Detail Progress Calculation Sheet for Construction

CV040 [Piperack Foundation]

WF(%) Step 1 Step 2 Step 3 Step 4 Step 5 Step 6


10% 20% 15% 20% 20% 15%
P/Rack Baseline Baseline Actual Actual Excavation and Lean Formworks Reinforcement Preparation Concrete Casting Stripping/Backfilling Final Check & QAQC Certi.
Activity ID Activity Description Q'ty Unit Progress Remarks
100.0% 27.63% Step 1 Step 2 Step 3 Step 4 Step 5 Step 6 Start Finish Start Finish Q'ty Q'ty Q'ty Q'ty Q'ty Q'ty
Start Finish % Start Finish % Start Finish % Start Finish % Start Finish % Start Finish %
10.0% 20.0% 15.0% 20.0% 20.0% 15.0% Total Done Total Done Total Done Total Done Total Done Total Done

Flare System (861-1) 0.0% 5,753 M3 8-Nov-22 23-Oct-23 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0%

IC861A1CV0402 Pipe Rack Foundation_861-PR-201_[861-1] 9.1% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 8-Nov-22 6-Feb-23 0.00% 0% 0% 0% 0% 0%

IC861A1CV0404 Pipe Rack Foundation_861-PR-202_[861-1] 9.1% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 26-Nov-22 23-Feb-23 0.00% 0% 0% 0% 0% 0%

IC861A1CV0406 Pipe Rack Foundation_861-PR-203_[861-1] 9.1% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 13-Dec-22 13-Mar-23 0.00% 0% 0% 0% 0% 0%

IC861A1CV0408 Pipe Rack Foundation_861-PR-204_[861-1] 9.1% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 31-Dec-22 9-Apr-23 0.00% 0% 0% 0% 0% 0%

IC861A1CV0410 Pipe Rack Foundation_861-PR-205_[861-1] 9.1% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 17-Jan-23 7-May-23 0.00% 0% 0% 0% 0% 0%

IC861A1CV0412 Pipe Rack Foundation_861-PR-206_[861-1] 9.1% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 4-Feb-23 4-Jun-23 0.00% 0% 0% 0% 0% 0%

IC861A1CV0414 Pipe Rack Foundation_861-PR-207_[861-1] 9.1% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 21-Feb-23 11-Jul-23 0.00% 0% 0% 0% 0% 0%

IC861A1CV0416 Pipe Rack Foundation_861-PR-208_[861-1] 9.1% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 11-Mar-23 15-Aug-23 0.00% 0% 0% 0% 0% 0%

IC861A1CV0418 Pipe Rack Foundation_861-PR-209_[861-1] 9.1% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 4-Apr-23 17-Sep-23 0.00% 0% 0% 0% 0% 0%

IC861A1CV0420 Pipe Rack Foundation_861-PR-210_[861-1] 9.1% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 4-May-23 5-Oct-23 0.00% 0% 0% 0% 0% 0%

IC861A1CV0422 Pipe Rack Foundation_861-PR-301_[861-1] 9.1% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 30-May-23 23-Oct-23

Interconnection System (861-2) 0.0% 11,517 M3 15-Oct-22 4-Jan-24

IC861A2CV0402 Pipe Rack Foundation_861-PR-001_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 15-Oct-22 12-Feb-23

IC861A2CV0404 Pipe Rack Foundation_861-PR-002_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 30-Oct-22 27-Feb-23

IC861A2CV0406 Pipe Rack Foundation_861-PR-003_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 14-Nov-22 14-Mar-23

IC861A2CV0408 Pipe Rack Foundation_861-PR-004_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 29-Nov-22 6-Apr-23

IC861A2CV0410 Pipe Rack Foundation_861-PR-008_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 14-Dec-22 3-May-23

IC861A2CV0412 Pipe Rack Foundation_861-PR-005_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 29-Dec-22 23-May-23

IC861A2CV0414 Pipe Rack Foundation_861-PR-006_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 14-Jan-23 22-Jun-23

IC861A2CV0416 Pipe Rack Foundation_861-PR-009_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 29-Jan-23 25-Jul-23

IC861A2CV0418 Pipe Rack Foundation_861-PR-007_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 13-Feb-23 24-Aug-23

IC861A2CV0420 Pipe Rack Foundation_862-PR-001_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 28-Feb-23 19-Sep-23

IC861A2CV0422 Pipe Rack Foundation_861-PR-101_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 15-Mar-23 5-Oct-23

IC861A2CV0424 Pipe Rack Foundation_861-PR-102_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 9-Apr-23 21-Oct-23

IC861A2CV0426 Pipe Rack Foundation_861-PR-103_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 4-May-23 5-Nov-23

IC861A2CV0428 Pipe Rack Foundation_861-PR-104_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 25-May-23 20-Nov-23

IC861A2CV0430 Pipe Rack Foundation_861-PR-105_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 698 M3 28-Feb-23 19-Sep-23

IC861A2CV0432 Pipe Rack Foundation_863-PR-003_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 785 M3 27-Jul-23 4-Jan-24

IC861A2CV0434 Pipe Rack Foundation_863-PR-003A_[861-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 262 M3 21-Nov-23 4-Jan-24

Utility - Water Systems (862-2) 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,046 M3 11-Apr-23 21-Dec-23 30-Dec-99 30-Dec-99 - - 0.00% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0%

IC862U2CV0402 Pipe Rack Foundation_862-PR-002_[862-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 11-Apr-23 20-Sep-23 0.00% 0% 0% 0% 0% 0%

IC862U2CV0404 Pipe Rack Foundation_862-PR-003_[862-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 21-Sep-23 21-Dec-23 0.00% 0% 0% 0% 0% 0%

Product Storage (863-1) 0.0% 1,204 M3 28-Mar-23 10-Jan-24 30-Dec-99 30-Dec-99 - - 0.00% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0%

IC863P1CV0402 Pipe Rack Foundation_863-PR-007A_[863-1] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 215 M3 28-Mar-23 25-May-23 0.00% 0% 0% 0% 0% 0%

IC863P1CV0404 Pipe Rack Foundation_863-PR-008_[863-1] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 363 M3 15-Aug-23 1-Nov-23 0.00% 0% 0% 0% 0% 0%

IC863P1CV0406 Pipe Rack Foundation_863-PR-005_[863-1] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 202 M3 2-Nov-23 6-Dec-23 0.00% 0% 0% 0% 0% 0%

IC863P1CV0502 Pipe Rack Foundation_863-PR-009_[863-1] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 202 M3 7-Dec-23 10-Jan-24 0.00% 0% 0% 0% 0% 0%

IC863P1CV0403 Pipe Rack Foundation_863-PR-007B_[863-1] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 222 M3 28-May-23 13-Aug-23 0.00% 0% 0% 0% 0% 0%

Propane System (863-2) 0.0% 523 M3 28-Mar-23 12-Sep-23 30-Dec-99 30-Dec-99 - - 0.00% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0%

IC863P2CV0402 Pipe Rack Foundation_863-PR-004_[863-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523 M3 28-Mar-23 12-Sep-23 0.00% 0% 0% 0% 0% 0%

Import / Export Facilities (863-3) 0.0% 719 M3 28-Mar-23 18-Oct-23 30-Dec-99 30-Dec-99 - - 0.00% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0%

IC863P3CV0402 Pipe Rack Foundation_863-PR-001_[863-3] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 195 M3 28-Mar-23 18-May-23 0.00% 0% 0% 0% 0% 0%

IC863P3CV0404 Pipe Rack Foundation_863-PR-001A_[863-3] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 175 M3 21-May-23 20-Jul-23 0.00% 0% 0% 0% 0% 0%

IC863P3CV0406 Pipe Rack Foundation_863-PR-006_[863-3] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 175 M3 23-Jul-23 17-Sep-23 0.00% 0% 0% 0% 0% 0%

IC863P3CV0408 Pipe Rack Foundation_863-PR-010_[863-3] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 174 M3 18-Sep-23 18-Oct-23 0.00% 0% 0% 0% 0% 0%

Sulfur Recovery & Tail Gas Unit (869-1) 0.0% 1,054 M3 28-Mar-23 17-Dec-23 30-Dec-99 30-Dec-99 - - 0.00% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0% 30-Dec-99 30-Dec-99 - - 0%

IC869S1CV0402 Pipe Rack Foundation_869-PR-101_[869-1] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 214 M3 28-Mar-23 25-May-23 0.00% 0% 0% 0% 0% 0%

IC869S1CV0404 Pipe Rack Foundation_869-PR-102_[869-1] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 140 M3 28-May-23 16-Jul-23 0.00% 0% 0% 0% 0% 0%

IC869S1CV0406 Pipe Rack Foundation_869-PR-103_[869-1] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 140 M3 18-Jul-23 3-Sep-23 0.00% 0% 0% 0% 0% 0%

IC869S1CV0408 Pipe Rack Foundation_869-PR-104_[869-1] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 140 M3 5-Sep-23 4-Oct-23 0.00% 0% 0% 0% 0% 0%

IC869S1CV0410 Pipe Rack Foundation_869-PR-105_[869-1] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 140 M3 5-Oct-23 29-Oct-23 0.00% 0% 0% 0% 0% 0%

IC869S1CV0412 Pipe Rack Foundation_869-PR-106_[869-1] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 140 M3 30-Oct-23 22-Nov-23 0.00% 0% 0% 0% 0% 0%

IC869S1CV0414 Pipe Rack Foundation_869-PR-107_[869-1] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 140 M3 23-Nov-23 17-Dec-23 0.00% 0% 0% 0% 0% 0%

Sulfur Recovery & Tail Gas Unit (869-2) 0.0% 1,120 M3 29-Apr-23 13-Jan-24

IC869S2CV0402 Pipe Rack Foundation_869-PR-201_[869-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 29-Apr-23 6-Jun-23 0.00% 0% 0% 0% 0% 0%

IC869S2CV0404 Pipe Rack Foundation_869-PR-202_[869-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 8-Jun-23 3-Aug-23 0.00% 0% 0% 0% 0% 0%

IC869S2CV0406 Pipe Rack Foundation_869-PR-203_[869-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 6-Aug-23 21-Sep-23 0.00% 0% 0% 0% 0% 0%

IC869S2CV0408 Pipe Rack Foundation_869-PR-204_[869-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 23-Sep-23 21-Oct-23 0.00% 0% 0% 0% 0% 0%

IC869S2CV0410 Pipe Rack Foundation_869-PR-205_[869-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 22-Oct-23 18-Nov-23 0.00% 0% 0% 0% 0% 0%

IC869S2CV0412 Pipe Rack Foundation_869-PR-206_[869-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 19-Nov-23 16-Dec-23 0.00% 0% 0% 0% 0% 0%

IC869S2CV0414 Pipe Rack Foundation_869-PR-207_[869-2] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 17-Dec-23 13-Jan-24 0.00% 0% 0% 0% 0% 0%

Sulfur Recovery & Tail Gas Unit (869-3) 0.0% 1,120 M3 27-Jun-23 19-Feb-24

IC869S3CV0402 Pipe Rack Foundation_869-PR-301_[869-3] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 27-Jun-23 22-Aug-23 0.00% 0% 0% 0% 0% 0%

IC869S3CV0404 Pipe Rack Foundation_869-PR-302_[869-3] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 24-Aug-23 2-Oct-23 0.00% 0% 0% 0% 0% 0%

IC869S3CV0406 Pipe Rack Foundation_869-PR-303_[869-3] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 3-Oct-23 30-Oct-23 0.00% 0% 0% 0% 0% 0%

IC869S3CV0408 Pipe Rack Foundation_869-PR-304_[869-3] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 31-Oct-23 27-Nov-23 0.00% 0% 0% 0% 0% 0%

IC869S3CV0410 Pipe Rack Foundation_869-PR-305_[869-3] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 28-Nov-23 25-Dec-23 0.00% 0% 0% 0% 0% 0%

IC869S3CV0412 Pipe Rack Foundation_869-PR-306_[869-3] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 26-Dec-23 22-Jan-24 0.00% 0% 0% 0% 0% 0%

IC869S3CV0414 Pipe Rack Foundation_869-PR-307_[869-3] 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 160 M3 23-Jan-24 19-Feb-24 0.00% 0% 0% 0% 0% 0%

Total 0.0% 24,056 M3 15-Oct-22 19-Feb-24