You are on page 1of 2

Assigned Plan Evaluator’s Signature DATE: TIME IN: TIME OUT:

PLUMBING

 1. Provide Site Development Plan  5. Provide / Comply to Application Documents


 2. Provide Plumbing / Sanitary Plans:  a. Secure Sanitary / Plumbing Permit with
 a. Water Supply Layout ( Hot & Cold, as required) signature and dry seal of professionals and
 b. Sewer / Soil Pipe Line Layout applicant.
 c. Drainage Layout  b. Clear Copy of Valid PRC ID and Updated PTR
 d. Storm Water Drainage Layout  c. Fill-out completely the Plumbing Permit
 e. Isometric Drawings of the systems Application Form (Check Marked)
 3. Plumbing / Sanitary Details  d. Provide Clearances from the National Water
 a. Area Drain / Catch Basin - must be watertight Resources Board (as required).
 b. Plumbing Fixtures Mounting & Connection Details  e. Secure ECC from DENR-EMB.
 c. Pipe Diameter & Specifications
 d. Septic Tank / Vault Details:  6. Reflect Septic Tank / Underground Tank on Foundation
 i. Provide 3-Chamber Septic Tank (Watertight) – Plan for Structural Evaluation since it is located under
as per GSC Septage Ordinance Parking Area / Driveway
 ii. Install Tee Inlet, Partitions and Outlet
 iii. Manhole minimum dimension: 508 mm x 508 mm  7. Provide Rain Water Collection Tank
 iv. Invert level of inlet pipe shall not be less than as per GSC Rainwater Ordinance
50.8mm than the invert of outlet.
 v. Digestive Chamber Min. L = 1500 mm, W = 900 mm  8. Provide Water Tank & Booster Pump for Uniform
 vi. Digestive Chamber shall not be less than 2/3 of Water Pressure and indicate capacity.
total tank capacity while Leaching Chamber shall not Submit installation detail (as required).
be less than 1/3 of total tank capacity.
 vii. Air Space = 230 mm minimum,  9. Cost Estimates and Specifications
Liquid Depth = 600 mm min – 1800 mm max  10. Settle Comments of Architectural re: _________.
 viii. Submit Septic Tank Design Basis / Calculation  11. Settle Comments of _______________________.
 ix. For Pre-fabricated Septic Tank - Submit Material  12. Provide General Notes, Legend.
Data Sheet (must be accredited by AITECH/DOST/DOH)  13. Submit Approved Building Permits and Plans.
 14. Other Details as deemed necessary (specify):
 4. Provide Water Treatment Prior Disposal: __________________________________________________
 a. Grease Trap / Oil & Water Separator __________________________________________________
 b. Waste Water Treatment Facility (WWTF) / STP __________________________________________________
& indicate sizes and dimension (as required) __________________________________________________
 i. Submit WWTF/STP Design Basis __________________________________________________
 i. WWTF / STP Process Flow __________________________________________________
__________________________________________________