You are on page 1of 37

Section-I

Technical Specifications

LIST OF APPROVED SOURCES:

All the items like light fittings, cable/wires, switches & sockets, conduits, fans MCB, ELCB,
Energy Meters & Distribution Boards etc. shall be of approved makes given below and shall
have prior approval of make so chosen.

S. Brief Description of Ref. and No. of Approved Sources


No Item the Specifications
(Latest Version)
1 Transformer IS:2026/Pt.I to IV Crompton Greaves, GEC (AREVA
/1977(Latest T&D), Kirloskar, Bharat Bijlee, BHEL,
Version) Andrew Yule & Co., Mirzapur electrical
Industries,
2 SF6 Insulated Vacuum IEC 62271-100 & Schneider Electric India Ltd., AREVA
Circuit Breaker Panels IEC 62271-102 T&D, ABB, Siemens.
(33 KV) (Latest Version)
3 HT Protection Relays IS:3842 (Latest AREVA T&D India Ltd., L&T, Siemens
Version) Ltd., Easun Rey Rolle Ltd., ABB,
4 ACB IS: 13947/Pt-I&II JSL Industries Ltd., Mysore, Electrical
as applicable. Industries Ltd., GE, Schneider,
Siemens, C&S, Beco Lawrie Ltd,
Havells, ABB.
5 HT CT IS:2705/Pt.I to Compton, Kappa, SIEL, AE Perfect or
Pt.IV/1972 as original Manufacturer of HT Panel
applicable
6 LT C.T IS:2 7 0 5 /Pt-I to AE, INDOTECH, IIC, Siemens
Pt- IV/1992 as
applicable
7 Measuring Instrument IS:1248 (Latest Havells, AE, L&T, National Instrument,
Version) Kolkata/Chennai, MECO Instruments,
Motwani, Secure Meters Ltd., Indo
Tech.
8 Electronic Trivector IS:13779 (Latest National Instruments Chennai, Motwani
Meter Version , JMP Power Ltd., L&T, EMCO
9 Electronic Energy IS:13779(Latest AE, L&T, HPL, Havell’s
Meter Version)
10 End Termination Kits IS:13573 (Latest Yamuna Gases & Chemical Ltd.,
for 33KV Version) Mohindra Engg. & Chemical Product,
Raychem RPG Ltd., Hari Consolidated
(P) Ltd.
11 Diesel Engine IS: 33Cummins, Kirloskar, Ashok Leyland,
10000/1980(Latest Perkins, Detroit, Greaves (Formerly
Version) M.W.M. & Ruston)

12 Alternator IS: 4722 Kirloskar, NGEF, KEL, Crompton,


Jyoti, Stamford.
13 Bus Trunking IS:8623/1993 Siemens, C&S, ABB, Schneider,
Part– I &II, IEC Legrand, Zucchini, GE
60439 Part–I &II,
IEC 60429
14 MCCB IS:13947/PtIII/1993 Schneider, Havells, AREVA, T&D Ltd.,

Page 141 of 177


Signature of Tenderer
as applicable L & T, Andrew Yule & Co., C&S,
Standard Electricals Ltd., Nikodar Rd,
Jallandhar, Indo Asian Fusegear Ltd.,
Siemens Ltd., Bhartia Cutler Hammer
Ltd., GE India, JSL Industries Ltd.,
Legrand, ABB.
15 MCB 10kA, RCCB & IS 8828/96 Legrand, Schneider, Hager, ABB Ltd.
Prefabricated
Distribution Board
16 Automatic Capacitor IS:8623/Pt.I&II/ L&T, Siemens, ABB, EPCOS, Havells,
Bank & Control Panel 1983(Latest GE
Version)&IS13925
/Pt.I&II/1998
(Latest Version)
17 Ferrules/Lugs Relevant IS Metal Works, Dowell’s, Usha Martin,
Killpon System & Electricals, Comet
18 Time Switch Relevant IS GIC, HDS Legrand, Havell’s, Noida, GE
(Latest) India, JSL Industries, Industrial Kalinga,
Indo Asian Fuse gear
19 . Clustered LED Relevant IS C& S, L&T, Siemens, ABB, Tecknic etc.
indication light
20 G I Pipe IS:1239/Pt.I/1990 Tata, Jindal, BST 15. CFL Lamp
Relevant IS Surya Roshni, Bajaj,
Crompton, Philips, GE Ltd., Osram,
MAC SUN Industrial Co., Wipro,
Havell’s, GE India, Asian Fuse gear.
21 HDPE (DWC) Pipe Relevant IS Carlon, Emtellle, Awadh, Gwalior,
Duraline, Rex Polyextrusion ltd
22 PVC Conduit Pipe IS9537/Pt.III/198 3 AKG, Kalinga, BEC,Setia
(Latest Version)
23 Energy efficient T-5 RDSO Crompton, Philips, Bajaj, Wipro etc.
fittings. Specification
24 Flood light fitting, Relevant IS ECE Ind. Ltd., Phillips, Bajaj, Crompton
Industrial type fitting & Greaves, Grossav Industries, Wipro
2x28 W Dust & Lighting, Keslecschireder, GE India,
moisture/ jet proof Padam Electricals, Industrial Kalinga,
fitting Lord Krishna Electronic, Havells.
25 CFL Fittings Relevant IS Keslech India, Sinco Lite, Twincle
Industries, Trilok Chand & Sons,
Crompton Greaves, Phillips, Surya
roshini, Wipro Lighting, Bajaj Industrial
Kalinga, Indo Asean Fuse gear, GE
India, Lord Krishna Electronic.
26 White Hylum Sheet IS:2036/1979 Bakelite Hylem, Formica
(Latest Version)
27 XLPE H.T Cables IS 7098/Pt.I/1985 Nicco Corp. Ltd., Havelles, Fort Gloster
Industries Ltd., Industrial Cables India
Ltd., Cables Corp. of India Ltd.,
Universal Cables Ltd., Asian Cables &
Industrial Ltd., Polycab Wires (P) Ltd.,
KEI Industries, KEI Industries Limited.
28 LT XLPE Cable IS 7098/Pt.I/1985 Nicco Corp. Ltd., Havelles, Fort Gloster
Industries Ltd., Industrial Cables India
Ltd.,Cables Corp. of India Ltd.,
Universal CablesLtd., Asian Cables &
Industrial Ltd., Polycab Wires (P) Ltd.,
KEI Industries, KEI Industries Limited.

Page 142 of 177


Signature of Tenderer
Havells, Polycab

29 ISI PVC insulated IS-694/1990 National Insulated Cable, Grandlay


FRLS copper Electricals, Finolex Cables Ltd., Cable
conductor cable Corporation of India Ltd., Indian Cable
Co. Ltd., Asian Cables Corp. Ltd.,
Oriental Power Cables Ltd., Fort
Gloster Industries Ltd., Universal
Cables Ltd., Glaxy Power Cables Ltd.,
Victor Cables Ltd., TARA Cables
Industries, Deco Industries, Vijay
Cables Industries, Maxwell Power
Industries, Pee Kay Industries, Cap
Cond. (India), Ajanta Electric Industries,
Insucon Cables & Cond. (P) Ltd.,
Uniflex Cables Limited, Apollo Electric
Industries, Sainath Fibers (P) Ltd.,
Chanda Cables, Goyolene Fibers
(India) P. Ltd., Shree Nakoda Cables
Pvt. Ltd., Preetam Electric Co., Unisef
Cable Industries, Somex (India),
Skytone Electrical (India) Ltd., Weldon
Cables Pvt. Ltd., Delton Cables Ltd.,
Suraj Cables, KEI Industries Limited,
Havelles, Midlife Electricals, Standard
Electricals limited, Ecko Cables Pvt.
Ltd., Gaurav Cables Pvt. Ltd, Mayur
Electrical Industries Pvt. Ltd

30 LT Cable IS 13573 (Latest Yamuna gases & Chemical Ltd.,


jointing/Termination kit Version)Relevant Mohindra Engg. & Chemical Product,
for XLPE/PVC/PILCA IS Raychem RPG Ltd., Hari Consolidated
cable Pvt. Ltd.
shrink/Tapex/Cold
shrink suitable for
cable to relevant
31 Selector Switch Relevant IS Kay Cee, L&T Salzar

Note:
1. RDSO’s specifications are priced document and can be purchased from RDSO.
2. The specifications of CEE/C/Northern Railway are part of the tender document.
3. Items which are not covered above shall be ISI marked
4. Items which are not covered shall be got approved from CEE/USBRL &
Dy.CEE/C/BANIHAL.

Page 143 of 177


Signature of Tenderer
Section –II

EXPLANATORY NOTES TO SCHEDULE OF PRICES FOR ELECTRICAL GENERAL


SERVICES WORKS.

GENERAL.

These explanatory notes are for guidance of field staff. Each work has its own particular
requirements. Engineer in-charge will be responsible for successful execution of work as
per technical specifications.

All electrical works should comply with Indian Electricity Act 2003 and Indian Electricity
Rules 1956.

All electrical installations works shall conform to relevant Indian Standard Code of Practice
and carried out as per relevant safety Code of Practices, Guide for Safety Procedures in
Electrical Work as per I.S. 5216/Pt.I& II/1982 shall be observed.

All components used in installation shall be of appropriate ratings of voltage, current and
frequency.

All minor items viz. hardware items, foundation bolts, termination lugs for electrical
connections etc. as required and necessary for proper working of the equipment shall be
deemed to have been included in the tender, whether such items are specifically mentioned
in the tender documents or not.

The work shall be carried out under the supervision of the Railway Engineer.

The tenderer must inspect the site thoroughly before quoting rates, later on no claim shall
be accepted.

The Railway reserves the right to reject or alter any part of the work executed by the
Contractor which in the judgment of the Railway does not comply with the requirements of
the above specifications. The decision of the Railway shall be final and conclusive for all
purpose and contractor shall have no claim on this account whatsoever.

TESTING & COMMISSIONING:

After satisfactory erection & installation of all items of each quarter shall be commissioned
by giving electricity and checked for its operation acceptance. In case regular electric
connection not available, the installation shall be commissioned with temporary electricity
arrangement.

ANCILLARY WORKS:

All other ancillary works and works incidental to main works shall be carried out ad per
code of practices and manual of instructions of Railways and as per the instruction of
Engineer-in-charge.

INSPECTION

The works shall be accepted after inspection by the competent authority, particularly for
following aspects:

(i) Setting out of electrical equipment.


(ii) Approval of quality of works Erection, testing and commissioning as per the
approved drawings & IS codes of practice.

Page 144 of 177


Signature of Tenderer
(iii) Safety works to conform to Indian Electricity Rules. These aspects shall be
checked during periodical inspections. Any defects/ deficiencies noticed in
construction works will be recorded in site order book so that Contractor Acts
upon it without loss of time.

ITEM NO NS- 1 OF BOQ

TECHNICAL SPECIFICATION FOR 33KV/0.433KV, 1500KVA ON LOAD TAP CHANGER


BASED TRANSFORMERS FORGENERAL SERVICES (OUTDOOR TYPE)

1. SCOPE
This specification covers the Supply, Installation ,Testing & commissioning and delivery of
oil immersed, naturally cooled, three phase, 50Hz double wound, on load tap changer
based distribution transformers of 1500kVA capacity for use on system voltage of 33kV with
AVR and RTCC Panel. The Transformers should be complete with first filling of transformer
oil conforming to IS: 335/ 1993 and all accessories.

2. LOCATION AND SITE CONDITIONS:

The general atmospheric conditions at site shall be as under:

Elevation above M.S.L. = 1600m above MSL

Maximum ambient temperature = +50Deg Centigrade

Minimum ambient temperature = -15 Deg Centigrade

Humidity = 60% to 100%

Insulation de-rating factor = 0.7% at high altitude

Incoming voltage is ranging from 21.45kV to 34.65kV at 33kV system.

3. GOVERNING SPECIFICATION.

a) The transformer shall fully conform to IS: 2026 –1977 and OLTC as per IS: 8448-
1977 (with latest amendments) and the Indian electricity rules wherever applicable,
unless otherwise modified and enclosed guarantee of technical particulars.
b) IS: 10028/1985 (Latest) – Code of practice for selection, installation and
maintenance of transformer.
c) IS: 1271(Latest)–Thermal evaluation and classification of Electrical Insulation.
d) IS: 2099(Latest) – AC 1000V and above.
e) IS: 3347(Latest) – Dimensions of Porcelain Transformer bushings.
f) IS: 3637(Latest) – Gas operated relay (as per requirement).
g) IS: 6600 (Latest) – Guide for loading of oil type transformer.
h) IS: 5(Latest) – Painting.
i) The Transformer oil shall comply with IS: 335-1972(latest) “Indian standard
specification for insulating oil for transformer and switchgears as amended till date.
j) In case of any conflict between the above standards and the stipulations of this
specification, latter shall apply.
k) Any deviation from this specification, calculated to improve the performance and
efficiency of the equipment, proposed by the tenderer shall be given due
consideration in fill particulars with justification thereof are given.
l) In such case the tenderer shall quote according to the specification and the
deviations proposed by him shall be quoted as an alternative.

4. RATING AND PARTICULARS:

Page 145 of 177


Signature of Tenderer
The transformer shall have the following rating and other particulars:

1 Type Double wound, three phase, oil immersed,


natural air cooled, and step down
transformer for outdoor installation.
2 Rated Primary voltage 33kV the primary voltage may however from
21.45kV to 34.65kV in service.
3 Rated secondary voltage 433 volts
4 Rated frequency 50Hz
5 Rated output As per capacity of transformer (at all tap
(at all tap positions) positions)
6 Tapping Tapping shall be provided for a voltage
adjustment on the high voltage of plus 5%
and minus 35% of the rated voltage, the
tapping being located on the high voltage
winding. All tappings shall be capable of
carrying full load current continuously.
7 Temperature rise See clause
8 Impedance at 75 Deg C 6.25% subject to tolerance as per IS 2026(
Latest amendments)
9 Efficiency Max. at 50% rated output
10 Type of cooling ONAN

5. TRANSFORMER TANK:
The tank shall be constructed of mild steel with a single tier construction so shaped
as to reduce welding. The tank shall withstand standard atmospheric pressure
under 95% vacuums for one hour without any leakage or deformation. The tank
shall also be tested for oil tightness for additional pressure of half atmosphere.
Certificates in compliance with these tests shall be furnished.

6. CORE:
(a) The core shall be built up of high grade cold rolled grain oriented silicon steel
laminations, conforming to BS: 601(Pt-II) (Latest). The transformer shall be suitable
for over fluxing up to 20% on any tapping without injurious heating. The maximum
flux density in any part of the core under such conditions shall not exceed 1.9 Tesla
on the basis of M4, M5 and M6 grades as per BS: 601- Part-II (latest).

(b) All laminations used shall be level, free from waves, deformations, scaling of core
plating insulation capable of withstanding trees relief annealing. A core clamping
frame shall be of provided with lifting eyes for the purpose of tanking and untanking
the active parts of the transformers. The core shall be electrically connected to the
frame and tank for providing earthing to drain off any electrostatic potential that may
be built up.
(i) The core bolts and parts of the core clamping frame shall be insulated from the
core laminations and be capable of withstanding 2500V AC (rms) for one
minute.
(ii) Adequate provision shall be made to prevent movement of the core and winding
relative to the tank, during transport and installation or while in service.
7. RADIATORS:
a) Radiators shall be made from pressed steel.
b) Radiators shall be detachable and interchangeable. Top and bottom shut off
valve shall be provided for each radiator.
c) Each radiator shall be provided with air release valve and lifting lugs.
8. WINDINGS:
a) The windings shall have the insulation levels as specified in data Sheet.

Page 146 of 177


Signature of Tenderer
b) The winding assembly shall be dried in vacuum and impregnated under
vacuum with tested insulating oil conforming to IS: 335-1972 (latest) Uniform
insulation shall be provided for both HV and LV windings.
c) The windings shall be designed to reduce to a minimum the out of balance
forces in the transformers at all taps. The windings shall be suitably
designed and braced to withstand without damage the thermal and dynamic
effects of external short circuits. All leads and connections shall also be
mechanically strong, protected and rigidly clamped to withstand dynamic
stresses due to terminal short circuits.
9. BUSHINGS AND TERMINAL ARRANGEMENTS
a. Bushings: The transformer bushings shall be type tested according to
IS:2099-1973.
b. Terminal arrangements: A high voltage porcelain bushing of appropriate
rating satisfying the requirements shall be used for the winding at the coming
line end. The other end of the HV class bushing and connected externally by
means of a suitable tin coated copper link to the tank. The whole
arrangement of the bushing and connection of the link to the tanks shall be
housed in a sheet steel enclosure welded on to the tank and having a bolted
cover. The terminal of HV bushing shall be of copper alloy. Precisely
threaded of suitable dimension.
c. Terminal Clearance: As per relevant IS.
d. The manufacturer shall be required to manufacture termination box for
Termination of 33kV XLPE cable on HT side and termination box suitable for
terminating copper bus trunking on LV side. The Contractor/Manufacturer to
coordinate with Railway/Bus Trunking Manufacturer regarding termination
arrangement on LV and HV sides.
e. GASKET High quality long life heat resistant gaskets shall be provided to
ensure that no oil leakage occurs. Nitrile gaskets shall be preferred.
10. STANDARD KVA RATING
The standard KVA rating shall be 1500 kVA for 33kV class station transformers.

11. VOLTAGE RATIO AT NO LOAD


33000/433 volts with On Load Tap Changer (OLTC).

12. TAPPINGS
(a) Tapping shall be provided for a voltage adjustment on the high voltage of
plus 5% and minus 35% of the rated voltage, the tapping being located on
the high voltage winding.
(b) Tap changing shall be effected by means of an in built On Load Tap
Changer switch capable of being locked in position, with AVR and RTCC
panel.

13. WINDING CONNECTION AND VECTORS

The primary winding of these transformers shall be delta connected and the secondary
winding star (vector symbol Dy -11). The neutral of secondary shall be brought out to a
separate insulated terminal.

14. CONSERVATOR

The Transformer should be fitted with conservator.

15. RATING AND TERMINAL MARKING PLATE

Page 147 of 177


Signature of Tenderer
Each transformer shall be provided with non detachable rating and terminal marking
plate of weather proof material fitted in a visible position and showing the complete
information as under clause - 17 of IS:1180(Part-1) 1980 (latest).

16. LIMITS OF TEMPERATURE RISE


50 Deg C rise of top oil over an ambient temperature of 50 Deg C.

17. FITTINGS AND ACCESSORIES


The following standard fittings shall be provided on each and every transformer,
depending upon its rating and in accordance with relevant reference standard,
unless otherwise modified.

a. Name rating and terminal marking plate.


b. Two earthing terminals.
c. Lifting Lugs.
d. Drain/sampling valve.
e. Silica Gel Breather with dehydrated silica gel.
f. Oil level indicator with minimum/maximum level marking.
g. Thermometer pocket with dial type thermometer.
h. Oil filling hole and cap.
i. Conservator tank with drain valve.
j. Explosion vent.
k. Valve for oil filtration.
l. H.V. protection bushing with arcing horns (3 Nos.).
m. L.V. protection bushings.
n. Unidirectional rollers.
o. Skids.
p. Air release device.
q. On load tap changing switch with automatic/manual override with locking
arrangement.
r. AVR and RTCC panel.
s. Buchholz relay as required.
18. PAINTING
All steel surfaces which are in contact with insulating oil shall be painted with heat
resistant, oil insoluble insulating varnish. All steel surfaces which are exposed to
weather shall be given a primer coat of zinc chromate, and two coats of light gray
paint.

19. DRYING OUT OF THE TRANSFORMERS:


The transformers shall be supplied complete under oil as per IS335-1972 after being
dried out under vacuum at the manufacturer’s works, ready for commissioning.

20. TESTS ON TANK DURING MANUFACTURE:

A. The following testes shall be carried out during manufacture of the transformer:
i) Oil leakage test:

a) All tanks and oil filled compartments shall be tested for oil tightness by being
completely filled with air/oil of viscosity not greater than that of the insulating oil to IS:
335 at ambient temperature and subjected to a pressure equal to the normal static oil
heating including atmospheric pressure plus 35 kg/m² measured at the base of the
tank. The pressure shall be maintained for a period of not less than 12 months for oil
and 1 hour for air, during which time no leakage shall occur.

b) Air pressure test:

The tank of one transformer together with all its fittings including bushing in position
shall be subjected to a pressure test as laid down in clause 21.5 of IS: 1180( Pt.- I)-
1981.

Page 148 of 177


Signature of Tenderer
c). Vacuum Test:

The tank of one transformer shall be tested for an internal pressure of 38mm of Hg
for one hour. The permanent deflection of sheet after release of vacuum shall not
exceed the values specified below:

Length of plate --- Deflection

Up to 750mm ---- 5mm

750mm to 1250mm ----- 6mm

21. A certificate of compliance with the above tests shall be furnished by the
manufacturer for each transformer; however, if considered necessary by the
purchaser, the above test on one of the unit shall also have to be arranged by the
manufacturer in presence of the purchaser’s representative.
22. TYPE TEST:
The following type tests shall be carried out on one proto type:
Temperature rise test:

This test shall be carried out as per clause 4 of IS 2026 (Pt.-II)- 1977, the temperature
rise under full load at lowest tap or the minimum HV voltage shall not exceed the
limits below:

a. Winding 55 Deg C (by resistance method)


b. b Insulating oil 45 Deg C ( by thermometer)

LIMITS OF TEMPERATURE RISE

The temperature rise shall not exceed the limits of 55 degree centigrade (measured
by resistance), for transformer windings and 45 degree centigrade (measured by
thermometer), in top oil when tested in accordance with IS 2026 amended up to date.

IMPULSE VOLTAGE TEST:

1.2/50 microsecond impulse voltage of 250kV crest value shall be applied as per
clause 11&12 of IS 2026 ( Pt-III)-1977 (as per amendment from time to time to the HV
winding Live end, the other HV terminal being earthed and the winding connected to
the core and earth. Oscillogram for the voltage as well as neutral current shall be
recorded during impulse test.

SHORT CIRCUIT AND IMPULSE VOLTAGE TESTS

The short circuit test shall be done in accordance with clause 16.11 of IS: 2026-1977
with the following provision. After the tests the winding shall be dismantled and
carefully examined for signs of damage or coil distortion. Copies of short circuit test
and impulse voltage withstand test as per IS: 2026 (latest) from a recognized test
house laboratory and heat run test certificates must be furnished. In case short circuit
test more than five year old, then fresh test shall be conducted free of cost by the
form at a reputed laboratory.

23. TESTS AND CERTIFICATES


(a) All transformers shall be subjected to all the manufacturer’s works tests as per
relevant reference standards, free of cost.

(b) Heat run test shall be conducted by the manufacturer, free of cost, when the
material is being inspected by an authorized representative of the Railway/RITES.

Page 149 of 177


Signature of Tenderer
24. TERMINAL ARRANGEMENT:
Terminal arrangement shall be cable termination box for HV Cable and Cable/Bus
trunking termination box for LV side as required for each side. The manufacturer shall
submit General arrangement drawing showing termination arrangement for each
rating of transformer for approval of NR.

25. LOADING:
In accordance with IS: 6600-1972, amended up to date, the transformer shall be
capable of being overloaded as per guidance given therein.

26. INSPECTION OF EQUIPMENT AND TESTING ATMANUFACTURER’S WORKS


Manufacturer must have suitable facilities at their works for carrying out various
performance tests on the plant. The tenderer should clearly confirm that all the
facilities exist and shall be made available to the inspecting authority.

The inspection shall be carried out as per sampling plan of relevant IS specification by
the representative of Railway/RITES. The tenderer should provide satisfactory evidence,
acceptable to the purchaser to show that he is a licensed manufacturer and has
adequate plant and manufacturing capacity and has a “quality assurance programme”.
The tenderer will submit quality assurance plan being followed at the manufacturer’s
works for ensuring quality of the product offered. A sample inspection chart for
inspecting the plant should be supplied along with the bid. The inspection chart should
indicate all the tests that are carried out during the plant manufacturer.

He should furnish a statement giving a list of supplies made by him in the last 3 years of
the items offered by him or similar items, along with the purchaser’s name and address,
order number, date and quantity supplied and their performance and whether the
supplies were made within the delivery period. In the absence of the above information,
the tender is liable to be rejected.

27. DEVIATIONS
The tenderer should certify that the transformers offered fully meets the
specifications. Various design features incorporated in the transformer to fulfil
different technical performance requirement shall be fully explained in the offer.
However, minor deviations from these specifications which do not effect, or in any
way interfere with the stipulated performance standards or would result in improved
safety/reliability or would reduce recurring maintenance/operating cost can be
considered for acceptance. The tenderer in such eventuality shall clearly indicate the
details of these deviations and their implications along with the bid. The inspection
charts should indicate all the tests that are carried out during the manufacturing.

Before giving the inspection call for testing of the prototype of the transformer, the
Manufacturer shall submit a detailed test schedule consisting of circuit diagram for
each of the tests and nature of the test and duration of each test and total no. of days
required to complete the test in one stretch. Once the schedule is approved, the test
shall invariably be done accordingly. However, during process of type testing or even
later, railway representative reserve the right to conduct any additional test(s) besides
those specified herein, or any equipment/sub system so as to test the system to his
satisfaction for gaining additional information and knowledge. In case any dispute or
disagreement arises between the OEM and Railway during the process of testing as
regards the type test results, it shall be brought to the notice of the CEE/NR whose
decision shall be final and binding.

Only after clear written approval of the results of the tests on the prototype is
communicated by the purchaser to the manufacturer, shall he take up the baulk
manufacture of the equipment-which shall be strictly with same material and process
as adopted for the prototype. In no circumstances shall material other than those
approved in the prototype.

Page 150 of 177


Signature of Tenderer
Manufacturer should submit routine test certificate for transformer.

28. TEST VOLTAGE


The transformer shall be capable to withstand power frequency and impulse test
voltage pressure.

Nominal Highest Impulse test Voltage Power Test


System System Standard Frequency Voltage
standard Voltage standard
voltage Standard I Standard II Standard I Standard II
(kV RMS) (kV RMS) (kV Peak) (kV Peak) (kV RMS) (kV RMS)
33 36 70 170 70 170

29. WINDING:
The 33kV class distribution transformers shall be copper wound (electro type quality)

30. CLEARANCE (ELECTRICAL):


Clearance from phase to phase and phase to earth shall be indicated by the
manufacturers.

31. DATA SHEET FOR 1500KVA 33KV/0.433KV DISTRIBUTIONTRANSFORMER


Sr. Item Details Details
No
1 Capacity / Rating 1500 KVA
2 Installation Indoor/Outdoor Outdoor
3 Reference Standard i) IS 2026 ( Part-I to Part IV with
latest amendments
ii) IS 8468-1977 & 8478 with
latest amendments and IEC
60214
4 Continuous rating under conditions specified in IS 2026 (Part-I)1977 Clause
No.3
A Type of Cooling ONAN
B Rating (MVA) with ONAN Cooling 1.5MVA
C Rated Voltage 33kV
i) HV kV 0.433kV
ii) LV kV
D Rated Frequency Hz 50± 3%
E Number of phases 3
F Rated current at rated no load voltage
and on principal tap
i) LV Amps 2000.0
ii) HV Amps 26.2
5 Connections
i) HV Delta
ii) LV Star
6 Connection Symbol
a) Temperature rise of winding above ≤ 50ºC
reference peak ambient
b) Limit of hot spot temperature for
which transformer is designed 0ºC 95ºC
7. Tap Changer
a) Type of Tap changer OLTC IS 8468 8478 & IEC
60214
b) Make CTR/OLG
c) Rated Voltage 33kV
d) Which winding is the tapped winding HV

Page 151 of 177


Signature of Tenderer
e) No. of Steps & Step Voltage 17 steps 850V
f) Range of Tap changer
i) Plus 5%
ii) Minus 35%
iii) Power out put
a) On plus tap kVA 1500
b) On Minus tap kVA 1500
g) Control Manual/Local Electrical Remote Elect
Remote
i) Voltage Control Automatic
ii) Approximate over all dimension of tap As per manufacture
changer
h) Maximum overall weight of tap Compact
changer
i) Approximate mass of oil Compact
8 a) No Load loss at rated voltage and 0.16% of rated capacity
frequency at principal tap (kW)
b) Tolerance if any ±10%
9. Operation Test for 5000 operations
without contacts energised
a) Load loss at rated output, rated 1.1% of rated capacity
frequency and corrected for 75ºC
winding temperature at
b) Tolerance, if any ±10%
10 Positive sequence impedance on rated 6.25%
MVA base at 75ºC winding temperature
at
11 Efficiency at 75ºC winding temperature
as derived from Guaranteed loss figures
and at
a) At full load % 97.64
b) At ¾ load % 98.02
c) At ¼ load % 98.37
12 Insulating & Cooling medium Transformer Oil/mineral oil
13 Test Voltage
i) Lightening impulse withstand test 75kV
voltage (kV peak)
ii) Power frequency withstand voltage 75kV
(dry & wet for 1 minute) (kV rms)
14 Details of winding
a) Type of winding CROSS OVER
b) Material of winding conductors Copper (Electrolytic Grade)
c) Maximum current density of winding
(at rated current) and conductor area
ii) HV 2.6
ii) LV 2.6
d) Insulating material used for
i) HV winding INSULATION PAPER
ii) LV winding INSULATION PAPER
15 Permissible duration/of over load
following continuous functioning at
normal rated load in an ambient
temperature or 50ºC
a) 10% Overload 2 Hours
b) 20% Overload 1 Hour
c)30% Overload ½ Hour

Page 152 of 177


Signature of Tenderer
16 RMS value of sum metrical short circuit 22 Times of Full Load Current
current which can withstand and its for 0.5 Second for Dynamic
duration according to the clause No.9.19
of IS/2026 or Clause 1001 of ISS
17 Particular of HV & LV Bushing w/o arcing As per IS 3347/2009
horn
18 Weight & Dimension As per manufacturer
19 Detail of tank Made of CRCA

Installation and Commissioning of Distribution Transformers

32. The transformers shall be installed in accordance with IS: 10028(Part-II&III) Code of
practice for Installation and maintenance of transformer. Necessary support
channels shall be grouted in the flooring.
33. The Transformer shall be moved to its location and shall be correctly positioned.
Transformer wheels shall be either locked or provided with wheel stoppers. All parts
of the transformers which are supplied loose, such as conservator, radiator banks,
Buchholtz relay; dial thermometer bushing etc. shall be fitted on the transformer.
Transformer oil supplied in drums shall be topped up into the transformer after duly
testing/filtering upto the correct level required.
34. Wiring of devices such as Buchholz relay, dial thermometer etc. shall be carried out
as per drawings, Earthing of neutral and body of the transformer shall be done in
accordance with section (7) of these specifications.
35. Drying out of transformer winding will be necessary when the di-electric strength of
the oil is lower than the minimum value as per IS:10028 or the transformer has not
been energized within 6 months of leaving the works or where the radiator assemble
is done at site. The transformer shall be dried out by one of the methods specified in
SI: 10028. Drying out with centrifugal or vacuum type filters will, however, be
preferred. The contractor shall carry out the process of drying without interruption
and shall maintain a log sheet indicating time, oil temperature and insulation
resistance.
36. After complete drying out of the transformer, oil sample shall be collected by the
contractor and shall be tested for dielectric strength as specified in IS:335/1993 with
approved test kit.
37. All devices such as dial type thermometers, Buchholz relays and main alarm and trip
contacts shall be checked for satisfactory operation.
38. All tests specified in 3.2.14 of these specifications shall be carried out by the
contractor in the presence of inspecting officer/consignee free of cost.
39. The control wiring between RTCC Panel, OLTC shall be done by the contractor
using copper control cable of good quality.

ITEM NO NS- 2 OF BOQ

33KV SF6 INSULATED VACUUM CIRCUIT BREAKER PANELS

1. SCOPE:
These specifications cover the detailed requirements for design, fabrication, supply,
installation, testing and commissioning of 33KV indoor, factory assembled, Type Tested, 3
pole Metal Enclosed SF6 insulated Vacuum Circuit Breaker High Voltage Panels of 3
Phase 630 Amp Capacity suitable for b/c 25 KA for fault current. This also includes any
material, equipment, appliances and incidental work not specifically mentioned herein or
noted on the Drawings/Documents as being furnished or installed, but which are necessary
and customary to be performed under this contract.

2. TYPE OF PANELS:

SF6 GAS INSULATED VACUUM CIRCUIT BREAKER: H.V. PANEL

Page 153 of 177


Signature of Tenderer
The Panel board shall be of indoor type, maintenance free, factory assembled, having the
incoming sectionalisation and switch gears as IEC 62271-100 for Breakers and-200 for
Panels/IS: 3427 of switch board. The contractor to ensure that the technology being used in
the Panel boards shall be proven for satisfactory operation over a long time. Panel shall
have internal enclosure of various components, internal arc resistant design and a
complete interlocking scheme to give a maximum degree of personnel safety.

The degree of enclosure protection shall be IP-3X for primary devices i.e. Vacuum Circuit
Breaker and three position disconnector and IP-65 for switchgear enclosure. Panel shall be
powder coated with highly resistant epoxy resin covering.

3. Ratings:
All panels assembled to form a board shall be suitable for the nominal operation voltage
and rupturing capacity as specified.They should be rated as specified with a minimum of
630 Amps and suitable for operation on 33KV, 3-phase, 50Hz system. Type test certificate
for the breaking capacity of the panel shall be supplied.

4. Type:
The HV panel Board shall be metal clad, indoor, floor mounting, free standing type. It shall
be totally enclosed dust, damp and vermin proof.

5. General Construction:
Switchgear panel shall consist of the following functional components:

a) Bus-bar compartment with 1-pole insulated, plugged in and bolted bus-bars.


b) Switchgear vessel with vacuum circuit-breaker and three-position dis-connector.
c) Cable compartment.
d) Low-voltage compartment.
e) Panel enclosure
The switchgear vessel shall be made of stainless steel, laser-welded and shall meet the
requirements of a sealed pressure system.

6. Bus Bar Compartment


Panels shall be interconnected by the plug-in bus-bars. The incoming and outgoing
Cables shall be connected through enclosed cable plugs of the outside-cone system.
All functional components of the primary part mentioned above shall be safe-to-touch.
Pressure shall be relieved to the top through a rear duct. The bus-bar cover shall
contain expanded metal to cool down the hot gases. The Internal arc classification
shall be according to IEC 62271-200.

7. Switchgear Vessel
The switchgear vessel made of hermetically welded stainless steel accommodates the
active, live parts of the switchgear:

- Vacuum interrupters

- Three-position disconnector

- Panel bars

- Bushings with capacitive layers

Gas pressure shall be maintained as specified by the manufacturer for operation of


switchgear in normal and fault conditions. Necessary arrangements shall be made for
measurement of Gas Pressure. Possibility of Leakage of gas shall be minimized ( as
specified in IEC) by using optimum technology for welding of vessel.

Page 154 of 177


Signature of Tenderer
8. Switching Devices

Vacuum Circuit Breaker

The vacuum interrupters shall operate linearly from the outside mechanism, without
kinematic deflections inside the enclosure. It shall be operated by the outside mechanism
without gaskets through hermetically sealed metal bellows which are welded into the
module partition.

The Operating mechanism of Vacuum circuit breaker shall be motorized with stored energy
spring mechanism. The operating mechanism shall be maintenance free having trip free
mechanism as per IEC. Auxiliary switch contacts for control and signaling shall be
available. It shall have indications for “Spring Charged” and “Mechanical Position”.
Manufacturer to provide in addition to motorized operation, provision for manual operation
of the mechanism. Tripping signal for circuit breaker and operation counter shall be
available.

Three Position Disconnector

The motorized disconnector and earth switch operation shall be in SF6 filled switchgear
vessel. The slow moving parts of the mechanism shall be outside the vessel. Manual
operation of disconnector and earthing switch shall also be possible. Position indicator shall
be provided on the front side pf the panel. Auxiliary contacts shall be provided for control
and signaling operation. Locking device shall also be provided for the three position
disconnector.

Following interlocks shall be existing in the breaker panel:

- Operation of the three-position disconnector cannot be selected as long as the circuit-


breaker is closed.

- When ''operation of three-position disconnector'' is selected, the circuit-breaker shall be


blocked against closing.

- Selecting ''disconnector function'' or ''earthing switch function'' shall release the operating
shaft of the associated switching operation only.

- The operating lever cannot be removed until the switching operation has been completed.

- The circuit-breaker cannot be operated until the operating lever of the three-position
disconnector has been removed and the control gate is moved to the center position.

- Feeder earthing (three-position disconnector to EARTH and circuit-breaker CLOSED) is


secured against ''deearthing'' (by a padlock).

- Electrical connections to releases are interrupted when the three-position disconnector is


switched to Earthed.

- The feeder locking device prevents the circuit-breaker from being switched off echanically
at the panel.

- Feeder locking device with signaling switch.

9. Cable Connections:
The Cable compartment shall be accessible from the front.Provision for connecting upto
three cables per phase shall be there. Cable testing shall be possible directly at the
terminations. Capacitive voltage detection system at the terminations in the bushings.

Page 155 of 177


Signature of Tenderer
10. Instrument Transformers:
Current transformer shall be ring core type and shall be fitted outside the switchgear vessel.
They shall be fitted on the bushings in front of the cable terminations. Ratio of both the
cores of the current transformers shall be selected as per the site requirements. Accuracy
class of Current transformer core for metering shall be 1.0 and 5P/10 for metering. Routine
test certificates shall be provided along with other documents.

11. Bus Bar


The bus-bar shall be located outside the SF6 compartment in a metal enclosure and shall
be plugged onto the switchgear vessels and bolted tight. The bus-bar itself shall be made of
round-bar copper. It shall be insulated with silicone rubber, which shall be coated with a
conductive layer on the outside and earthed. The bolted joints shall be insulated with cross
adapters, also made of silicone rubber. These cross adapters shall also be coated with a
conductive layer both inside and outside.

12. Switchgear Operation:


Switchgear operation shall be mechanically via control elements at the panel front.
Switchgear operation shall also possible through a suitable bay controller processing unit to
be mounted on the panel front. This bay control unit shall also act as an interface between
SCADA and the VCB panel. An LCD with mimic diagram of the feeder shall show the
switch position. More information such as voltage, current, power, power factor etc. shall be
possible to be accessed through this display.

13. Low Voltage Compartment


Low-voltage compartment shall be located at the front and shall be removable.

The secondary devices (numerical relays, metering, etc) shall be mounted in the low-
voltage compartment. The electrical connections to the primary part and from panel to
panel shall be through flexible wire harnesses using plug connectors.

External control cables shall be possible to be inserted from below /top of the panel on the
left side of the panel through a cutout in the panel base.

Rating plate of the panel shall be fixed on the inside of Low voltage compartment door.

14. Protection and Tripping Arrangement

(a) Protection:
The Relays shall be microprocessor based numerical relays with O/L, E/F and S/C
protection, and differential protection of transformer as specified.

Tripping relay shall be used for tripping signal to the Shunt Trip Coil of Circuit
Breaker operating on 30V DC supply Power pack/110 V VT supply.

(b) Alternatively Auxilliary power can be supplied using convertor, battery chargers and
lead acid Ni-Cd batteries of suitable rating to give 30V DC output and to cater to
load of the control system in the VCB Panels. The ratings of the auxiliary power
system shall also be got approved from the VCB Panel manufacturer.
(c) ) Relays:
Numerical Over current Relays shall be provided in incomer and outgoing VCBs as
specified in the bill of quantities and shall have adjustable setting for current from
50% to 200% and earth fault from 10% to 40% or 20% to 80%. Numerical
Differential relays shall be provided for transformer outgoing VCBs. These should be
of manual reset type. All relays shall have a digital display LED indicator which will
indicate operation for each function. It shall be possible to reset it only by manual
operation. The number and types of relays shall be as specified. Numerical type
Differential relay shall be provided for each outgoing VCB for transformer and shall
be of 2 winding type, compatible for future SCADA system. The auxiliary control
relays can be of electro-mechanical type.

Page 156 of 177


Signature of Tenderer
15. TESTING AND COMMISSIONG
Procedure for testing and commissioning of relay shall be in general accordance with good
practice. Commissioning checks and tests shall include in addition to checking of all small
wiring connections, relays calibration and setting tests by secondary injection method and
primary injection method. Primary injection test will be preferred for operation of relay
though CTs. Before panel board is commissioned, provision of the safety namely fire
extinguishers, rubber mats and danger board shall be ensured. In addition all routine
megger tests shall be performed. Checks and test shall include following.

i. Operation checks and lubrication of all moving parts.


ii. Interlock function checks.
iii. Continuity checks of wiring, fuses etc. as required.
iv. Insulation tests.
v. Trip test and protection gear tests.
vi. The complete panel shall be tested with 5000V megger for insulation between poles
and poles to earth. Insulation test of secondary of CTs and VT to earth shall be
conducted using500V megger.
vii. Any other tests as may be required by the Licensee /Inspector shall be conducted.
viii. Where specified, the entire switch board shall withstand high voltage test after
installation.

16. DATA SHEET FOR 33KV VCB PANEL BOARD

Electrical Data And Unit 33KV VCB


Service Conditions
Rated Voltage KV 36 KV
Power Frequency Withstand KV 70
Voltage
Impulse Withstand Voltage KV 170
Rated Frequency Hz 50
Rated Current- Bus bars Amp 630
Rated Current-Vacuum Circuit Amp 630
Breaker
Short Circuit Breaking Current kA 25
for 1 sec (Vacuum Circuit
Breaker)
Short circuit making current kA 50kA
Trip/Close coil voltage 30VDC
Motor Voltage 110V AC
Busbar Material COPPER
Cable Entry I/C Through Rear bottom
Cable Entry O/G Through Rear Bottom
Enclosure Protection IP3X
Paint Shade Siemens Grey Shade
RAL 7032

17. Documentation:
Contractor to submit detailed General Arrangement Drawing of VCB along with the tender
documents. The VCB dimensions shall be in line with layout drawings for respective
substations attached with the tender. No deviation shall be entertained. On award of
contract the General Arrangement drawing shall be approved by NR, thereafter, the
contractor can go ahead with procurement of VCB Panel. Contractor shall also submit
Installation Manuals for VCB Panel, relays or any other equipment installed in VCB panel
along with the supply of material at site. The Contractor shall also be responsible for

Page 157 of 177


Signature of Tenderer
arranging the manufacturer’s engineer visits to site at the time of installation, testing and
commissioning and nothing shall be paid extra in this regard to the contractor.

ITEM NO NS- 3 , 26, 27,28 & 29 of BOQ

Technical specification 11/33KV XLPE Underground Cable & 1.1KV grade XLPE
Cable.

1. General Specifications:

(i) “Technical specification for manufacture & supply of 11/33KV XLPE Underground
Cable shall be as per the RDSO Technical Specifications NO. DSO/2009/EM/SPEC/
0002, REV. “O” JULY 2009” with latest amendment.

(ii) “Technical specification for manufacture & supply of 1.1KV grade XLPE Underground
Cable shall be as per the RDSO Technical Specifications NO.RDSO/ 2009/EM
/SPEC /0006,REV. “O” with latest amendment.

Specifications for laying of Cable shall be as per the CPWD General specifications for
Electrical Works Part–IV, Sub- Stations, 2007/latest.

2. Storage and Handling

a. Storage:-The Cable drums supplied by the contractor shall be storedon a


well drained, hard surface, so that the drums do not sink in the ground
causing rot and damage to the cable drums. Drums shall be stored on their
flanges and not on their flat side. Both ends of the cables shall be properly
sealed to prevent ingress/absorption of moisture by the insulation during the
storage. Protection from rain and sun is preferable for long term storage of
cables. there should also be ventilation between the drums. Damaged
battens of drums should be replaced as may be necessary.
b. Handling:-When the cable drums have to be moved over short distance
they should be rolled in the direction of the arrow marked on the drum.

For loading into and unloading from vehicles, a crane or a suitable lifting
tackle should be used. Small sized cable drums can also be rolled down
carefully on a suitable ramp or rails, for unloading, provided no damage is
likely to be caused to the cable or to the drum.

3. Installation
General

Cables with kinks, straightened kinks or any other apparent defects like defective
armouring etc. shall not be installed Cable shall not be bent sharp to a small radius
either while handling or in installation. The minimum safe bending radius for XLPE
cables shall be 12 times the overall diameter of the cable. At joints and terminations,
the bending radius of the cables shall not be less than 15 times its overall diameter.

a. Route :-Before the cable laying work is commenced, the route of the cable shall
be decided by Rly.
b. Proximity to communication cables: Power and communication cables shall be
as far as possible cross each other at right angles. The horizontal and vertical
clearance between them shall not be less than 60cm.
c. Methods of laying: The cables shall be laid direct in ground, pipe (for road
crossings etc.) or in trench as specified.

Page 158 of 177


Signature of Tenderer
Laying direct in ground:

a. Trenching: For laying cable/s directly in ground, the trench shall be made as per
drawing below. Width and depth of the trench for single and multiple cables is
shown in following drawing. Excavation of the trench shall be done by suitable
means –manual or mechanical. The excavated soil shall be stacked firmly by the
side of trench. Such that it may not fall back into the trench.

Laying of cable in trench:

a. Sand cushioning: The trench shall be then provided with a layer of clean, dry sand
cushion of not less than 8cm in depth before laying the cables therein.

The cable shall be tested for continuity and insulation resistance before laying.

The cable drum shall be properly mounted on jacks, or on a cable wheel at a


suitable location, Making sure that the spindle, jack etc. are strong enough to carry
the weight of the drum without failure, and that the spindle is horizontal in the
bearings so as to prevent the drum creeping to one side while rotating.

The cable shall be pulled over on rollers in the trench steadily and uniformly without jerks
and strain. The entire cable length shall as far as possible be laid off in one stretch. PVC/
XLPE cables less than 120 sq mm size may be removed by making one long loop in the
reverse direction.

Note: For short runs and sizes upto 50 sq mm of MV cables, any other suitable method of
direct handling and laying can be adopted without strain or excess bending of
cables. After the cable has been so uncoiled, it shall be lifted slightly over the rollers
beginning from one end by helpers standing about 10m apart and drawn straight.
The cable shall then be lifted off the rollers and laid in a straight line. The cables
shall be tested for continuity of cores and insulation resistance and the cable length
shall be measured, before closing the trench.

b. Sand Covering: Cables laid in trenches in a single tier formation shall have a
covering of dry sand of not less than 17cm above the base cushion of sand before
the protective cover is laid.

In the case of vertical multi tier formation, after the first cable has been laid, a sand
cushion of 30cm shall be provided over the base cushion before the second tier is
laid. The cables in top most tiers shall have final sand covering of not less than
17cm before the protective cover is laid.

c. Extra loop cable: At the time of original installation, approximately 3m of surplus


cable shall be left on each terminal end of the cable and on each side of the
underground joints. The surplus cable shall be left in the form of a loop.
d. Mechanical protection over the covering
(i) Mechanical protection to cables shall be laid over the covering as given below
to provide warning to the future excavators of the presence of the cable and to
protect the cable from accidental mechanical damage by pick-axe blows.
(ii) The cable shall be protected by second class brick of nominal size
22cmx11.4cmx7cm or locally available size, placed on the top of the sand. The
brick shall be placed breadth wise for the full length of the cable. Where more
than one cable is laid in the same trench this protective covering shall cover all
the cables and project at least 5cm over the sides of the end cables.

e. Back filling

Page 159 of 177


Signature of Tenderer
The trenches shall then be back-filled with excavated earth, free from stones or
other sharp edged debris and shall be rammed and watered, if necessary in
successive layers not exceeding 30cm depth.

(i) Unless otherwise specified, a crown of earth not less than 50mm and not
exceeding 100mm in the center and tapering towards the sides of the trench
shall be left to allow for subsidence.
(ii) Where, road be rms or lawns have been cut out of necessity or kerb stones
displaced, the same shall be repaired and made good except for turfing/
asphalting, to the satisfaction of the Engineer-in – Charge, and all the earth and
rock shall be removed to places as specified.

f. Route Markers: Route markers shall be provided by the contractor along the runs
of the cables at locations approved by the Engineer-incharge and generally at
intervals not exceeding 100m. Cable Route Markers shall be as per approved/
specification of Northern Railways.

Laying in Pipes:

In locations such as road crossing, entry to the buildings, paved area etc. cables shall
be laid in GI or RCC pipes. Pipes shall be continuous and clear of debris or concrete
before cables are drawn. Sharp edges, if any at the ends shall be smoothened to
prevent damage to cable sheathing. The same shall be arranged by the contractor at
no extra cost to Railway.

These pipes shall be laid directly in ground without any special bed. No sand
cushioning or tiles need be used in such situations.

a) Road Crossings:

i. The top surface of the pipes shall be at a minimum depth of 1m from the
pavement level when laid under roads, pavements etc.
ii. The pipes shall be laid preferably askew to reduce the angle of bend as the
cable enters and leaves the crossing.
iii. When pipes are laid cutting the existing roads , care shall be taken so that the
soil filled up after laying the pipes is rammed well in layers with watering as
required to ensure proper compaction. A crown of earth not exceeding 10 cm
should be left at the top.
iv. The temporary reinstatements of roadways should be inspected at regular
intervals, particularly after a rain, and any settlement should be made good by
further filling as may be required.
v. After the subsidence has ceased, the top of the filled up trenches in roadways
or other paved areas shall be restored to the same density and material as the
surrounding area in accordance with the relevant CPWD building specifications
to the satisfaction of the Engineer-in-Charge.
vi. Manholes shall be provided to facilitate feeding/drawing in of the cables with
sufficient working space for the purpose. They shall be covered by suitable
manhole covers.

b). Cable entry into the building


Pipes for cable entries to the building shall slope downwards from the building. The
pipes at the building end shall be suitably sealed to avoid entry of water after the
cables are laid. Cable-grip/draw wires/winches etc. may be employed for drawing
cables through pipes.

c) Cables for Main distribution boards

Cables used for connection between feeder pillar to Main distribution boards shall be
XLPE Insulated, PVC sheathed conforming to IS: 7098 (Part-1) 1988. The Cables

Page 160 of 177


Signature of Tenderer
shall be having stranded aluminium conductor. All multicore cables shall have GI
strip/wire armour as specified for the work.

Testing

a) Testing before laying :- All cables, before laying shall be tested with a 500V
Megger for cables of 1.1kV grade. The cable cores shall be tested for continuity,
absence of cross phasing, insulation resistance from conductors to earth/armour and
between conductors.
b) Testing before backfilling: All cables shall be tested with tests as above before
coveringthe cables by protective covering and backfilling.
c) Testing after laying: After laying and jointing, the cable shall be subjected to a 15
minutes 2kV pressure test. DC pressure testing shall be preferred over AC testing.

In the absence of facilities for pressure testing as above, it is sufficient to test for one
minute with 1000V Megger for cables of 1.1kV grade.

ITEM NO NS- 4 OF BOQ


33kV Heat Shrinkable Outdoor End Termination,33kV Heat Shrinkable Straight
Through Joints and 33kV Heat Shrinkable Indoor End Termination.

Heat Shrinkable End Terminations/ Straight Through Joints for 33kV 3Cx120 sqmm cable
shall conform to IEEE-48, VDE0278 & IS: 13573. End Terminations and Straight A.C. Dry
withstand voltage of 75kV for 1 Min. Impulse voltage withstand capacity shall be 170kV for
10 shots. Corona Extinction voltage shall be more than 38kV. End Terminations/ Straight
Through Joints shall consist of following components:

- Terminal connector

- Conductor

- Lug Sealing Tape

- Terminal sleeve

- Anti Tracking sleeve

- Rain Shed

- Stress control sleeve

- Adhesive lined trifurcating breakout

- Worm drive clamp

- Stress control paint

- Tinned copper wire

- Armour bonding braid

ITEM NO NS- 5 OF BOQ


This shall be provided as per detail given in BOQ.

ITEM NO NS- 6 OF BOQ


SANDWICH TYPE COPPER BUS TRUNKING:

1. Scope:
This specification covers the Supply, Installation, Testing and commissioning of 3
phase 4 wire ,Copper Sandwich Feeder Bus Trunking System suitable for operation
at 433V, 50Hz, from 3 Nos 1500 KVA Transformer LT Termination box to Main LT

Page 161 of 177


Signature of Tenderer
Panel. The Contractor to prepare G.A. Drawing of substation showing all equipment
as per the actual dimensions of manufacture & get approved from NR. Necessary
steel structure for mounting of the Bus trunking shall be fabricated and installed by
the Contractor. In case the supervision of manufacturer’s Engineer is required at site,
the same shall be arranged by the contractor at no extra cost to Northern Railway.

2. General Construction:

a. Feeder Bus Trunking:

Bus bar Trunking shall be of sandwich type construction. It shall be 3 Phase with
100% Neutral and 50% PE conductor enclosed in all aluminum housing. Bus bar
Trunking shall be rated for operational voltage of 690V with insulation voltage of
1000V and shall be suitable for 50/60Hz frequency. The Bus trunking are to be
manufactured as per the site requirement. The General Arrangement drawing of the
trunking route showing plan and elevation shall be got approved from Northern
Railway by the contractor. The Bus Trunking shall be IP-65 in construction suitable for
outdoor application, The End flange, and Flexible bus-bar for connection into
Transformer LT Termination Box and Main LT Panel vertical and horizontal bends.
The bus bar trunking housing shall be constructed of extruded aluminum on all the
sides to reduce hysteresis and eddy current losses and shall be provided with a
suitable protective finish of epoxy powder coated RL 7032 Housing shall be light in
weight for ease of installation and maintenance. Color indication of RYBN should be
there on the housing for phase sequence identifications. The bus bar trunking
housing shall be totally enclosed non ventilated, extruded aluminium for protection
against mechanical damage and dust accumulation. Housing shall be non corrosive
and shall be able to withstand 1000 hours of salt spray test.

b. Copper Sandwich Feeder bus trunking

Bus bar conductors shall be high conductivity copper (with 99.95% conductivity). Bus
bar conductors shall be tin plated copper throughout the length. Each bus bar shall be
insulated with two layers of Class B rated 130ºC Insulation, providing significant
insulation level and resistance impact. The temperature rise at any point in the bus
bar trunking shall not exceed 55 º C rises above ambient temperature when operating
at rated load current. Internal neutral conductor shall be 100%, which can meet with
the requirements of various power systems for eliminating harmonic effects in the
installations where non-linear loads are present. The bus bar trunking joint shall be of
the on-bolt type which utilizes a high strength steel bolt(s) and Belleville washers to
maintain proper pressure over a large contact surface area. The bolt shall be torque
indicating and at earth potential. Each joint shall also have a colour coded thermal
indicator for indicating the rise in temperature over and above ambient by changing
colour at 60 degree centigrade to BLACK/GREEN/RED of that particular length,
enabling clear visual inspection, without the use of any tools. The voltage drop (input
voltage minus output voltage) specified shall be based on the bus bar trunking
operating at full rated current and at stabilized operating temperature. The copper bus
conductor shall be encased in light weight, rust free, metallic enclosure, having high
conductivity/low resistivity for ground path and also working as a good medium for
heat dissipation. The copper bus bars inside the encasing shall be tin plated and
wrapped in B class insulating material thus limiting the temp rise to 130Deg C. Short
time withstand rating for 1second of the Bus Trunking shall be 65kA. Bus Trunking
shall generally conform to following standards: IEC 60439-1,2004, 60439-2 & IEC
60529.

Page 162 of 177


Signature of Tenderer
ITEM NO. NS-7
Specification for water-cooled Diesel Engine Driven Alternating Current Silent Type
Generating set ( 1500 KVA) with Acoustic Enclosure: .

1. SCOPE
This specification covers, design, manufacture, supply, installation, testing and
commissioning of 1500 KVA capacity Silent DG Set complete with diesel engine,
conforming to IS:10000, ISO 3046 or DIN 6271 Rating 1or latest, copper wound alternator
conforming to BS: 2613/IS:4722 capable of delivering continuously power out put at 3
Phase 4 wire 415 Volts AC supply, The generating set shall be complete with accessories,
auxiliaries and AMF control panel etc. The DG set to be placed on DG set foundation in
enclosure outside the Sub Station Building as shown in the Equipment layout drawing of
Sub Station Any equipment not specifically mentioned herein but essential for
completeness of the equipment may also be supplied.

The set shall be working as single unit for catering to mixed load comprising electrical
power and for charging battery, average power factor of load being 0.8 lagging. The set
should be suitable for operation at the following site conditions.

2. SITE CONDITION

Height above mean sea level not exceeding ---- 1600 meters

Maximum ambient temperature ----- 50 degree C

Minimum ambient temperature --- -5 degree C

Relative humidity ---- 95%

3. RATED POWER OUTPUT

The Diesel Generating Set shall be capable for delivering continuously (0n 24 hours basis)
power output at 1500 rpm at site conditions specified under clause 2 of this specifications
and the engine shall confirm to IS:10000, ISO :3046 or DIN 6271 Rating 1 or latest..

The output available from diesel engine under site condition should be specified. The diesel
engine shall be capable for working on 10% over load for 1 hour in any 12 hours running.

4. OIL ENGINE

The diesel engine shall be cold starting vertical direction injection 4 stroke cycle 6 cylinder
model, water cooled (through heat exchanger/radiator), electric battery start, directly
coupled to the alternator on a combination base plate through a flexible coupling.

A suitable extension pipe shall be used with exhaust air chest so that the silencer can be
mounted.

A fuel tank for storing the fuel oil with the capacity corresponding 10 to 12 hours
consumption of the D.G. set shall be provided. The piping as required shall be design as to
be free from leakage and air locks. The fuel tank shall be supplied with a level gauge to
indicate the oil level in the tank. Exhaust Pipe to be extended by the contractor, as required
at site. The rates shall include cost of any exhaust piping required to lead the exhaust
fumes of engine outside the enclosure.

The engine shall be required to operate on Diesel Fuel Oil grade “A” to IS:1460. Governor
the engine shall be supplied with Governor to maintain the engine speed at varying load
within +3% of the rated speed. The engine shall be complete with standard accessories and
protective devices including the following:-

1. Heavy Duty Air Cleaner.

Page 163 of 177


Signature of Tenderer
2. Radiator.
3. Fan for Radiator (in case of radiator).
4. Lubricating Oil Filters.
5. Fuel Oil filters.
6. Fuel injection equipment with governor to control the engine speed upto +3% under
varying load.
7. Engine speed control unit.( Manually Operated).
8. Sump.
9. Thermostat.
10. Safety control against low Lube oil pressure, high cooling water temperature and
engine over speed.
11. Flywheel to suit flexible coupling.
12. Exhaust silencer.
13. Lube oil cooler and water pump.
14. Fuel tank made of 14SWG sheet with marking of 50lts on clear transparent glass
guage.
15. Corrosion register.
16. Self starter for electric start system with Battery of adequate capacity with battery
charging alternator. ( 24V for AMF set).
17. Engine control panel comprising of:
Oil pressure guage

Water temperature guage

Ammeter

Hour meter with RPM indicator

Push buttons for starter/key switch starter

Pilot Lamp

Failure Indicator

Battery charging indication

Magnetic pick up fall indication

HWT trip indication

LLOP trip indication

O/S Trip indication

18. Tool kit complete (as supplied by engine and alternator manufacturers).
19. One set of foundation bolts with nuts.
20. O&M Manual of diesel engine.
21. Spare parts Catalogue of Diesel Engine.
22. Test Certificates

5. ALTERNATOR

The 1500 KVA Alternator shall be exciting brush less, copper wound, self regulating with
Screen Protected enclosure suitable for feeding 415V,3phase, 4 Wire, 50Hz AC system
with neutral point brought out. The alternator shall conform to BS:- 2613/IS: 4722 and
winding shall conform to class -B insulation. Voltage regulation shall be +/-5% of the
voltage under varying load. Permissible overload shall be of 10% for one hour in12hours
operation. The alternators have permanent lubricated, sealed bearing.

Page 164 of 177


Signature of Tenderer
6. AUTOMATIC ON MAIN FAILURE CONTROL PANEL FOR 1500KVA SILENT DG
SET

A. GENERAL
Auto main failure unit shall be capable of starting the Diesel Generating set in the event
of main power supply failure or low voltage below the specified value.

The DG set shall start automatically on full load current within 10 seconds of the supply
failure and on restoration of the main supply shall stop within 3 minutes after the
changeover of supply has taken place in Main LT Panel. The control cables required for
the wiring between DG set and AMF Panel shall be in the contractor’s scope of work
under schedule of rates.

B. CONSTRUCTION FEATURES

The AMF Panel shall be totally enclosed made of mild steel of at least 14/16 SWG
CRCA sheet, free standing floor mounted type and totally enclosed type. The cubical
shall have proper powder coating of 40 microns of approved colour to give long lasting
finish. Wiring circuit diagram of the AMF panel should be affixed inside the cubical so
that when front hinged panel is removed it is clearly visible. All the switchgears, control
devices, push buttons, indication lamps should be clearly labeled to indicate their
operation. The wiring connection in the control panel shall be ferruled.

C. PROTECTION AND CONTROL EQUIPMENTS

The following control device and equipments shall be suitably housed in the cubical.

a. Suitably a sealed flush mounted type digital A.C. Voltmeter–One No.


b. Selector Switch for Voltmeter for OFF/RB/YB/RY reading and with provision for
selection of DG set voltage measurement as the case may be – One No.
c. Suitably sealed flush mounted digital A.C. Ammeter Scaled with current transformer
of suitable ratio. – One No.
d. Selector Switch for ammeter OFF/R/B/Y reading – One No.
e. Digital frequency meter reed type – 1No.
f. Mode selector switch for OFF/AUTO/MANUAL/TEST – 1 Set.
g. Push button for start/stop/acknowledge/reset – 1 Set
h. A set of indication lamps for the following purpose – 1Set
Load on Mains

Load on Dg set

DG set fails to start

Low lube oil pressure

High coolant temperature

i. Battery charger consisting of


Transformer

Rectifier

DC Voltmeter

AC Voltmeter

Charging rate selector switch for trickle / booster charging

Pilot lamp to indicate that the charger is working

Page 165 of 177


Signature of Tenderer
On/off switch

j. Main supply voltage monitor – 1No.


k. DG control relays & timer for start/stop/three attempt starting facilities and failure to
start and lock.
l. Audio Alarm, hooter in case of low lub oil pressure, high coolant temperature, DG
set fails to start- 1 No
m. Earth fault relays to cut of the field supply of the alternator.
n. Copper Bus bar of rating 3000Amps for phase and 1500amps for neutral on the
basis of 1000amp/sq.inch.
o. 2500 Amps 4 pole EDO ACB Ics = Icu = Icw = 55kA with microprocessor release–
1No.

The Tenderer will submit the detailed drawing/circuit diagram of AMF Panel indicating
therein size of the cubical prior to manufacturing.

D. ARRANGEMENT
The engine shall be directly coupled to the alternator through flexible coupling and both the
units including the radiator/heat exchanger shall be mounted on a rigid fabricated bed plate.

The plant/equipment shall conform to relevant IS in addition to the following:

Indian Electricity Act 2003 & rules framed there under.

BS 5514/IS:10000 IC Engine

IS 4722 Electrical performance of rotating electrical machines

BS 1271- Classification of insulating materials

IS:722-KWHr. Meter/kWH Meter (accuracy class-1.0)

IS:13947 Air circuit breaker

IS:1248 – Ammeter, Voltmeter (accuracy class 1.0)

E. TESTS
The generating sets shall be tested at the makers works by nominated representative for
NR for:

i) Guaranteed fuel consumption

ii) Overload capacity

iii) Proper operating of protective devices provided for safety of the generating set and AMF
panel.

F. INSTRUCTION MANUALS AND CATALOGUES


Triplicate copies of operator’s guide, manuals, and maintenance schedules, repair
Overhaul instructions the complete equipment shall be supplied by the contractor)

G. ACOUSTIC ENCLOSURE
 The acoustic enclosure shall be mad of 14/6 SWG CRCA sheet.
 The Enclosure shall be made of modular construction with the provision to
assemble and dismantle easily at site.
 The sheet metal components shall be hot dip pre treated before powder coating.
 The enclosure shall be powder coated (inside as well as outside) with a special pure
polyester base powder. All nut and bolts/external hardware shall be made from
stainless steel.

Page 166 of 177


Signature of Tenderer
 The doors shall be gasketed with high quality EPDN gaskets to prevent leakage of
sound.
 Noise level should not be more than 75db (A) at 1 meter distance.
 Temperature of enclosure shall not exceed beyond 7deg C of ambient temperature.
 The door handles shall be lockable type
 Sound proofing of the enclosure shall be done with high quality rock wool/mineral
wool conforming to IS: 8183. The rock wool shall be further covered with fiber glass
tissue and perforated sheet.
 A special residential silencer shall be provided within the enclosure to reduce
exhaust noise.
 Specially designed attenuators shall be provided to control sound at air entry and
exit points.
 Adequate ventilation shall be provided to meet total air requirement.
 There shall be provision of emergency shut down from outside the enclosure.

Note: The Acoustic enclosure should be CPCB approved.

ITEM NO. NS-8 .


630SQ .MM LT XLPE CABLE

1. SCOPE

This specification covers, Supplying, laying, testing and commissioning of LT U/G cable
1X630 Sq.mm XLPE insulated, PVC sheathed 1100 Volt grade armoured aluminium
conductor cable in the trench 0.8 Mts deep with supply and laying of GI wire 8 SWG along
the entire length of cable including supply and providing bed of soft sand 75 mm below the
cable and 75 mm .

i. Supply of Cross linked polyethylene (XLPE) insulated PVC outer sheathed


armoured cables with aluminium conductor suitable for rated voltage of 1100 Volts
grade conforming to IS 7098/Pt.I/88 (latest version).

ii. The cable shall be laid in conformity to IS 1255/1984 (Latest Version) from L.T.
Switch board to AMF control panel, AMF control panel to DG set & L.T. Switch
board. The Tenderer will submit the detailed drawing of Connection.

(Item No. NS- 9 of BOQ)

TECHNICAL SPECIFICATION of 17 Panel LT Switch Board:

1. SCOPE
This specification covers design, manufacture, testing, supply, installation and
commissioning of 17 Panel LT Switch Board of low voltage switchgear panels suitable to
operate on 433volts, 50 cycles, and three phases 4-wire system comprising with :(i)
Incoming ACB 2500 A, 4 pole with micro processor release (MDO type) (minimum 65KA
B/C) (lcs = lcu = lcw) - 03. Nos. (ii) Bus Coupler 2500A ACB 4 Pole fixed type manually
operated (Without CTs & PTs)-2Nos (iii) O/G 400A 4 Pole MCCB Pole 35 KA B/C = 4 Nos
(iv) O/G 250A 4 Pole MCCB Pole 35 KA B/C = 4 Nos (v) O/G 125A 4 Pole MCCB Pole 25
KA B/C = 2 No to be provided with LT system in sub-station at budgam .

2. ENVIRONMENTAL CONDITIONS:

The equipment shall be suitable for the following environmental sub-zero temperature
weather conditions in J & K state, as given below:

Page 167 of 177


Signature of Tenderer
i) Max Altitude above 1600 MSL

ii) Temperature (-) 10˚C to 35ºC

iii) Humidity 100%

iv) Installation de-rating factor 8% for high altitude.

SPECIFICATION FOR LV SWITCHGEARS/ACCESSORIES:

3. (i) Air circuit Breaker:

Air Circuit Breaker shall be with Microprocessor adjustable overload release with
communication port. Current Breaking Capacity (Ics = Icw) of ACB shall be 55KAmps shall
be suitable to operate on 433V 50Hz, 3-phase supply. The breaker shall be continuously
rated for specified current ratings to operate at a height of 1600m above MSL. ACB shall be
electrically operated and draw out type in construction as specified in schedule of rates.
ACB shall meet necessary specification as per IS:13947-2. ACB shall be suitable to protect
against Overhead, short circuit and Earth faults. ACB of Northern Railway approved make
shall be used. For LT panel in SS-03, the Air Circuit Breaker size shall be limited to 450mm
width and accordingly the width of the one ACB compartment in the Main LT panel shall not
exceed 550mm.

(ii)MODULDED CASE CIRCUIT BREAKER:


MCCB shall be current limiting and comprise of quick break switching mechanism,
insulated moulded case with high withstand capacity against thermal and mechanical
stress. MCCB shall employ maintenance free contact system to minimize the let through
energy. MCCB should be meeting necessary standards as per IS: 13947-2/IEC947-2 of
IEC 60947. All these MCCB shall be provided with Static/Electronic releases wherever
mentioned in the bill of quantities, rated operational voltages upto 433 volt and insulation
voltages to be 1000 volts. Suitable current rating and Breaking Capacities as specified in
Schedule/BOQ (All mentioned Breaking Capacities are service Breaking Capacities lcs). All
MCCBs shall be with Adjustable Overload setting. MCCB of Northern Railway approved
make shall be used.

ON LOAD CHANGEOVER:

The challenger shall be of digital type suitable for mounting in LV panel. The changeover
shall have high mechanical life and shall provision for padlocking and shall confirm to IS:
13947-3. This shall be of approved makes.

METERS:

Meters shall be of Digital type suitable for measurement of voltage, Amperes, Frequency,
Power factor. Suitable to operate on current range of 0-5 Amps and voltage of 230V AC.
Indicators shall be of LED type suitable to operate button shall be of approved makes.

SPECIFICATION FOR LT PANEL (CUBICAL):

DESIGN & CONSTRUCTION:

The cubical distribution would be fabricated from specially selected smooth finished 2mm
Thick CRCA sheet. The design of this panel would be arranged free standing type on floor
dust & vermin proof. This would have sufficient structural reinforcement to provide rigidly
during transportation and installation etc and also ensure a flat level surface. The opening
of doors would be locked by threaded knobs. The LT panel shall of IP 52 Construction with

Page 168 of 177


Signature of Tenderer
necessary space heaters and provision for light to be given in the panels. Accessories to be
used in the panel builder shall have got CPRI type certificate for temporize test for panel.

SURFACES:

The panel would be duly phospatised and powder coated. All the Corners shall be properly
grinded to give round corners.

PANEL WIRING:

The panel wiring would be carried out with single core, super flexible colored PVC
insulation of 660 volts grade copper wire as per IS: 694/1997 the standard size of wire
should be 2.5 sq mm. for CT circuit 1.5 sq mm. For PT and other circuits, wire should be
terminated with Dowell’s solders less coppers ring lounge /fork cable lugs. The size of cable
lugs should be suited to the size of the wire terminated. Cable lugs would be provided with
insulated sleeves to reduce the possibility of short circuits. The panel wire would be
bunched together and bound to wiring strips provided inside the panel. Should be neatly
arranged and connected to equipments terminal and terminal block with easy accessibility.
Control wiring shall be suitably rated MCBs of minimum breaking capacity of 10KA wiring
shall be of approved makes of cables.

CABLE & CABLE GLANDS:

The panel boards should be suitable for cable entry (PVC sheathed cable of 1.1 KV
minimum conductors) from bottom would be provided in the base frame to make the entry
dust flight. Detachable gland plate of sufficient thickness should be provided on the top of
the base fixing the cables. Cable glands shall of Dowell’s/Comet makes.

BUS BARS:

The bus bars shall be Aluminum and shall be suitable for carrying the rated current
continuously. The bus bar chamber should be so designed to allow easy interchange ability
of switch gear etc. All bus PBC colour coded sleeves/PVC non adhesive taps. The bus bars
would be supported by non-hygroscopic insulation material with high bus bars coupling
insulators used for connecting up the bus bar of the adjacent section of bus bar are of
bolted type.

APPROVED MAKES:

All the switch gear items, accessories, induction lights and instrumentation, wires, etc shall
be used from approved makes of CEE/NR list of December, 2007. Any deviation, if
required, prior approval shall be obtained from CEE/USBRL Project, Northern Railway.

DESIGN & DRAWINGS:

All manufacturer/supplier will submit the detail design calculations and Engineering drawing
for approval of Northern Railway before taking up the manufacturer of the panels, with
wiring diagram and layouts. Manufacturer of the LT panel shall be approved by Northern
Railways.

MAKE OF EQUIPMENTS/INSTRUMENTS:

All the equipments used for projection panels shall be fire retardant including wiring etc.
The switch gear/instruments shall be used from the approved make list of CEE, Northern
Railway. Whenever these equipments/instruments are not appearing in approved list, the
same shall be got approved in advance from Northern Railway.

INSPECTION:

Page 169 of 177


Signature of Tenderer
All the major equipments shall be inspected by the representative of Northern Railway at
the premises of the manufacturer or these may be got inspected by RITES.

WARRANTY:

The equipments system shall be guaranteed against manufacturing defects and for its
smooth functioning for a period of minimum 2 years from date of supply and 18 months
from date of commissioning whichever is earlier.

INSTALLATION:

It will be the responsibility of the manufacturer/supplier to install the equipments in


Engineering manner with minimum modifications/repairs in close coordination with other
Engineering counters shall be tested minimum for 24 hours for all functional requirements
at site after installation and commissioning.

NOTE:

i) All Incoming and Outgoing MCCB provided as per detail given in BOQ.
ii) All Incoming and Outgoing cable should be suitably earthed with cable
glands.
General arrangement and wiring drawings shall be got approved by the
successful tenderer before manufacturing the board.

ITEM NO. NS-10


AUTOMATIC POWER FACTOR CONTROL PANEL AT Budgam SUBSTATION NO.2.
WITH MAIN LT PANEL
1. Scope: Design, manufacture, supply, erection, testing and commissioning of 200 KVAR
3 phase capacitor bank automatic control panel to be provided with LT system in sub-
station at Budgam.
2. General construction: The control panel shall be totally enclosed made of mild steel
sheet of size 14 SWG, free standing floor mounting type weather proof with degree of
protection IP-42. The Panel shall be compartmentalized fixed type, manufacture as per
IS-8623 Pt-I & II -1993 (Latest Version) & powder coated with approved colour of
thickness not less than 40 microns. The panel shall be capable of operation on 3 phase
4 wire 415V 50 Hz AC supply system 200KVAR capacity bank conforming to IS-13925
Pt-I & II 11998 (Latest Version) with automatic/manually switching arrangement for 10
steps power factor correction to achieve power factor between 0.8 to 0.95 lagging. The
capacitor bank shall be complete with inter-connection & a continuous aluminium earth
bus bar shall run at bottom and comprising of the following:
1. Incoming 400 A. MCCB 4 Pole 50KA breaking capacity shall have thermo-magnetic
type release with adjustable protection for over load and short circuit and conforming
to IS 13947/Pt.II/1993 (Latest Version). Rated short circuit breaking capacity (Ics=
Icu) should not be less than 35 KA rms at 415 Volt 50 Hz AC. The MCCBs shall have
spreader links and barriers as standard feature of manufacturer.

2. Microprocessor based Automatic Power Factor Control Relay 10 steps with display of
Electrical Parameter i.e. power factor, current, voltage, etc. with following
specifications.

a. 415V 50Hz
b. Capacity 5 Amps
c. Intelligent type
d. Built in Automatic and manual control
e. Low current cut out relay,
f .Relay should function even at low loads.

Page 170 of 177


Signature of Tenderer
g. It should have data logging facility and sufficient memory back up to log the data for
30 days or above.

3. Indicating Lamp with suitable back up protection in incoming.

4. On/ Off indication lights for each set of capacitor

5. Configuration of Capacitor output steps 6 x 25 KVA R, 4 x 10 KVAR & 2 x 5 KVAR.

6. Knife type HRC fuses with base of suitable capacity should be provided for backup
Protection of capacitor duty contactor for each Capacitor Bank.
7. 3 Pole capacitor duty contactors suitable as required.

8. Capacitors 415V 50 Hz conform to IS 13340/1993, IS 13341/1992 & IEC 60831- 1+2.


The Capacitor should be of Siemens EPCOS make Phi cap capacitor/L&T make MD-
XL/ABB make CLMD type. The capacitor should be low loss type (Total watt-losses
including discharge resistors: ≤ 0.5 W/kVAr). Temperature category : -25º C to 70º C.

9. TPN Copper bus bar of 400A capacity fitted on insulators and PVC sleeves colour
coded provided.

10. Suitable size cooling fan.

11. Inter connection of capacitor duty contactors to bus bars has to be done with suitable
size PVC copper conductor cable of 1.1 KV grade with suitable lugs. For control
wiring of relay, meters, equipments and indicating light etc. has to be done with lugs
wherever required. Inter connection from 630 A. MCCB has to be made with suitable
size copper bus bars as required. If any other item is required to complete the work
that shall be supplied within quoted rates only.

12. LT summation current transformer (CT) conforming to IS 2705/Part/I to IV as


applicable suitable for CTR 400/5A. of both incoming feeder complete with four
terminal at input side and two terminal at output side. Connection from incoming CTs
to summation CT and APFC Relay should be carried out with suitable size copper
conductor cable with proper wiring arrangement.

NOTE: General arrangement and wiring drawings shall be got approved by the
successful tenderer before manufacturing the board.

ITEM NO. NS-11,12, 13 and 14)

a) Cubicle type, LT outdoor feeder pillar shall conform to IS 8623/1993/Part I to III


(Latest Version) with degree of protection not less than IP 54. Board shall be
complete in all respects including interconnection with suitable size copper
conductor cable, copper lugs , cable glands, earthing terminals etc. A danger notice
board will be provided on front of cover conforming to IS 2551/1982 (Latest
Version).
b) The MCCB shall be complete with thermal magnetic release with adjustable over
load & short circuit protection of Suitable Breaking Capacity and conforming to IS
13947/Pt.II (Latest Version) and MCB shall be 10 KA Breaking Capacity ’C’ Series
and conforming to IS 8828/1996 (Latest Version).
c) Installation of distribution board shall be conformed to IS 732/1989 (Latest Version),
4648/1968 (Latest Version).
d) The distribution board shall be cubical type metal clad, wall mounted/pillar mounted,
dust and vermin proof of uniform height and multitier construction so as to occupy
minimum area.

Page 171 of 177


Signature of Tenderer
e) The distribution board shall be manufactured with 2mm thick CRCA sheet. Bus bars
should be of high conductivity electrolytic copper/ aluminum suitable for electrical
purpose and of uniform cross section (Basis for bus bar size = 1000 Amps. /Sq.
inch). LT panel board shall be powder coated of approved colour thickness not less
than 40 microns.
f) The work also include fixing the complete distribution board in concealed/erection
on pillar with Suitable Size MS flat/ Chanel/ Angle as reqd at site . The tenderer
shall have to cut the wall and also make good the wall after installation of board
where ever reqd .

NOTE:
iii) All Incoming and Outgoing MCCB provided as per detail given in BOQ.
iv) All Incoming and Outgoing cable should be suitably earthed with
cable glands.
General arrangement and wiring drawings shall be got approved by the
successful tenderer before manufacturing the board

ITEM NO. NS-15

MAINTENANCE FREE EARTHING.


This item shall be in conformity to as per RDSO specification No.
RDSO/PE/SPEC/PS/0109, REV "0" 2008/ Latest Amendment. Excavation shall be done
complying with Code of Safety as per IS 3764/1992.

ITEM NO. NS-16

40X6 MM COPPER STRIP

This item shall be in conformity to IS 3043/1987 (Latest Version). Excavation shall be done
complying with Code of Safety as per IS 3764/1992.

ITEM NO. NS -17

G.I. PLATE EARTHING

This item shall be in conformity to IS 3043/1987 (Latest Version). Excavation shall be done
complying with Code of Safety as per IS 3764/1992.

ITEM NO.NS-18
Connection with GI strip 300mm deep

This item shall be in conformity to IS 3043/1987 (Latest Version). Excavation shall be done
complying with Code of Safety as per IS 3764/1992.

Item No. NS-19

GI wire 8 SWG.

This item shall be in conformity to IS 5613/Pt.I sec. 1& 2/1985 (Latest Version), GI wire
shall conform to relevant IS.

Item No.NS- 20.


Heavy duty PVC conduit pipe 25 mm dia

Laying of conduit shall be in conformity to the IS 732/1989 (Latest version), IS


4648/1968(Latest version) Fittings for PVC conduit for electrical wiring shall conform to

Page 172 of 177


Signature of Tenderer
IS 2667/1988 (Latest version) & accessories shall conform to IS 3837/1976 (Latest
Version).
ITEM NO. NS-21 & 22

VARIOUS SIZES FRLS PVC INSULATED COPPER CONDUCTOR WIRING CABLES

Fire Retardant Low Smoke (FRLS) PVC insulated multi stranded unsheathed copper
conductor wiring cable for working voltage up to & including 1100 Volts, ISI marked
conforming to IS 694/1990 (Latest Version).Wiring of installations shall be in conformity with
IS 732/1989 (Latest Version), IS 4648/1968 (Latest Version)

ITEM NO. NS- 23

As per detail given in BOQ and as per CEE/NR specification No. CEE/NR/21-
Elect./PS/2017 dated 06.01.2017 or latest. Fitting shall be got approved before supply.

ITEM NO. NS- 24

As per detail given in BOQ Fitting shall be got approved before supply.

ITEM NO. NS- 25

As per detail given in BOQ and as per CEE/NR Specification No. CEE/NR/121-
Elect./PS/2017 (Rev.-1) dated 25.09.2017 and Eligibility criteria No. CEE/NR./PS/EC/LED/1
(Rev.-2) date 26.09.2017 or latest. Fitting shall be got approved before supply.

Page 173 of 177


Signature of Tenderer
Special Data, Drawings Section –III

Page 174 of 177


Signature of Tenderer
Detail Drawing of cable Trench

Page 175 of 177


Signature of Tenderer
Alternative Proposal of the Tenderer (Deviations) Section –IV

Page 176 of 177


Signature of Tenderer
END OF TENDER DOCUMENT

Page 177 of 177


Signature of Tenderer

You might also like