You are on page 1of 2

DAILY REPORT

Project Name : NPK Chemical Plant 500.000 MTPY


Location : Krueng Geukueh, North Aceh
Client : PT. Pomeurah Acindo
Subcontractor : PT. Pupuk Iskandar Muda
Page : 1 Of 1
Day/Date : Rabu /30 September 2020

No. Today Activity Quantity Prev. Today Cum. Weight No. Today & Tomorrow Activity Status Remark
A SA TANK TK-801A Today Activity
1 Welding Bottom Plate 326.29 Meter 319.8 - 319.8 98.01 % 1 Welding Bottom Plate SA-A Tank Partial
2 Welding Vertikal Out Shell Plate 1 13 Joint 11.0 - 11.0 84.62 % 2 Welding Vertikal Out Shell Plate 1 SA-A Tank Pending Man Hole
3 Welding Vertikal In Shell Plate 1 13 Joint 11.0 - 11.0 84.62 % 3 Welding Vertikal In Shell Plate 1 SA-A Tank Pending Man Hole
4 Welding Horizontal Out Shell Plate 2&1 99.7 Meter 85.0 - 85.0 85.26 % 4 Welding Horizontal Out Shell Plate 2&1 SA-A Tank Pending Man Hole
5 Welding Horizontal In Shell Plate 2&1 99.7 Meter 80.0 - 80.0 80.24 % 5 Welding Horizontal In Shell Plate 2&1 SA-A Tank Pending Man Hole
6 Welding Roof Plate 400 Meter 150.0 30.0 180.0 45.00 % 6 Weding Roof Plate SA-A Tank Continue
7 Erection Handrail & Accessories 188 Ea 165.0 23.0 188.0 100.00 % 7 Erection Handrail & Accessories SA-A Tank Finish
8 8 Welding Bottom Plate SA-B Tank Partial
9 9 Welding Vertikal Out Shell Plate 1 SA-B Tank Pending Man Hole
B SA TANK TK-801B 10 Welding Vertikal In Shell Plate 1 SA-B Tank Pending Man Hole
1 Welding Bottom Plate 326.29 Meter 319.8 - 319.8 98.01 % 11 Welding Horizontal Out Shell Plate 1 SA-B Tank Pending Man Hole
2 Welding Vertikal Out Shell Plate 1 13 Joint 11.0 - 11.0 84.62 % 12 Welding Horizontal In Shell Plate 2&1 SA-B Tank Pending Man Hole
3 Welding Vertikal In Shell Plate 2 13 Joint 11.0 - 11.0 84.62 % 13 Welding Roof Plate SA-B Tank Continue
4 Welding Horizontal Out Shell Plate 2&1 99.7 Meter 85.0 - 85.0 85.26 % 14 Erection Compression Ring PA-A Tank Continue
5 Welding Horizontal In Shell Plate 2&1 99.7 Meter 80.0 - 80.0 80.24 % 15 Welding Roof Plate to Rafter Segment-7 PA-B Tank Continue
6 Welding Roof Plate 400 Meter 100.0 10.0 110.0 27.50 % 16 Erection Radial Bracing RR 03-11 Segment-8 PA-B Tank Finish
7 17 Erection Dome Segment-6 PA-B Tank Finish
8 18 Laying Roof Plate Dome Segment-9 PA-B Tank Finish
9 19
C PA TANK TK-701A 20
1 Welding Compression Ring 297.80 Meter 120.0 20 140.0 47.01 % 21
2 22
3 23
4 24
5 25
6 26
7 27
8 28
9 29
D PA TANK TK-701B No. Tommorow Activity
1 Welding Roof Plate to Rafter Dome Roof Segment-7 129 Meter 40.0 40 80.0 62.02 % 1 Continue Welding Bottom Plate SA-A Tank
2 Erection Radial Bracing RR 03-11 Segment-8 27 Ea 12.0 15 27.0 100.00 % 2 Continue Welding Vertikal Out Shell Plate 1 SA-A Tank
3 Erection Dome Segment-6 1 Segment - 1 1.0 100.00 % 3 Continue Welding Vertikal In Shell Plate 1 SA-A Tank
4 Laying Roof Plate Dome Segment-9&10 18 Ea - 18.0 18.0 100.00 % 4 Continue Welding Horizontal Out Shell Plate 2&1 SA-A Tank
5 5 Continue Welding Horizontal In Shell Plate 2&1 SA-A Tank
6 6 Welding Fit Up Roof Plate SA-A Tank
7 7 Erection Stairway SA-A Tank
8 8 Continue Welding Bottom Plate SA-B Tank
9 9 Continue Welding Vertikal Out Shell Plate 1 SA-B Tank
Photograph 10 Continue Welding Vertikal In Shell Plate 1 SA-B Tank
11 Continue Welding Horizontal Out Shell Plate 1 SA-B Tank
12 Continue Welding Horizontal In Shell Plate 2&1 SA-B Tank
13 Welding Roof Plate SA-B Tank
14 Continue Welding Compression Ring PA-A Tank
15 Continue Welding Roof Plate to Rafter Segment-7 PA-B Tank
16 Welding Roof Plate to Rafter Segment-8 PA-B Tank
17 Laying Roof Plate Dome Segment-9 PA-B Tank
18 Fit Up Roof Plate Dome Segment-9 PA-B Tank
19 Fit Up Roof Plate Dome Segment-10 PA-B Tank
20
21
No. Concern / Potential Delay
1 Dome Segmen PA Tank
2
3
No. Indirect Worker Quantity
1 Project Manager 1 Person
2 Site Manager 1 Person
3 Construction Manager 1 Person
4 Supervisor 1 Person
5 Admin Project 1 Person
6 Accounting & Finance 1 Person
7 HSE Officer 1 Person
8 Foreman Welder 1 Person
9 Foremen Fitter 4 Person
10 Foreman Schafolder 1 Person
11
12
No. Tools & Equipment Quantity No. Tools & Equipment Quantity No. Direct Worker Quantity
1 Crawler Crane 150 Ton 1 Unit 13 Cutting Torch 1 Unit 1 Operator 2 Person
2 Crawler Crane 100 Ton 1 Unit 14 Clamp Verikal 2 Unit 2 Rigger 4 Person
3 Portable Air Compressor 1 Unit 15 Clamp Horizontal 3 Unit 3 Welder 25 Person
4 Gerinda 14 Inch 2 Unit 16 WireRoup Sling 3 Unit 4 Fitter 29 Person
5 Gerinda 7 Inch 10 Unit 17 Sackle 8 Unit 5 Helper 6 Person
6 Gerinda 4 Inch 14 Unit 18 Spreader Beam 2 Unit 6 Schafolder 6 Person
7 Gerinda 5 Inch 2 Unit 19 Railway Gusset 5 Unit 7 Electrical Control 2 Person
8 Trafo Las 29 Unit 20 Bag P3K 1 Unit 8 Tool's Control 3 Person
9 Trafo Las MIG 4 Unit 21 Webbing Sling 2 Fly 2 Unit 9
10 Oven 3 Unit 22 Shackle 1/2" 8 Unit 10
11 Dryer 19 Unit 23 Tune Buckle 1/2" 8 Unit 11
12 Apar 8 Unit 24 12
No. Materials Quantity No. Materials Quantity Weather Status Condition
1 Pipa Schafolding 1 1/2" RENDEZ EN39 140 Btg 9 07.00 - 10.00 B
2 Clamp ANMAN 48,6 800 Ea 10 10.00 - 12.00 C
3 Metal Plank Ashiba 90 Ea 11 12.00 - 14.00 B
4 12 14.00 - 16.00 A
5 13 16.00 - 18.00 B
6 14 Remark :
7 15 A = Clear C = Drizzle E = Heavy Rainy
8 16 B = Cloudy D = Rainy
PT. Pupuk Iskandar Muda PIC Sign PT. Pomeurah Acindo PIC Sign Note

Created By Checked By

Checked By Approved By

Page 1 of 2
Approved By

Page 2 of 2

You might also like