File No. CR-HQ0ELEC(CPSI)/4/2021-O/o DY CEE/CONV/II/HQ/CR (Computer No.

86117 ) 1

Note No. #1

Central Railway CEE(Project.)’s Office,

Wadibunder.

No: CEE/P/WB/MUTP/Phase-IIIA/2019-20/01 Date: 21.04.2021

OFFICE NOTE

Sub: Sanction of Detailed Estimate for Power Supply Augmentation – Traction


Power Supply & General Power Supply in connection with work of MUTP-
Phase-IIIA of Mumbai Division of Central Railway.

Ref: 1) Railway Board’s letter No. 2018/Proj/MUTP-3A/1/1 Vol.II dated


01.04.2019.
2) Railway Board’s letter No. 2018/Proj/MUTP-3A/1/1 Vol.II dated
02.04.2019.
3) MRVC’s letter No. MRVC/EL/MUTP-IIIA/149 dated 24.09.2019
4) PCEE/CR’s letter No. W.828. BXG.4LP.PROGRESS dated 3.10.2019.
5) PFA/CSMT Mumbai’s letter No. AC/DC-AC/MUTP/Phase III dated
16.04.2021
*******
1.0 Railway board vide letter No. 2018/Proj/MUTP-3A/1/1 Vol.II dated 01.04.2019
(# Page No.1 ) has approved Mumbai Urban Transport Project, Phase-III A, which
includes various works including works of “Power Supply Augmentation- Traction
Power Supply & General Power Supply” . Further Railway Board has advised the above
work will be executed by Central Railway vide letter No. 2018/ Proj/MUTP-3A/1/1 Vol.II
dated 02.04.2019 (# Page No.9 ).

2.0 MRVC /Mumbai has given the proportionate estimated cost of Rs.471 Cr. and
completion cost Rs.540.57 Cr for the execution of work of “Power Supply
Augmentation- Traction Power Supply & General Power Supply” by Central Railway
vide letter No. MRVC/EL/MUTP-IIIA/149 dated 24.09.2019 (# Page No.6 ). The brief
detailed of abstract estimate are as mentioned below.

SN. Name of work Proportionate Proportionate


Estimated cost Completion cost

1 Traction sub station- 3 Nos. Rs.135 Cr. Rs.154.93 Cr

2 Section Post – 3 Nos. SP Rs.30 Cr. Rs.34.43 Cr.

3 Power supply arrangement from Rs.54 Cr. Rs.62.00 Cr


receiving to TSS.

4 Traction Power supply up gradation and Rs.252 CR. Rs.289.71 C.


strengthening.

Generated from eOffice by TAUQIR KHAN, SSE-I/CPM/HQ/CR, CENTRAL RAILWAY HEADQUARTERS on 03/05/21 12:37 PM
File No. CR-HQ0ELEC(CPSI)/4/2021-O/o DY CEE/CONV/II/HQ/CR (Computer No. 86117 ) 2

Total Rs.471.00 Cr. Rs.540.57 Cr.

3.0 Further PCEE/CR has advised that above works will be executed by conversion unit,
including preparing of detailed estimate vide letter No. W.828. BXG.4LP.PROGRESS
dated 3.10.2019 ( # Page No. 10). Again vide Note No. CEE/P/WB/MUTP/PHASE-
IIIA /2019-20 dated 24.12.2019 ( #Page No. 7 ) CEDE has confirmed that he work of
Transformers upgradation will be carried out by Conversion unit and “110KV
transmission line work will be carried out by Sr.DEE/TRD/KYN as discussed earlier out
of the “Traction Power supply up gradation and strengthening.

4.0 PCEE/CR has accorded Technical Approval to the complete detailed estimate at
total cost of Rs.547.96 Crore against abstract cost off Rs.471.00 Cr. vide office note No.
CEE/P/WB/MUTP /Phase IIIA/2019-20/01 dated 11.02.2021 (#Page No.29 ) for
carrying out following work against the “Power Supply Augmentation -
Traction Power & General Power Supply” . The Technical Details are as under.

A: TECHNICAL DETAILS OF ESTIMATE .


SN. Name of work Approved

1 Traction sub station- 3 Construction of outdoor type AC TSS at Kanjurmarg and


Nos.
Construction of GIS type AC TSS at Dativali; Total 2 Nos

TSS against 3 Nos. TSS.

2 Section Post – 3 Nos. Construction of new SP at Ghatkopar & Kopar. and


SP
Conversion of Existing SSP into SP at Mulund.

3 Power supply 110KV supply from TATA to proposed Kanjurmarg TSS and
arrangement from
receiving Dativali TSS.

to TSS.

4 Traction Power supply up gradation and strengthening.

i Upgradation of The Detailed Estimate for Traction Power supply up


Transformers in AC gradation has been prepared as per Committee
TSS of NE and SE recommendation and accepted by PCEE/CR vide office
section of Mumbai Note No. CEE/P/WB/MUTP/Phase-IIIA/2019-20/01 dated
Division. 17.11.2020 ( # Page NO. 19 ) . The brief of
recommendation and acceptance are as under.

a. Up gradation of four TSS (CHG, Sion, THA & THK)


transformers capacity with 2 x 40/56 MVA ,
b. 110KV/27 KV.
c. Provision of 3rd Transformer of 40/56 MVA at Thakurli
TSS as feed of this TSS is extending in NE & SE

Generated from eOffice by TAUQIR KHAN, SSE-I/CPM/HQ/CR, CENTRAL RAILWAY HEADQUARTERS on 03/05/21 12:37 PM
File No. CR-HQ0ELEC(CPSI)/4/2021-O/o DY CEE/CONV/II/HQ/CR (Computer No. 86117 ) 3

direction of Kalyan District.


d. Upgradation of 8 TSS existing transformers at TLA,
TMM, KSRA, IGP, KJT, UBG, LNL & MNKD with
2x30MVA , 110KV/27KV.
e. Released transformers from 4 TSS ( CHG, Sion, TNA
& THK) of 30/42 MVA capacity will be utilized for
upgradation of 4 Nos TSS existing transformers at
Kasara, Igatpuri, UBG and Lonaval TSS.
f. Providing of new 8 Nos 30/42 MVA transformers at
TLA, TMM, KJT and MNKD TSS.
g. Released 16 Nos 21.6 MVA, 110KV/27 KV from
TLA, TMM, KSRA, IGP, KJT, UBG, LNL & MNKD
will be utilized in Nagpur & Bhuawal division of
Central Railway.
ii Strengthening of Sr.DEE (TD) KYN has prepared detailed estimate at a total
110KV power supply in cost of Rs.239.66 Crore and same has been vetted by
NE & SE Section. Sr.DFM/BB vide letter /AC/F-I/TD/RE dated 22.3.2021
( # Page- 96)

5.0 Covering of above technical details, a Detailed Estimate prepaid for Electrical, S&T and
Engineering portion of work. It was sent to HQ account for vetting vide letter No.
CEE/P/WB/MUTP/Phase-IIIA/2019-20/01dated 28.01.2021 at a estimated cost of Rs.547.96
Cr. . PFA vide letter No. AC/DC-C/MUTP/Phase-III dated 16.04.2021 ( # Page No. 123) has
vetted the detailed estimate at a cost of Rs.516.05 Cr. The details of the vetted detailed
estimate are as under.

i. Details of vetted Detailed Estimate.

SN. Name of work Abstract Detailed Excess/ Saving Remarks


cost in Estimate
Cr. Cost in
Cr.
Value %
in Cr.
1 Traction sub 165.00 115.77 -49.23 • 29.84 Construction of outdoor
station- 3 Nos. % type AC TSS at
Kanjurmarg (#Page No. 36 )
and Construction of GIS
type AC TSS at
Dativali (#Page No. 46 ) .
Total 2 Nos TSS against 3
Nos. TSS. Cost reduced due
to construction of 2 Nos TSS
in place of 3 Nos. TSS.

2 Section Post – 3 Construction of new SP at


Nos. SP Ghatkopar & Kopar. and
Conversion of Existing SSP

Generated from eOffice by TAUQIR KHAN, SSE-I/CPM/HQ/CR, CENTRAL RAILWAY HEADQUARTERS on 03/05/21 12:37 PM
File No. CR-HQ0ELEC(CPSI)/4/2021-O/o DY CEE/CONV/II/HQ/CR (Computer No. 86117 ) 4

into SP at Mulund (# Page


No.85)

3 Power supply 54.00 69.72 15.72 29.11% 110KV supply from TATA
arrangement to proposed Kanjurmarg
from receiving TSS and Dativali TSS ( #
to TSS. Page No. 90).

4 Traction Power 252 330.56 78.56 31.18% 1) Transformer Upgradation


supply up in TSS at a total cost of
gradation and Rs.95.38 Crore. ( # Page
strengthening. No. 91)

2) 110 KV transmission line


augmentation in NE & SE at
a total cost of Rs.239.66
Crore. (# Page N0. 99)

Gross Total 471.00 516.05 45.05 9.57%


CRRM 0 2.77 2.77 100%
Net Total; 471.00 513.28 42.28 8.98%

ii. PFA/CR, while vetting the detailed has observed the following, the remarks of this
office are as under.

SN Account Observation Executive’s remarks


i It is to be certified /ensured that there is no It is certified /ensured that there is no
overlapping of the work by other overlapping of the work by other department
department like construction/MRVC/Open like construction /MRVC/Open line etc.
line etc.
ii Certifying that quantities are based on It is certified that quantities are based on
approved drawing/survey etc. approved drawing/survey etc.
iii Approval of MRVC being obtained as there Noted. MRVC has been advised vide letter
is 8.98% excess over cost as communicated No. CEE/P/WB/MUTP/Phase-IIIA/2019-
by MRVC. 20/01 dated 16.04.2021 ( # Page No.
125 ) for additional funds. However after
sanction of detailed estimate, it will be got
confirmed from MRVC.
iv Debit of 5.38 Crore for Kharbao TSS being Noted.
accepted only after vetting of associate
finance of CE/C
v This office concurrence for sub estimate Noted.
accorded vide letter No.
AC/FE/Estimate/MUTP/Aug/NE/SE/2020-

Generated from eOffice by TAUQIR KHAN, SSE-I/CPM/HQ/CR, CENTRAL RAILWAY HEADQUARTERS on 03/05/21 12:37 PM
File No. CR-HQ0ELEC(CPSI)/4/2021-O/o DY CEE/CONV/II/HQ/CR (Computer No. 86117 ) 5

21 dated 30.06.2020 for NEI, NE-II, & SE-I


& SE-II up gradation of 110 KV
transmission line is with drawn.
vi This will require sanction of GM in term of Sanction of GM to the detailed estimate at a
Item No. 40 (i) Note (v) of GM’s total Gross cost of Rs.516.05 Crore is being
delegation. obtained vide this office note.

6.0 The vetted estimates along with all Technical details, Narrative Report etc are placed
in e- office.

7.0 As per PFA/CR’s letter No. AC/DC-C/MUTP/Phase-III dated 16.04.2021


(# Page No. 123 ) vide item No. 40 ( i) Note ( V) of GM’s delegation of Power ( # Page
No. 126- 130 ) , the estimate over Rs.500 Cr. Requires GM’s sanction. The cost of detailed
estimate is Rs.516.05 Cr, which is more than Rs.500 Cr. .

8.0 In view of the above, GM/CR is requested to kindly sanction the Detailed Estimate
for the work of “Power Supply Augmentation - Traction Power & General Power Supply
at a Gross total cost of Rs.516,05,14,507/-, ( With CRRM Rs, 2,77,46,250/- and net cost of
Rs.5132768257/-) which is higher by Rs.45,05,14,507/- i.e 9.57% against abstract cost of
Rs.471 Crore.

21/04/2021 1:35 PM
MAYANK SINGH RAJPUT
(DY CEE/CONV/II/HQ/CR)

Note No. #2

Sanction of the detailed estimate for the work of "Power Supply Augmentation -
Traction Power and General Power Supply" may please be accorded.

21/04/2021 2:03 PM
HARI MOHAN SHARMA
(CEDE/HQ/CR)

Note No. #3

GM is requested to kindly sanction the detailed estimate for the work of "Power
Supply Augmentation-Traction Power & General Power Supply" at a gross total
cost of Rs 516,05,14507/-(with CRRM of Rs 2,77,46,250/- and net cost of Rs
513,27,68257/-) which is higher by Rs 45,05,14507/- i.e. 9.57% higher than the
abstract cost of Rs.471 crore. The detailed estimate is vetted by Finance(PFA).

Generated from eOffice by TAUQIR KHAN, SSE-I/CPM/HQ/CR, CENTRAL RAILWAY HEADQUARTERS on 03/05/21 12:37 PM
File No. CR-HQ0ELEC(CPSI)/4/2021-O/o DY CEE/CONV/II/HQ/CR (Computer No. 86117 ) 6

21/04/2021 3:08 PM
ARUN KUMAR TEWARI
(PCEE/HQ/CR)

Note No. #4

The subject detailed estimate is vetted (CP/123-124).

26/04/2021 8:01 PM
RUBY AHLUWALIA
(PFA/HQ/CR)

Note No. #5

28/04/2021 10:15 AM
SAKET KUMAR MISHRA
(SECY/HQ/CR)

Note No. #6

Sanctioned

29/04/2021 1:41 PM
SANJEEV MITTAL
(GM/HQ/CR)

Note No. #7

30/04/2021 11:23 AM
SAKET KUMAR MISHRA
(SECY/HQ/CR)

Note No. #8

Generated from eOffice by TAUQIR KHAN, SSE-I/CPM/HQ/CR, CENTRAL RAILWAY HEADQUARTERS on 03/05/21 12:37 PM
File No. CR-HQ0ELEC(CPSI)/4/2021-O/o DY CEE/CONV/II/HQ/CR (Computer No. 86117 ) 7

30/04/2021 2:31 PM
ARUN KUMAR TEWARI
(PCEE/HQ/CR)

Note No. #9

The DE has been sanctioned by GM/CR. May further process the execution as per
extant provisions

30/04/2021 2:45 PM
VIVEK DIXIT
(CEGE/HQ/CR)

Note No. #10

For further necessary action.

30/04/2021 5:01 PM
MAYANK SINGH RAJPUT
(DY CEE/CONV/II/HQ/CR)

Generated from eOffice by TAUQIR KHAN, SSE-I/CPM/HQ/CR, CENTRAL RAILWAY HEADQUARTERS on 03/05/21 12:37 PM