/d ### 10 0 5 0 0 m2 sirius
f.4 Plastering for paraphet roof PoP ToC +10.800 ### s/d ### 0 0 0 0 0 m2
f.5 Grouting and finishing wall of mockarabieh ### s/d ### 10 2 0 0 0 m2

G. Baja 0 0 0 0
g.1 ### s/d ### 0 0 0 0 0 kg
g.2 ### s/d ### 0 0 0 0 0 kg
g.3 ### s/d ### 0 0 0 0 0 kg
g.4 ### s/d ### 0 0 0 0 0 kg
g.5 ### s/d ### 0 0 0 0 0 kg

H. Anti-Thermite 0 0 0 0
h.1 ### s/d ### 0 0 0 0 0 m2
h.2 ### s/d ### 0 0 0 0 0
h.3 ### s/d ### 0 0 0 0 0
h.4 ### s/d ### 0 0 0 0 0
h.5 ### s/d ### 0 0 0 0 0

I. Waterproofing Sub Structure 0 0 0 0


i.1 ### s/d ### 0 0 0 0 0 m2
i.2 ### s/d ### 0 0 0 0 0
i.3 ### s/d ### 0 0 0 0 0
i.4 ### s/d ### 0 0 0 0 0
i.5 ### s/d ### 0 0 0 0 0

J. Waterproofing Wet Area 0 0 0 0


j.1 ### s/d ### 0 0 0 0 0
j.2 ### s/d ### 0 0 0 0 0
j.3 ### s/d ### 0 0 0 0 0
j.4 ### s/d ### 0 0 0 0 0
j.5 ### s/d ### 0 0 0 0 0

K Lain-Lain 34 24 0 0 ls
k.1 Storing ### s/d ### -7 2 0 0 0 ls 2 shift
k.2 MEP Crew ### s/d ### 10 1 0 0 0 ls
k.3 SHE Crew ### s/d ### 10 4 4 0 0 ls
k.4 Surveyor Crew ### s/d ### 10 2 0 0 0 ls
k.5 Scaffolder ### s/d ### 10 1 0 0 0 ls
k.6 Canteen Crew and office boy ### s/d ### 10 2 0 0 0 ls
k.7 Driver and Operator ### s/d ### 12 3 5 0 0 ls
k.8 Warehouse assistant ### s/d ### 10 1 0 0 0 ls
k.9 Laboratory quality control assistant ### s/d ### 10 1 0 0 0 ls
k.10 Equipment assistant ### s/d ### 12 0 1 0 0 ls
k.11 Foreman ### s/d ### 10 1 0 0 0 ls
k.12 Leave or sick ### s/d ### 8 4 0 0 0 ls
k.13 Shifting materiel for metal structure ### s/d ### 0 0 0 0 0 ls
k.14 Fabrication door and windows SVB ### s/d ### 0 0 0 0 0 set
k.15 levelling land for LC tie beam corridor PoP ### s/d ### 0 0 0 0 0 m2
k.16 Fabrication of concrete deck ### s/d ### 10 1 0 0 0 ls
k.17 Cleaning and shifting materiel ### s/d ### 10 2 9 0 0 ls 3 person over time until 21.00 for intall formwo
k.18 Install a frame celling in SVB ### s/d ### 9 0 5 0 0 m2 aigle royal
k.19 Install mockarabieh in Ballroom ### s/d ### 10 4 0 0 0 m2 Valasindo
k.20 Removing doors and windows from safe house ### s/d ### 0 0 0 0 0 m3
k.21 Install metal structure and metal roof in the ballroom ### s/d ### 10 5 0 0 0 kg Valasindo
k.22 Finishing and expose column and beam ### s/d ### 0 0 0 0 0 ls
25
L Alat
l.1 Excavator ### s/d ### 10 1 0
l.2 Trailler Truck ### s/d ### 9 0 0
l.3 Compactor ### s/d ### 10 1 0
l.4 Bob Cat ### s/d ### 0 0 0 bobcat off
l.5 Fiori ### s/d ### 10 2 0
l.6 Rough Terrain Crane ### s/d ### 10 1 0
l.7 Concrete Vibrator ### s/d ### 10 3 0
l.8 Bar Bending ### s/d ### 10 1 0
l.9 Bar Cutter ### s/d ### 10 1 0
l.10 Flat Bed Truck ### s/d ### 10 1 0
l.11 Circle Cutter ### s/d ### 10 4 0
l.12 Welding Machine ### s/d ### 10 4 0
l.13 Stamper ### s/d ### 10 1 0
l.14 Compressor ### s/d ### 10 1 0
l.15 Tile Cutter ### s/d ### 10 2 0
l.16 Seaming Roofing Machine ### s/d ### 10 2 0
l.17 Hand Bor ### s/d ### 10 6 0

Indonesia Local
n
Workers Workers ###
Temperature (Celcius) Amount of Working Hours Overtime (hours) Management Staff TOTAL
76 113
ENG 7 HC / GA 7
22 - 38° C 10 0 189 SPV 9 SHE 4
SURVEYOR 4 KOM 6

Notes : Maitre Douvrage Entrepreneur Dibuat Oleh,

Chef de Department Technique Chef de De Department D'ingenierie


NIAMEY NYALA PT. WIJAYA KARYA (Persero) Tbk.

You might also like