3) A crane is working near 2 meter deep excavation, minimum distance from the edge shall be:
a) 1 Meter
b) 2 Meter
c) 3 Meter
d) None of the above
5) When grinding a piece of metal with a portable power grinder, the type of Personal Protective
Equipment required is:
a) Safety glass only
b) Goggles only
c) Face shield only
d) Safety glasses/face shield combination
6) The maximum voltage permitted for portable power tool in construction site is:
a) 110 Volt
b) 220 Volt
c) 240 Volt
d) 150 Volt
7) Flammable materials storage area cannot be located within_________ of other buildings or structure.
a) 25 ft
b) 50 ft
c) 50 Meters
d) 100 ft
8) The ratio of vertical to horizontal spacing for a straight or extension ladder is:
a) 1 to 1
b) 2 to 1
c) 3 to 1
d) 4 to 1
9) A straight or extension ladder must extend over the edge of a roof, excavation, or scaffold platform
by minimum distance:
a) 1 foot
b) 4 feet
c) 0.9 meter
d) No ser distance
10) The Saudi Aramco General Instruction which sets forth the Work Permit Receiver’s requirement is:
a) GI 1.200
b) GI 5.430
c) GI 2.100
d) GI 6.200
11) If someone is injured on your job site, a preliminary written report must submitted to the Saudi
Aramco PMT within _________ period of time:
a) 2 Hours
b) 24 Hours
c) 8 Hours
d) 3 Days
12) Work platforms must have toe boards, top rails and access ladders once they reach a height of_____:
a) 4 ft
b) 8 ft
c) 6 ft
d) When the height is four times greater than the base width
13) Excavation “Spoils” must be set back a minimum of _____ from the sides of the excavation.
a) 1 Meter
b) 6 feet
c) 3 feet
d) 2 feet
15) During storage of oxygen and acetylene gas cylinders they must be separated by (1) A fire Resistant
wall or (2) a Distance of______:
a) 20 feet
b) 50 feet
c) Not required if tanks are empty
d) None of the above
16) Which of the following would be classified as a Class “A” fire
a) A Fire involving ordinary combustible
b) A fire involving flammable liquid
c) A fire involving combustible metal
d) A fire involving live electrical equipment
18) What is necessary for a worker to wear on a steel beam six feet of more above ground?
a) A steel belt with steel or brass coupling
b) A full body harness with lanyards attached to an anchor point
c) He must never go on steel beam
d) None of the above
19) When there is opening in roof work and/or edges of roof, and a fall hazard exist, barricades must be
installed capable of withstand a force of:
a) 100 lbs (54.4kg)
b) 150 lbs (68kg)
c) 200 lbs (91kg)
d) 125 lbs (56.7kg)
20) Which of the following factors does affect the load capacity of a mobile crane?
a) Boom length
b) Boom angle
c) Extending the out rigger fully
d) Installation of an anti-two block device
21) How many clips are required to construct an eye in a one half inch wire rope?
a) 3 clips with U bolts on the live end
b) 4 clips with U bolts on the live end
c) 3 clips with U bolt on the dead end
d) 4 clips with U bolts on the dead end
22) Class “B” fires involve flammable liquids or gases that could be under pressure. What would give you
most concern when selecting a Class “B” fire extinguisher?
a) Exposure to electrical equipment
b) Depth of flammable liquid
c) Location of fire exits
d) Type of fire detectors present
25) When transferring an extremely flammable liquid from a 55 gallon drum via a drum a hand pump to a
small metal can, which of the following provides the best protection?
a) Ground both container
b) Bond both container together
c) Bond container together and ground each to a separate ground
d) Ground one container and then bond them to each other
26) A small mobile crane with rubber tires has struck a power line. The line, which I s now believed to be
dead, is lying across the crane boom. Which of the following best describes the proper course of.
action for the crane operator?
a) Jump from the crane and run away
b) Stay in the crane until emergency crews arrive
c) Have the oiler knock the line from the boom with a wood pole
d) Swing the boom back and forth until the line breaks or fall off
27) When checking the ground on a duplex outlet, which of the following provides the best method?
a) Check the continuity between the block and the white wire
b) Check the continuity between green wire and the outlet box
c) Check the continuity between white wire and the outlet box
d) Check the continuity between green wire and the building ground
28) Which of the following is true concerning explosive proof equipment? Explosive proof equipment is allowed to
operate in a flammable or explosive atmosphere because it is capable of:
a) The explosion if it happens will stay inside the container
b) Not producing sparks under any condition
c) Operating below ignition temperature
d) Shutting down the equipment serviced in an emergency
29) Minimum period of time the appointed “fire watch” remain at the site of HOT work after the activity
has stopped
a) 10 minutes
b) 15 minutes
c) 30 minutes
d) 60 minutes
33) When lifting over or adjacent to process piping, etc. what is required?
a) Hold tag
b) Welding Machine
c) Rigger 3
d) Hot work
e) All of above
35) If you found a fire exit blocked by a wooden pallet what would you do?
a) Leave it
b) Move it at quitting time
c) Move it immediately
d) Wait for someone else to move it
37) What is the permissible noise exposure for an eight hours work shift?
a) 80
b) 90
c) 100
d) 120
41) What is the grade of the supplied air for hood and respirators during abrasive blasting?
a) A
b) B
c) C
d) D
43) Flammable materials storage areas cannot be located within________ of other buildings or Structures:
a) 25 ft
b) 50 ft
c) 50 meters
d) 100 ft
44) Keep stored O2 cylinders separated from fuel gas cylinders by ___ or by a ____ high noncombustible barrier.
a) 20ft, 10ft
b) 15ft, 5ft
c) 20ft, 5ft
d) 10ft, 5ft
45) At what concentration of H2S will loss of consciousness and death occur within minutes?
a) 100 ppm
b) 250 ppm
c) 500 ppm
d) 1000 ppm
46) If someone is injured on your job site, a preliminary written report must be submitted to the Saudi
Aramco PMT within ________ period of time and final report within _________:
a) 2 hours, 48 hours
b) 24 hours, 72 hours
c) 8 hours, 72 hours
d) 1 hour, 48 hours
47) Guardrail systems shall be able to withstand, without failure a force of at least _______ lbs. applied in any
downward or horizontal direction at any point on the top rail or equivalent member.
a) 200
b) 300
c) 400
d) 500
48) What is the minimum concentration of H2S that is considered immediately dangerous to life and Health (IDLH)
a) 10 ppm
b) 50 ppm
c) 100 ppm
d) 500 ppm
49) The maximum working pressure on an acetylene gauge is ________ psig.
a) 7
b) 10
c) 15
d) 20
52) Crane operation shall be stopped at wind speed above ________ km/h.
a) 24
b) 28
c) 32
d) 36
53) The contractor shall provide one toilet for every __________ worker.
a) 15
b) 20
c) 35
d) 50
54) When there are openings in roof work and/or at edges of roofs, and a fall hazard exist, barricades must be
installed capable of withstanding a force of:
a) 100 lbs (45.4 kg)
b) 150 lbs (68 kg)
c) 200 lbs (91 kg)
d) 125 lbs (56.7 kg)
55) The Saudi Aramco Sanitary Code states that:
a) Eating is allowed on the worksite.
b) You shall provide one toilet for every 50 workers.
c) You shall provide drinking water and a dipper.
d) None of the above.
60) When transferring an extremely flammable liquid from a 55-gallon drum via a hand pump to a small metal safety
can, which of the following provides the best protection?
a) Ground both containers.
b) Bond both containers together.
c) Bond containers together and ground each to separate ground.
d) Ground one container and then bond them to other.
62) What should people look for when inspecting hand tools before use?
a) Check the load rating.
b) Missing or broken parts.
c) Electric rating.
d) Load rating.
63) Which of the following is true concerning explosive proof equipment? Explosive proof equipment is allowed to
operate in a flammable or explosive atmosphere because it is capable of:
a) The explosion if it happens will stay inside the container.
b) Not producing sparks under any condition.
c) Operating below the auto ignition temperature.
d) Shutting down the equipment serviced in an emergency.
64) How long should the appointed “Fire Watch” remain at the site of HOT work after the work has stopped?
a) 10 minutes
b) 15 minutes
c) 20 minutes
d) 30 minutes
67) When lifting over or adjacent to process piping, etc., what is required?
a) Hold Tag.
b) Welding Machine.
c) Rigger 3.
d) Hot Work Permit.
e) All of the above.
69) Identify two things that must be done to make sure hand tools do not cause injury.
a) Properly ground and bond them.
b) Inspect them and use them safely.
c) Check the Saudi Aramco approval.
d) Check the certification and sticker.
72) The top edge height of top rails shall not be less than ______ and not more than _____ above the walking /
working surfaces of a platform.
a) 0.95 m (38 in) / 1.27 m (50 in)
b) 089 m (35 in) / 1.15 m (45 in)
c) 0.95 m (38 in) / 1.15 m (45 in)
d) 1.016 m (40 in) / 1.27 m (50 in)
74) Crane boom shall be kept ________ feet from overhead power lines up to 50,00 volts and _________feet over
250,000 volts.
a) 10;20
b) 15;20
c) 10;25
d) 15;25
75) You need to inform the operator of heavy equipment to stop work. The operator is in the cab operation the
equipment and is wearing ear defenders. What should you do before approaching?
a) Shout loudly to the signal man.
b) Establish eye contact with the signal man.
c) Establish eye contact with the operator.
d) Shout loudly to the operator.
78) A ladder shall extend _______________________ above the upper point of contact.
a) 1 meter (3 ft)
b) 3 meters (10 ft)
c) 4 rungs
d) 12 inches
79) Portable electric tools must be:
a) Insulated or double grounded.
b) Single insulated or bonded.
c) Double insulated or grounded.
d) Double grounded or de-energized.
80) A confined space must not be entered without wearing supplied-air respirators if the oxygen level is below:
a) 21 %
b) 18 %
c) 25 %
d) 19.5 %
81) During which of the following activities should you wear a personal floatation device?
a) When boarding a boat.
b) When on an offshore rig.
c) When disembarking from a barge.
d) All of the above.
e) A and C only.
82) What must you ensure when boarding a vessel from a pier?
a) You have a work permit.
b) You have your luggage.
c) Winds are less than 20 knots.
d) You have a safe access.
83) When performing crane operations on a vessel, what can affect control of crane loads?
a) Passing vessels.
b) Drilling operations.
c) Wave Action.
d) All of the above.
e) A and C only.
84) Who is responsible for all safety on board a marine vessel or barge?
a) Site PMT.
b) Construction Manager.
c) Captain/Master.
d) Safety Officer.
86) Personnel basket shall not be permitted to transfer personnel when the wind speed exceeds _______ or in
rough weather.
a) 28 km/h (21 knots)
b) 50 km/h (28 knots)
c) 13 km/s (7 knots)
d) 25 km/h (14 knots)
87) What is the first thing you should do if a person falls in the water?
a) Inform the Captain/Maser.
b) Shout “Man Overboard”.
c) Follow the directions of the Captain/Master.
d) Throw a floatation device in the water.
90) When can you transfer from a boat to a boat landing (or vice versa) using the swing rope technique?
a) If you have both hand free.
b) During an emergency drill.
c) When the winds are light.
d) After you have received the training.
91) Fall protection training shall be provided for personnel exposed to fall hazards. The training shall include, but not
be limited to, the following topics “select all that apply”
a) Fall hazard recognition mitigation measure
b) Use, operation and inspection of temporary guardrail system (including perimeter safety cable systems)
fall arrester system, safety net systems and other fall protection to be used.
c) Procedure for erecting, maintaining, disassembling and inspecting temporary guardrail system.
d) Procedure to prevent fall through holes and openings in walking/working surface and walls.
e) a, b and d only
92) Whenever there is any doubt as to safety of the lift, the crane operator shall:
a) Stop all hoisting activities.
b) Refuse to handle unsafe loads.
c) Discuss the matter with the signal man
d) a and b only
93) Contractor personnel shall be familiar with the following “Select all that Apply “
a) Facility’s audio and visual alarms.
b) Evacuation routes and procedures.
c) Assembly areas and shelters.
d) Specific roles/responsibilities
e) Specific facility emergency response plan
94) Personnel performing work at heights and their supervisors shall:
a) Be trained in the nature of fall hazards in the work area and Undergo refresher training at least every 3
years.
b) Demonstrate competency by successfully passing written and practical tests.
c) All of the above
96) Moving machine parts shall be ________ if located 2.5m(8.2ft) or less above the floor or working surface. This
includes flywheels, shafts, pulleys and belt/chain drives.
a) Removed
a) Guarded
b) Separated
c) Eliminated
98) A design of straps that may be secured about a person in a manner to distribute the fall arrest forces
over the thighs, pelvis, waist, chest and shoulders, with means for attaching the harness to other
components of a personal fall arrest system is called:
a) Positioning Device
b) Body Belt
c) full Body Harness
d) Layard
105) Forks shall be tilted back and raised no more than______ above the ground to maintain stability
when traveling with loads.
a) 10-20 cm (4-8 inches)
b) 15-20 cm (6-8 inches)
c) 15-30 cm (6-12 inches)
d) not required.
106) A person allowed to operate crane in S.A project, “Select all that apply:”
a) S.A. certified crane operator
b) Trainees Under the direct supervision of qualified trainer.
c) Crane maintenance personnel and inspector in the performance of duties.
d) SAG licensed personnel.
107) Reverse alarms shall be minimum_____ audible and working on all heavy equipment.
a) 10 decibels (dBA).
b) 20 decibels (dBA).
c) 30 decibels (dBA).
d) 85 decibels (dBA).
SECTION - 2 CHOOSE TRUE OF FALSE
1) When step ladders have step on one side and rungs on the other, two men may be on the same
ladder at the same time
a) True
b) False
2) Portable power tools being operated from an onsite generator need not be protected by a GFCI to be
consistent with the Saudi Aramco CSM
A) True
B) False
3) Excavation not subjected to vehicle traffic may barricaded using Red and White warning tape
a) True
b) False
4) The new heavy plastic % gallon drums may be used to store. Transport, and dispense diesel fuel only
a) True
b) False
5) Cigarette smoking is forbidden anywhere on Saudi Aramco construction sites except in designated
and approved smoking shelters.
a) True
b) False
6) Hole may be drilled into sides of hard hats to provide for cross ventilation air flow during very hot
weather
a) True
b) False
8) Soap and paper towel must be provided for the men to clean up before meal
a) True
b) False
9) Push sticks must be used when guiding wood work into a table saw
a) True
b) False
10) Rubber boots must be provided for person engaged in the pouring of concrete
a) True
b) False
11) When wearing rubber boots for pours, it is not necessary to have your steel toe shoes on
a) True
b) False
12) Placing as 8’2” X 12” board over two 20 –liter paint cane is allowed for temporary work platform
a) True
b) False
13) Formwork boards should be removed to the de nailing area as soon as possible after they are disassembled.
a) True
b) False
14) A fire extinguisher must be placed near (5 to 15 feet) to any combustible engine being operated on site
a) True
b) False
15) Tool box safety briefing must be held at site once I n a week.
a) True
b) False
17) Hand held power tool such as drill and grinders may be locked on if the job is going to take a long
period of time to accomplish
a) True
b) False
18) Permanent scaffold should be secured by tying off to a firm portion of the structure every 26 ft
a) True
b) False
19) Scaffold planks must be at least 2” thick by 9” wide or up to 2” thick by 12” wide
a) True
b) False
20) Scaffold planks must be tied to or otherwise secured to the scaffold bearers
a) True
b) False
21) The windsocks in Saudi Aramco facilities are to let people know in which direction a gas or chemical leak will flow
a) True
b) False
22) A safety officer must tour the site several times a day because condition is changing constantly during
construction activities
a) True
b) False
23) Dangerous safety hazards should be noted and kept in writing so that they can be reported at next safety
meeting
a) True
b) False
24) A weekly safety inspection of each area should carried out and a report of defects given to those responsible for
correcting them
a) True
b) False
25) A safety officer should check all construction activities only. The personnel officer checks the
medical facilities, toilet, drinking water and all things affecting health and welfare
a) True
b) False
26) When hot tapping gasoline lines, it is very important to establish and maintain product flow
a) True
b) False
27) It is okay to bring chemicals on site without a MSDS if you only have 20 liters of liquid or 10 cubic
meters of a toxic gas
a) True
b) False
28) Crane operation must be stopped when the wind speed is over 32 mph
a) True
b) False
30) Before use, all new lifting equipment should be subjected to a proof load test
a) True
b) False
31) Respiratory protective devices can be classified as, air purifying, supplied air, and self-contained
breathing devices
a) True
b) False
32) When performing excavation work and there are no known underground utilities, or suspected
utilities, it is permissible to use mechanical equipment to excavate
a) True
b) False
33) A PFAS with a shock absorbing lanyard is required protection when working at 10 feet height to the
lower level
a) True
b) False
34) A scaffold tag is NOT required for scaffold less than 6 feet in height
a) True
b) False
35) Primary requirement in a confined space entry permit is gas testing by a worker
a) True
b) False
36) The ratio of number of portable toilets to number of workers at site is 1:15
a) True
b) False
38) The minimum clearance between building in lay down yards is 50 feet
A) True
B) False
41. Personnel working on, over or near water shall wear approved Personal Floatation Device (PFD)’s per GI 6.020,
unless prevented from falling into the water by a fall protection system
a) True
b) False
42. Portable power tools being operated from an onsite generator need not be protected by a GFCI (ground fault
circuit interrupter) to be consistent with the Saudi Aramco CSM.
a) True
b) False
43. The new heavy plastic 5 gallon drums may be used to store, transport, and dispense diesel fuel only.
a) True
b) False
44. Cigarette smoking is forbidden anywhere on Saudi Aramco Construction sites except in designated and approved
smoking shelters.
a) True
b) False
45. The work permit should be revised if there is any change in the condition.
a) True
b) False
46. If a tool breaks it is permissible to weld a piece of pipe as a handle temporarily
a) True
b) False
47. Soap and paper towels must be provided for the men to clean up before meals.
a) True
b) False
48. Slings shall be tagged with a safe Working Load (SWL) in the field.
a) True
b) False
49. Personnel basket transfers shall not be conducted when the wind speed exceeds 25 km/h 15 mph, 14 knots) or
in rough weather.
a) True
b) False
50. A fire extinguisher must be placed near (5 to 15 feet) to any combustion engine being operated on site.
a) True
b) False
51. Hand held power tools such as drills and grinders may be locked-on if the job is going to take a long period of
time to accomplish.
a) True
b) False
53. Scaffold planks must be at least 2” thick by 9” wide or up to 2” thick by 12” wide.
a) True
b) False
Mmay
54. Scaffold planks must be tide to or otherwise secured to the scaffold bearers.
bethis
a) True
b) False
55. A safety Officer must tour the site several times a day because condition is changing constantly during
construction activities.
a) True
b) False
56. A weekly Safety Inspection of each area should be carried out and a report of defects given to those responsible
for correcting them.
a) True
b) False
57. A Safety Officer checks all construction activities only. The personnel officer checks the medical facilities, toilet
facilities, drinking water and all things affecting health and welfare.
a) True
b) False
58. It is okay to bring chemicals on site without a MSDS if you only have 20 liters of liquid or 10 cubic meters of a
toxic gas.
a) True
b) False
59. Crane operation must be stopped when the wind speed is over 10 mph?
a) True
b) False
63. Personnel shall not be on any scaffold or other temporary elevated work area during sustained winds more than
65 kph (40 mph)
a) True
b) False
64. Climbing of scaffold braces, runners, etc., is not permitted, except as required by a scaffold craftsmen during
scaffold erection, alteration and dismantling.
a) True
b) False
65. Ladder should be positioned at an angle where the horizontal distance from the top support to the foot of the
ladder is ¼ the working length of the ladder or 75 degrees’ angle.
a) True
b) False
66. Use GFCI’s on all 120-volt, single-phase, 15 and 20 ampere receptacles, or have an assured equipment
grounding conductor program.
a) True
b) False
67. Only UL, FM or other recognized testing lab approved extension cords bearing appropriate lab trademarks shall
be used.
a) True
b) False
68. Eye and face protection devices shall meet ANSI Z87.1 requirement.
a) True
b) False
69. Hard hats shall be replaced not more than 5 years from the date of manufacture stamped/printed/embossed on
the inside of the shell.
a) True
b) False
70. Forklift operators shall travel in reverse when the load obstructs the operator’s forward view.
a) True
b) False
71. Outdoor storage of flammable and combustible materials shall not be within 3 meters (10 ft) of a building or
structure.
a) True
b) False
72. Screw-type (Jubilee)) hose clamps can be used to secure compressed air hoses to fittings/couplers.
a) True
b) False
73. Portable electric power tools shall be certified by an independent testing and certification services such as
Underwriters’ Laboratories (UL), Factory Mutual (FM) or Conformite Europeene (CE) and shall bear the
appropriate certifying agency mark.
a) True
b) False
74. Job-made extension cords shall be fabricated by a certified electrician and shall meet the requirements in
Section 11.7.15 (A) through 11.7.15(H) of the Construction Safety Manual (5th edition).
a) True
b) False
75. Personnel shall not be on any scaffold or other temporary elevated work area during storms or high winds (i.e.,
sustained winds more than 65kph).
a) True
b) False
76. Mobile and tower scaffolds shall be plumb, level and square, and shall be horizontally and vertically braced in
both directions by diagonal braces.
a) True
b) False
77. Personal fall arrest systems shall include a full body harness, shock absorbing lanyard or self-retracting lifeline
and a substantial anchor point and/or horizontal/vertical lifeline.
a) True
b) False
78. Safety belts shall be used as part of a personal fall arrest system.
a) True
b) False
79. Self-retracting lifelines shall not be connected to a lanyard, but shall be directly attached to a D- ring on the full
body harness.
a) True
b) False
80. Abrasive blasting breathing air equipment shall include a high efficiency breathing air filter and water/oil traps
before the filter in the breathing air delivery system to remove moisture, oil, mist and particulates.
a) True
b) False
81. Hearing protection shall be provided to all personnel in areas near abrasive blasting operations where noise
levels exceed 85 decibels (dBA).
a) True
b) False
82. Breathing air quality shall meet Compressed Gas Association (CGA) Grade “D” and shall be tested by every six
(6) months by a SA approved independent 3rd party testing facility.
a) True
b) False
83. All sand blasting component and work surfaces shall be electrically grounded to the compressor, and the
compressor bonded to a permanent ground to prevent static electricity build up.
a) True
b) False
84. Flashback flame arrestor shall be installed on all oxygen/fuel cylinder regulators and check valves shall be
installed at the end of hoses near the torch.
a) True
b) False
85. If a welding cable becomes damaged beyond a distance of 3 meters (10 ft) from the end to which the electrode
holder is connected, it shall be repaired using a standard plug-and-socket coupling.
a) True
b) False
86. Electrical equipment shall not be used in electrically classified locations, unless it is marked to show the class,
group and operating temperature for which it is approved.
a) True
b) False
87. All heavy equipment/vehicles shall be grounded as soon as they are positioned near overhead power lines for
any type of work.
a) True
b) False
88. Slings and other rigging hardware shall have a minimum design safety factor of 5.
a) True
b) False
89. Aluminium ferrules are permitted to be used for wire rope slings.
a) True
b) False
90. Slings, other rigging hardware and hooks shall be periodically inspected by a SA certified rigger at a maximum
interval of 6 months.
a) True
b) False
91) Unstable or insecure loads shall not be transported. Loads shall not be raised or lowered while the
forklift is moving.
a) True
b) False
92) Diesel or gasoline powered forklifts shall not be used in closed buildings, warehouses or poorly
ventilated areas.
a) True
b) False
93) Forklifts shall not be left unattended with the engine running. When forklifts are parked the forks shall
not be in a raised position.
a) True
b) False
SECTION – 3 MATCH THE FOLLOWING
AB
1.
G 1 Loose Soil A Standard spacing between fire extinguisher
L 2 2 1.2 meter deep excavation B 120 meters
C 3 50 feet C 50% times
B 4 Maximum distance between fire hydrants D 25 feet clearance
E 5 Certified operator E Crane
N 6 Common drinking cup F No work on height
p 7 7 Fire water minimum discharge pressure G Type C
C 8 Out rigger mats to pads H Man lift activity
I 9 Distance between lay down yard & building I 16 meters
J 10 25 kph J Man basket operation not allowed
Q 11 First aid facilities K Bed-space allocation per worker
H 12 Properly anchored PFAS L Confined space
D 13 More than 250,000 volts M Well ventilated
T 14 Approval of a critical lift plan N Prohibited
F 15 65 kph O All types of fire except metal fires
S 16 BC dry chemical fire extinguisher P 80 psig
R 17 32 kph Q MMSR
M 18 Laundry, toilets bathroom R Crane lifting operations
K 19 50 square feet S Purple K
O 20 ABC dry chemical fire extinguisher T Rigger I
2
B 1 Oxygen cylinder A Red
C 2 Acetylene cylinder B Green
D 3 Argon cylinder C Yellow
E 4 Nitrogen cylinder D Grey
A 5 DCP Fire extinguisher cylinder E Blue
3
C 1 Hot work A Activities that will not produce sufficient energy to ignite
flammable atmospheres or combustible materials.
A 2 Cold work B The entrance of any part of the body into a space that
meets the criteria for a confined space
B 3 Confined space Entry C Any activity that may develop sparks, flames or heat