Installation of Potable Drinking Water Line System with Cooling-and-Heating Dispenser in
Different Areas in Technological University of the Philippines-Visayas
Work Breakdown Structure (WBS) I. Site Evaluation a. Investigation of campus geography/landscape b. determination of possible locations for tank, pumps, water lines and dispensers II. Designing of the Water Line System a. Design and Drawings III. Identifying Suppliers a. Canvassing of Items IV. Procurement a. Pipings, elbows, and fittings, i. Delivery and Inspection b. Dispensers, centrifugal pump, and water tank V. Installation a. Tank and pump installations b. Pipe, elbow, fittings, and dispenser installations VI. Testing and Modifications a. Pressure/head testing and leakage detection b. Water quality assessment (Temperature, pH, Turbidity, TDS, Coliform, etc.) VII. Operation Procedures a. Pump priming and Dispenser start-up VIII. Maintenance Procedures a. Monthly preventive maintenance i. Water analysis ii. Pump, tank, and piping maintenance