Professional Documents
Culture Documents
8 m Dia
8B Bridge Construction Project - PIK 2
Concrete Usage
PT. GEOTEKINDO
BORED PILE FOUNDATION BRIDGE J8B
Starting July 1, 2021 we started moving the equipment to the site one by one
to the construction of bore pile area 8B Bridge A1 And started the first drilling on
July 05, 2021 because we just found out the very soft ground condition under the
surface of the first pile was completed on July 9, 2021 and the last pile finished on
August 12th. A total of 36 poles were completed. The overall pile depth is 1895.09
m and the amount of concrete according to the design is 954 m3 but after
completing all bore pile points the total amount of concrete used is 1245 m3 with
The first time we drilled the machine was always tilted due platform very soft
and to anticipate the equipment being in a safe condition first we put 1 m thick
stone on the platform and then installed a lot of steel plates for equipment
This method is used on “self-restraining” soils or soils that are prone to “over
provides protection and prevents the soil from collapsing into the hole. However,
have also checked the results of the slurry test together with the Wika staff for the
foundation treatment
And then 15 – 53 m the condition of the soil type is clay where the soil is
With the condition of the soil layer as the data above will be easily prone