Professional Documents
Culture Documents
1.0 PURPOSE
2.0 SCOPE
The scope of works covers under this procedure applies to the fabrication
and installation of gratings and miscellaneous structural steel section
required to complete installation of pipe-racks for commercial buildings,
plants and refineries.
3.0 REFERENCES
5.0 PROCEDURE
General:
• Installation / Erection
5.1.13 Any Installation and Erection activity shall be in accordance with and
Saudi Aramco approved drawing.
5.1.14 Materials lifting activity shall be carried out by an approved Saudi
Aramco Rigger from Fabrication to Site to avoid damage to materials and
property. Lifting of painted structural members shall be done with a
nonabrasive choker.
5 .1.15 Evidence of materials quality inspection documentation such as
receiving inspection and fabrication approval drawing shall be available
prior to installation and erection for easy site references during installation
and erection.
5.1.17 Before any erection and installation work commencement, the erector
shall check foundations and other connection points to confirm their
location, orientation, elevation, and condition.
5 .1.18 Erection and Shop drawing shall be available during installation to
ensure that all parts, sizes, and fabricated materials is as per approved
drawing.
5.1.19 Any circumstances discovered by the erector that affect progression,
performance, or completion of the erector’s work activities such as
discrepancies between the erection/shop drawing and the delivered steel
members, incorrectly fabricated steel members, or incomplete or
unacceptable work of other contractors affecting the erector’s work shall be
immediately reported to JGC/DEC Engineering Department and SAUDI
ARAMCO for final disposition.
5.1.20 Any damage incurred caused during erection or installation shall be
reported for disposition. Corrective measures shall be completed as directed
by SAUDI ARAMCO.
5.1.21 Temporary erection loads or permanent loads during installation
shall not be place on any incomplete portions of the structure being erected
unless the erector can demonstrate by analysis that the contemplated action
is safe.
5.1.22 Loose timbers, metal sheeting, bolt buckles, tools, debris, and
temporary scaffolding shall be kept restrained or removed from work areas.
The erector shall be responsible for securing all equipment and materials
within the erector’s care, custody and control during the erection I
installation operation.
5.1.23 Before and After erection and installation activities is carried out, job
site shall maintain a clean and safe condition environment at all times and
shall dispose of, off the premises all crating, waste materials, and other
refuse that has accumulated as a result of the erector’s activities.
5.1.24 Lifting of painted structural members shall be done with nonabrasive
choker.
5.1.25 Erectors and installers shall verify the following crucial activities
prior to commencement of any erection and installation as per PIP
STS05130 standard as follows:
6.1 Quality Inspector shall ensure that all fabricated and installed, erected
structural steel forms shall be in compliance with approved design drawing,
standard and specification.
6.2 All inspection activities shall meet Saudi Aramco Inspection
requirement as per SATIP.
6.3 QC Inspector shall coordinate with construction installer, erector any
noncompliance found during inspection and shall ensure that corrective
action is taken with approval of JGC/DEC Engineering.
7.1 Safety requirements at site during field erection and installation shall be
strictly monitored and an implementation of complete PPE shall be strictly
observed.
7.2 Safety Barricades from the job site where installation and erection is on
progress shall be installed.
7.3 Ensure that work permits shall be available prior to any site installation,
erection commencement and that safety tool box meeting is conducted.
7.4 Ensure that Flagmen, whole watcher, riggers and operators shall have a
competency training certificates or certified in their own field of works prior
to start of any job site work activities.
7.5 Safety Officer shall have a close and strict monitoring implementation of
safety at site before and after work is carried out and a house keeping shall
be observe before and after work activities to avoid any accident or incident
cause of negligence.
8.0 ATTACHMENT