ANALYSIS
PO: VSCWLL-13
JOB COMPLETION REPORT
Transformers Oil Process
and Analysis
Po :VSCWLL-13
Content
❖ Introduction
❖ Scope of work
❖ Site Preparation
❖ Oil sampling
❖ Oil circulation
❖ Handover
❖ Annexures
• Annexure 2 – TR4003J4 BDV Report (Barrel Oil / storage tank circulation oil )
• Annexure 6 – TR4004J4 BDV Report (Barrel Oil / storage tank circulation oil )
Po :VSCWLL-13
Introduction
The main objective of this project describes Transformer Oil Processing and Testing
(BDV & DGA Analysis) at Bapco . PGP contracting carried out the services on
Transformer Id TR4003J4 & TR4004J4 under the supervision of Voltech.
Scope of work:
• Transformer Vacuuming
• Filling oil from storage tank to Main body with BDV test.
Po :VSCWLL-13
Po :VSCWLL-13
Po :VSCWLL-13
Safety
In BAPCO Area 4 transformer units , all necessary safety PPEs and procedures
are followed by PGP employees as per the BAPCO safety Policies .
Po :VSCWLL-13
Note:
The Activities described in this report is for TR4003J4 & TR4004J4 Transformer unit.
Work summary
Transformer Area4 :
Manpower -3
• Safety talk and Tool box talk
• Transformer circulation 2nd cycle
3 5.7.2022 TR4004J4
completed.
• Housekeeping
Po :VSCWLL-13
Site preparation
All necessary tools and equipment were mobilized to site and stored in allocated area
and barricaded.
Oil sampling:
Oil samples has been taken from the new barrels and existing transformer before
commencing the work. These sample are subjected to DGA & BDV test ( refer test
results in Annexures)
Transformers Oil Process
and Analysis
Po :VSCWLL-13
The breakdown voltage test performed before filtration . Refer BDV results for new
oil & old transformer in Annexures
Po :VSCWLL-13
Oil circulation :
Oil in the Transformer were circulated on required cycles and ensured the BDV and
PPM values are at correct parameters . Refer BDV results for transformer TR4004J4 &
TR4003J4 in annexures.
Transformers Oil Process
and Analysis
Po :VSCWLL-13
Final Inspection :
• Ensure releasing of gases from the transformers.
• Ensured No leakage of oil in any part of unit.
• Ensured oil level in the conservator.
• Ensured that all valves are in normal Position.
Handover :
After completion of final inspection , Ensured all the tools and materials are cleared
from the site with proper housekeeping and handover to client .
VACUUM & OIL PROCESSING
4.7.2022
PGP CONTRACTING
ANNEXTURE - 1
OIL BREAKDOWN VOLTAGE TEST
Sample point BARREL OIL & STORAGE TANK Sampling Date 5.7.2022 & 6.7.2022
Sample point MAIN BODY OIL CIRCULATION Sampling Date 5.7.2022 & 6.7.2022
3.7.2022
PGP CONTRACTING
Annexure -5
OIL BREAKDOWN VOLTAGE TEST
Sample point BARREL OIL AND STORAGE TANK Sampling Date 4.7.2022 & 5.7.2022
.
Oil Barrel Before Filling Storage Tank after oil circulation
Sample point Transformer Main Tank Sampling Date 4.7.2022 & 5.7.2022
.
1st cycle after Circulation 2nd cycle after circulation