Aker Powergas Pvt Ltd Operating System Procedure Number G-INST-004.233-A-01 Control Object Check List for Ultrasonic Level Transmitter Sheet 1 of 6
Group Head-Instruments
Control Object Check List Checklist approved for use by:
Aker Powergas Pvt Ltd
for Ultrasonic Level Transmitter Issued date: 15.03.2011
1.17 Whether all revision marks on revised document and index are in place. X X
a General Standards X
b Norms X
c Contractual Requirements X
d Licensor documents X
1.20 Whether Site conditions are enclosed. X
Aker Powergas Pvt Ltd Operating System Procedure Number G-INST-004.233-A-01 Control Object Check List for Ultrasonic Level Transmitter Sheet 2 of 6
Group Head-Instruments
Control Object Check List Checklist approved for use by:
Aker Powergas Pvt Ltd
for Ultrasonic Level Transmitter Issued date: 15.03.2011
Whether the process fluid checked for corrosive nature & formation of
2.9 X
corrosive fumes and a 'process seal' type of sensor used for such cases.
Whether the correct measurement range & unit based on IPDS / Vessel
2.10 X X
datasheet/Vessel drawing/Instrument Level sketches is specified.
Aker Powergas Pvt Ltd Operating System Procedure Number G-INST-004.233-A-01 Control Object Check List for Ultrasonic Level Transmitter Sheet 3 of 6
Group Head-Instruments
Control Object Check List Checklist approved for use by:
Aker Powergas Pvt Ltd
for Ultrasonic Level Transmitter Issued date: 15.03.2011
Aker Powergas Pvt Ltd Operating System Procedure Number G-INST-004.233-A-01 Control Object Check List for Ultrasonic Level Transmitter Sheet 4 of 6
Group Head-Instruments
Control Object Check List Checklist approved for use by:
Aker Powergas Pvt Ltd
for Ultrasonic Level Transmitter Issued date: 15.03.2011
N.A.
3.4 Electrical
3.4.1 Whether power supply details are specified for 4 wire Instrument. X
3.5 Civil
N.A.
3.6 Vessels
For Instruments mounted on Vessel, check the
Whether checked with latest revision of vessel drawing / mechanical flange rating, facing, face finish & material,
3.6.1 X X Design Pressure, Temperature, Full vacuum
data sheet.
compatibility & any other relevant data.
Whether the mounting orientation based on Vessel drawing/ datasheet in
terms of Nozzle standout height, inner diameter and distance of Nozzle
3.6.2 X
centre line from vessel wall is checked to be suitable with Instrument
Installation requirements.
Whether the presence of heating coil / Agitator / Jet mixer / any other
3.6.3 X
obstacles in the vessel is included where applicable.
Whether the requirement of a still pipe is checked for vessels where
turbulence/agitation or where probable interference in path of ultrasonic
3.6.4 X
beam can occur. Indicate in remarks column the applicable tags with the
scope of supply of still pipe.
3.7 Mechanical
N.A.
3.8 Construction
N.A.
Aker Powergas Pvt Ltd Operating System Procedure Number G-INST-004.233-A-01 Control Object Check List for Ultrasonic Level Transmitter Sheet 5 of 6
Group Head-Instruments
Control Object Check List Checklist approved for use by:
Aker Powergas Pvt Ltd
for Ultrasonic Level Transmitter Issued date: 15.03.2011
Aker Powergas Pvt Ltd Operating System Procedure Number G-INST-004.233-A-01 Control Object Check List for Ultrasonic Level Transmitter Sheet 6 of 6