You are on page 1of 17

Sheet : 1 of 17

Program for Balance work of Civil Tank Foundation

Balance Qty. as Balance Qty. as MATERIAL Program for Balance Work


Sl. No. Balance Work Unit P/A
on 25-05-22 on 31-05-22 AVAILABILITY 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun

MS TANK-39
YES NO
1 BITIMINUS PAINTING Sq.M 200 0 P 200

A
2 SAND FILLING 1ST LAYER Cu.M 450 0 P 450

A
3 SAND FILLING 2ND LAYER Cu.M 415 415 P 207.5 207.5

4 SAND FILLING 3RD LAYER Cu.M 415 415 P 207.5 207.5

5 PVC LINING Sq.M 1500 1500 P 1500

6 SAND FILLING 4TH LAYER Cu.M 415 415 P 207.5 207.5

7 C P SYSTEM Lot 1 1 P 50% 50%

8 SAND FILLING 5TH LAYER Cu.M 415 415 P 207.5 207.5

9 SAND FILLING 6TH LAYER Cu.M 415 415 P 207.5

10 CRUSED STONE LAYING Cu.M 138 138 P

11 TACK COAT PREMIX CARPET Sq.M 1497 1497 P

MS TANK-40

1 SAND FILLING 4TH LAYER Cu.M 415 0 P 415


Sheet : 2 of 17

Program for Balance work of Civil Tank Foundation

Balance Qty. as Balance Qty. as MATERIAL Program for Balance Work


Sl. No. Balance Work Unit P/A
on 25-05-22 on 31-05-22 AVAILABILITY 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun

2 C P SYSTEM Lot 1 50% P 50%

3 SAND FILLING 5TH LAYER Cu.M 415 415 P 103.75 103.75 103.75 103.75

4 SAND FILLING 6TH LAYER Cu.M 415 415 P 103.75 103.75 103.75 103.75

5 CRUSED STONE LAYING Cu.M 138 138 P 69 69

6 TACK COAT PREMIX CARPET Sq.M 1497 1497 P 374.25

ACTUAL AVAILABILITY OF MAN POWER BOTH TANKS

CONTRACTOR /AGENCY NAME NKS


NAME OF THE PERSON ASSIGNED FROM B&R

CONTACT DETAILS

CIVIL ENGINEER SIGNATURE LEAD CIVIL ENGINEER SIGNATURE


Sheet : 3 of 17

Program for Balance work of Civil Tank Foundation

Balance Qty. as Balance Qty. as MATERIAL Program for Balance Work


Sl. No. Balance Work Unit P/A
on 25-05-22 on 31-05-22 AVAILABILITY 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun

ALKYLATE TANK-43

1 REINFORCEMENT (RAFT & WALL) RM 159 0 P 159

2 SHUTTERING & RCC Cu.M 171 85.5 P 85.5

3 BITIMINUS PAINTING Sq.M 175 175 P 87.5 87.5

4 SAND FILLING 1ST LAYER Cu.M 600 600 P 300 300

5 SAND FILLING 2ND LAYER Cu.M 600 600 P 300 300

6 PVC LINER Sq.M 2170 2170 P 2170

7 SAND FILLING 3RD LAYER Cu.M 600 600 P 300 300

8 SAND FILLING 4TH LAYER Cu.M 600 600 P 300 300

9 SAND FILLING 5TH LAYER Cu.M 600 600 P 300 300

10 C P SYSTEM Lot 1 1 P 50% 50%

11 CRUSED STONE Cu.M 81 81 P 40.5

12 PREMIX CARPET Sq.M 2137 2137 P

A
Sheet : 4 of 17

Program for Balance work of Civil Tank Foundation

Balance Qty. as Balance Qty. as MATERIAL Program for Balance Work


Sl. No. Balance Work Unit P/A
on 25-05-22 on 31-05-22 AVAILABILITY 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun

ALKYLATE TANK-44

1 PVC LINER Sq.M 2170 0 P 2170

2 SAND FILLING 3RD LAYER Cu.M 600 0 P 600

3 SAND FILLING 4TH LAYER Cu.M 600 600 P 200 200 200

4 SAND FILLING 5TH LAYER Cu.M 600 600 P 200 200 200

5 C P SYSTEM Lot 1 1 P 50% 50%

6 CRUSED STONE Cu.M 81 81 P 27 27

7 PREMIX CARPET Sq.M 2137 2137 P 427.4 427.4

ACTUAL AVAILABILITY OF MAN POWER BOTH TANKS

CONTRACTOR /AGENCY NAME


BP CONSTRUCTION
NAME OF THE PERSON ASSIGNED FROM B&R

CONTACT DETAILS

CIVIL ENGINEER SIGNATURE LEAD CIVIL ENGINEER SIGNATURE


Sheet : 5 of 17

Program for Balance work of Civil Tank Foundation

Balance Qty. as Balance Qty. as MATERIAL Program for Balance Work


Sl. No. Balance Work Unit P/A
on 25-05-22 on 31-05-22 AVAILABILITY 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun
Sheet : 6 of 17

Program for Balance work of Civil Tank Foundation

Balance Qty. as Balance Qty. as MATERIAL Program for Balance Work


Sl. No. Balance Work Unit P/A
on 25-05-22 on 31-05-22 AVAILABILITY 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun

SULPHAR TANK-54

1 SAND FILLING 4TH LAYER Cu.M 77 0 P 77

2 SAND FILLING 5TH LAYER Cu.M 77 0 P 77

3 SAND FILLING 6TH LAYER Cu.M 77 77 P 25.6 25.6 25.6

4 PCC Cu.M 25 25 P 12.5 12.5

5 FIRE BRICKS Sq.M 260 260 P 130 130

SULPHAR TANK-55

1 SAND FILLING 5TH LAYER Cu.M 77 0 P 77

2 SAND FILLING 6TH LAYER Cu.M 77 77 P 25.6 25.6 25.6

3 PCC Cu.M 25 25 P 12.5 12.5

4 FIRE BRICKS Cu.M 260 260 P 130 130

ACTUAL AVAILABILITY OF MAN POWER BOTH TANKS

CONTRACTOR /AGENCY NAME panda


Sheet : 7 of 17

Program for Balance work of Civil Tank Foundation

Balance Qty. as Balance Qty. as MATERIAL Program for Balance Work


Sl. No. Balance Work Unit P/A
on 25-05-22 on 31-05-22 AVAILABILITY 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun

NAME OF THE PERSON ASSIGNED FROM B&R

CONTACT DETAILS

CIVIL ENGINEER SIGNATURE LEAD CIVIL ENGINEER SIGNATURE

LS-ATF TANK-50

1 Stone Blanket Cu.M 750 0 P 750

2 PCC Cu.M 11 0 P 11

3 Reinforcement MT 14 MT 14 MT P 4.66 4.66 4.66

4 Shuttering Cu.M 554 554 P 184.67 184.67 184.67

5 RCC Casting Cu.M 119 119 P 59.5 59.5

6 Bitiminus Painting Sq.M 150 150 P 75 75

7 SAND FILLING 1ST LAYER Cu.M 300 300 P 150 150

8 SAND FILLING 2ND LAYER Cu.M 300 300 P 150 150

9 PVC Liner Sq.M 1100 1100 P 1100

A
Sheet : 8 of 17

Program for Balance work of Civil Tank Foundation

Balance Qty. as Balance Qty. as MATERIAL Program for Balance Work


Sl. No. Balance Work Unit P/A
on 25-05-22 on 31-05-22 AVAILABILITY 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun

10 SAND FILLING 3RD LAYER Cu.M 300 300 P 150 150

11 SAND FILLING 4TH LAYER Cu.M 300 300 P 150 150

12 SAND FILLING 5TH LAYER Cu.M 300 300 P 150

13 C P SYSTEM Lot 1 1 P

14 Crused Stone Cu.M 100 100 P

15 Premix Carpet (Asphalt Skim Coat) Cu.M 96 96 P

ACTUAL AVAILABILITY OF MAN POWER

CONTRACTOR /AGENCY NAME


GDC
NAME OF THE PERSON ASSIGNED FROM B&R

CONTACT DETAILS

CIVIL ENGINEER SIGNATURE LEAD CIVIL ENGINEER SIGNATURE


Sheet : 9 of 17

13-Jun 14-Jun 15-Jun

207.5

138

748.5 748.5
Sheet : 10 of 17

13-Jun 14-Jun 15-Jun

374.25 374.25 374.25

E
Sheet : 11 of 17

13-Jun 14-Jun 15-Jun

40.5

712.33 712.33 712.33


Sheet : 12 of 17

13-Jun 14-Jun 15-Jun

427.4 427.4 427.4

E
Sheet : 13 of 17

13-Jun 14-Jun 15-Jun


Sheet : 14 of 17

13-Jun 14-Jun 15-Jun


Sheet : 15 of 17

13-Jun 14-Jun 15-Jun

E
Sheet : 16 of 17

13-Jun 14-Jun 15-Jun

150

50% 50%

100

96

E
Status of Sand Supply As on 31-05-2022
Available Qty. (cum)
Required
Sl. No. Tank No. Upto
Qty. (cum) Today Cumulative
Previous

1 Alkylate-TK-44 2400 1800 1800


112
2 Alkylate-TK-43 2400 -

3 MS Tank 40 2525 1695 1695


120
4 MS Tank 39 2525 450 450

5 Sulpher Tank 54 462 385 385

6 Sulpher Tank 55 462 385 385

7 LS ATF Tank 50 1500 -

Total : 12274 4715 232 4715