You are on page 1of 13

MATERIAL APPROVAL SUBMISSION

JAZZ CITY KULIM

REFERENCE NO : ELDSB/KJC/2021/ SCOPE OF WORKS


ISSUE DATE : 17-Nov-22
TO : PERUNDING GD Architectural Mechanical & Electrical
ATTENTION :
Civil & Structural Landscape

Others ….....................

MANUFACTURER : EBARA PUMPS MALAYSIA SDN BHD PRODUCT NAME : CENTRIFUGAL PUMP

SUPPLIER : MODEL / :
SERIAL NO.

CONTACT NO : SPEC / DRWG REF :

APPROVAL STATUS :
Authorise the Main Contractor to proceed with procurement, manufacture, fabrication and/or construction no. resubmittal is required.

Authorise the Main Contractor to proceed with procurement, manufacture, fabrication and/or construction, provided that the work
is performed in accordance with the comments. Re-submittal of required samples/documents within two weeks in accordance with
the comments in the document.

Indicates the Main Contractor shall NOT proceed with procurement, manufacture, fabrication and/or construction. A full submittal is
required in accordance with the comments.

NOTES :
1. Direction provided to the Main Contractor to proceed with procurement, manufacture, fabrication and/or construction does not relieve the
Main Contractor of his responsibilities under the Conditions of the Contract.
2. The approval of this submittal does not constitute a variation to the Contract in terms of either time or cost, however if you deem otherwise
kindly raise a Notification Of Potential Change within 7 working days of the approval.
3. This approval shall not relieve the Contractor of any of his contractual and/or statutory obligations

COMMENTS :

REQUESTED BY : ENDORSED BY CONSULTANT :

Signature : ENG LEE DEVELOPMENT SDN BHD Signature : PERUNDING GD


Name : LILY FAREEZA BINTI RAZALI Name :
Date : 17/11/2022 Date :
(Co.Stamp) (Co.Stamp)
CC :
SITE OFFICE PERUNDING GD

TTM KONSURTIUM SDN BHD


ARKITEK TEOH CHARTERED ARCHITECHT

OKS CONSULTING ENGINEER OTHERS