The document outlines the key stages of concrete construction:
1) Site preparation involves clearing vegetation, leveling the ground surface, and marking pillar placements.
2) Excavation is carried out based on the structure type. Footings are constructed in trenches to support the foundation.
3) Columns are cast on site by pouring concrete into shutter molds.
4) A plinth beam is built between the foundation and walls to transfer structural loads.
5) A roof slab is constructed using reinforced concrete to provide the roof structure.
6) Block masonry work involves constructing the walls using materials like brick or concrete blocks.
The document outlines the key stages of concrete construction:
1) Site preparation involves clearing vegetation, leveling the ground surface, and marking pillar placements.
2) Excavation is carried out based on the structure type. Footings are constructed in trenches to support the foundation.
3) Columns are cast on site by pouring concrete into shutter molds.
4) A plinth beam is built between the foundation and walls to transfer structural loads.
5) A roof slab is constructed using reinforced concrete to provide the roof structure.
6) Block masonry work involves constructing the walls using materials like brick or concrete blocks.
The document outlines the key stages of concrete construction:
1) Site preparation involves clearing vegetation, leveling the ground surface, and marking pillar placements.
2) Excavation is carried out based on the structure type. Footings are constructed in trenches to support the foundation.
3) Columns are cast on site by pouring concrete into shutter molds.
4) A plinth beam is built between the foundation and walls to transfer structural loads.
5) A roof slab is constructed using reinforced concrete to provide the roof structure.
6) Block masonry work involves constructing the walls using materials like brick or concrete blocks.
CONSTRUCTION CLEARING • The clearing of the site should be completed by gathering all cut vegetation, stumps, roots and large stones. All these should be removed from the work area . LEVELLING • Smooth out the ground with the flat side of a rake so that you have a level surface. Fill in any low spots with soil.. MARKING ON SITE • Site marking is one of the starting point of your construction. • In this activity your Engineer and Meastri will identify pillar placements. Once pillars placement is identified based on soil condition earth work will start. • Once pillars placement is identified based on soil condition earth work will start. • Engineer will mark the area around the pillar. Earth workers will dig marked area • Depending on soil condition pillar depth will vary. • Some people perform puja before starting this marking. • The easiest way to begin is to measure the width of the foundation wall and mark it along the strings set out for two opposite walls. Then set out a string between these two points and fasten the ends with pegs. Use a plumb bob to be sure each peg is directly beneath the outside foundation line. EXCAVATION • Excavation is the first step in soil preparation for concrete works. Depending upon the type of structure, excavation is carried out. Additional 2 inches is added in the excavation for gravel if the soil is normally moist or has a high concentration of clay. FOOTING • Footings are the most important part of foundation construction. The purpose of footings is to support the foundation, prevent settling, and is crucial to providing the proper support for the foundation and ultimately the structure. • Trenches are made on the site. • They are typically made of concrete with rebar reinforcement that has been poured into an excavated trench. The purpose of footings is to support the foundation and prevent settling. Footings are especially important in areas with troublesome soils. COLUMN CASTING • Columns are constructed on the pits • Shuttering is made in the position of the column • Pour the concrete in to the shuttering mould. • Remove the shutter 7 – 10 days after casting PLINTH BEAM • The Plinth beam is a reinforced concrete beam built between the wall and its foundation resting on ground and transfer load of building structure to the foundation and soil. Over the plinth beam, masonry work is started. And space between foundation and plinth beam filled with soil. ROOF SLAB CONSTRUCTION • The design of a roof slab is based on the thickness of slab, size of bars, distances of bars, hooks, cranks and laps of bars, minimum cover of concrete etc. The concrete mix for the slab is normally provided with volume and it's ratio is 1:2:4 ( cement, sand and aggregate). BLOCK MASONRY WORK • In building construction wall occurs in various forms of masonry work such as brick masonry, concrete block masonry, hollow cement concrete block masonry. • The lintel is constructed on the door and window to support the masonry work over it, • Sill level height up to the window base, measuring from the floor level to the window base. Sill is horizontal plane base for window which is mostly provided of granite, concrete or tambour wood.
2.2. What Are The Types of Excavation Needed For This Foundation? Construction? Describe The Associated Temporary Works For The Construction of Foundation