Production Schedule

Write down a ‘shopping list’ of tasks, jobs, things to do, with a start date and a completion date:

Student Names: Joshua Morgan 10651924 Sheet

Production Title: The time walkers 0 of 0

DATE / LESSON: PRE / PROD / POST TASK TO BE COMPLETED BY? TO BE RESCHDULED?

To complete Script and precure props and


18/4/2023 Preproduction 20/4/2023
costumes. Scout locations.
Complete Location recce, contingency plan, call
19/4/2023 Preproduction 19/4/2023 28th April
sheet and risk assessment.

18/4/2023 Preproduction Recruit actors 28/4/2023

2/5/2023 production Film 80’s and lift scenes 2/5/2023

3/5/2023 production 1920’s scenes 3/5/2023

5/5/2023 Production Film 90’s scenes 5/5/2023

9/5/2023 Postproduction Editing the video 12/5/2023

10/5/2023 Postproduction Editing the video 12/5/2023

11/5/2023 Postproduction Editing the video

12/5/2023 Postproduction Complete the editing the video