Version Revision Code Nº Issued Page

1 1 EL009B 1-Jan-08 1/1 PROJECT

ADRS
CONTRACTING DIVISION UPS TEST REPORT
No 8b, Down Town Road 7,P.O.Box 28,
Phnom Penh, Kingdom of Cambodia PAGE

SYSTEM

SCHEDULE

SPECIFICATION

REF. DRWG

STATUS
No. DESIGNATION DATE
YES NO
A INSPECTION
1 Work Task Folder prepared.
2 Shop Drawings issued, approved and attached.
3 Materials/ Equipment approved and & record avail.
4 Technical schedules issued, approved & attached.
5 List of materials and tools available.
6 Safe Work Method Statement complete & avail.
7 Toolbox Meeting has been held for activity.
B TEST
Ph1/Ph2 Ph1/Ph3 Ph2/Ph3
V V V
1 Input Voltages (Mains 1)
Neutral/Ph1 Neutral/Ph2 Neutral/Ph3
V V V
2 Input Frequencys (Mains 1) Hz
Ph1/Ph2 Ph1/Ph3 Ph2/Ph3
V V V
3 Input Voltages (Mains 2)
Neutral/Ph1 Neutral/Ph2 Neutral/Ph3
V V V
4 Input Frequencys (Mains 2) Hz
Ph1/Ph2 Ph1/Ph3 Ph2/Ph3
V V V
5 Output Voltages (Inverter)
Neutral/Ph1 Neutral/Ph2 Neutral/Ph3
V V V
6 Output Frequencys (Inverter) Hz
7 Voltage (Battery) V
8 Back up Time Min

REMARK

READ BY: APPROVED BY: WITNESSED BY:

DATE: DATE: DATE: