This document provides an installation guide for Wavistrong pipe systems. It discusses positioning pipe components in the plant by lowering them into the trench manually or with equipment, depending on the size. It also covers joining the components by inspecting them, assembling mechanical joints in the trench, and not disturbing adhesive bonds during curing. Maintaining sufficient space around joints and the system's center in the trench is recommended.
This document provides an installation guide for Wavistrong pipe systems. It discusses positioning pipe components in the plant by lowering them into the trench manually or with equipment, depending on the size. It also covers joining the components by inspecting them, assembling mechanical joints in the trench, and not disturbing adhesive bonds during curing. Maintaining sufficient space around joints and the system's center in the trench is recommended.
This document provides an installation guide for Wavistrong pipe systems. It discusses positioning pipe components in the plant by lowering them into the trench manually or with equipment, depending on the size. It also covers joining the components by inspecting them, assembling mechanical joints in the trench, and not disturbing adhesive bonds during curing. Maintaining sufficient space around joints and the system's center in the trench is recommended.
6.2. System assembly • Standard pipe lengths may be doubled in order
to reduce the installation time. The assembly procedure of a piping system may vary per project. Generally, this procedure deals with positioning • Ensure sufficient space around joints for proper and joining of components in the plant. alignment and joining.
• Keep the system centred in the trench.
6.2.1. Positioning components in the plant
After positioning of the pipe system elements next to the
trench, these components have to be handled into final position in the trench.
• Small diameter pipe sections can be lowered
manually using ropes, slings or light lifting devices.
• Large diameter piping requires heavier
equipment during final positioning.
• To avoid damage the minimum bending radius
of a pipe shall be respected. Fig. 6.4. Assembly activities • Avoid unwanted objects falling into the trench during lowering pipe sections.
• Use nylon sling belts or special designed
equipment during product handling.
6.2.2. Joining of components
Respect next requirements and recommendations for
joining of underground pipe systems:
• Inspect all products before installation.
• Components with mechanical O-ring joints shall
be assembled in the trench.
• Adhesive bonded and laminated joints can be
assembled either inside or outside the trench.
• Never move or disturb a joint during the curing
process. Fig. 6.5. Assembly in the trench