- The document is a check sheet for bored pile work that lists verification and inspection items for various stages of the project including document verification, material inspection, pile properties, setting out, boring process, concreting, and post-concreting.
- It includes checking items such as shop drawings, material properties, pile dimensions, installation layout, boring depth, concrete slump, reinforcement, and finished pile position and straightness.
- Upon completion of each stage, the relevant parties must sign off to confirm the listed items have been checked.
- The document is a check sheet for bored pile work that lists verification and inspection items for various stages of the project including document verification, material inspection, pile properties, setting out, boring process, concreting, and post-concreting.
- It includes checking items such as shop drawings, material properties, pile dimensions, installation layout, boring depth, concrete slump, reinforcement, and finished pile position and straightness.
- Upon completion of each stage, the relevant parties must sign off to confirm the listed items have been checked.
- The document is a check sheet for bored pile work that lists verification and inspection items for various stages of the project including document verification, material inspection, pile properties, setting out, boring process, concreting, and post-concreting.
- It includes checking items such as shop drawings, material properties, pile dimensions, installation layout, boring depth, concrete slump, reinforcement, and finished pile position and straightness.
- Upon completion of each stage, the relevant parties must sign off to confirm the listed items have been checked.
Level: Checked by Checked by STAGE ITEM YES/NO DATE S/C CONT. CONSULTANT
Document - Shop drawing and Method statement
Verification are approved. - Concrete trial mix design is approved - Rebar Sample testing and submission are approved - Steel casing material is approved Incoming - Concrete Grade: material - Concrete Slump: inspection - Reinforcement Cage: Main rebar (eg: 32DB20), Link (DB12@200, tie) - Steel reinforcement strength: - Lapping length: - Concrete Cover/Spacer: - Fresh bentonite slurry mixture - Steel casing diameter: - Steel casing thickness: - Steel casing length: Property of - Pile diameter: drilled pile - Pile head level: - Pile Toe level: - Pile length: Setting out - Check building boundary - Check gridline - Check pile setting out - Set up referent points (3 points) - Check steel casing setting out - Check steel casing verticality - Check pile rig verticality Boring Process - Temporary steel casing must be extend at least 1m above the ground level to prevent loose material falling into the bottom of bored hole PROJECT NAME
- Check bored hole depth to follow
approval design - Check bentonite slurry before rebar installation - Check any deviation in the distance of the pile point to the referent points after soil boring - The depth achieved (penetrated hard strata to specify depth are checked by the measurement tap - No excavation commences within 8m of any concrete pile curing less than 24 hours - Piles are not bored next to other piles which are just casted (less than 24 hours) Concreting - Check dimension of reinforcement - Check bentonite slurry mixture to follow specification - Check concrete tremie pipe for concreting - Tremie pipe will be raised about 200mm above the base of bored hole - Bottom end of tremie pipe is always submerged 2 to 3 meters below the level of concrete. - Concreting only stopped at about 1 to 1.5 meter above the cut-off level - Check slump of concrete for selected deliveries - Prepare test cube or cylinder following standard requirements - Record number of trucks and discharge amount per truck Post Concreting - Pile head positioned within max. deviation 75mm in any direction from its design position - Max. Deviation of finished pile from vertical at any level is less than 1/150 PROJECT NAME
- Conduct sonic pipe test
- Estimate the amount of concrete for each pile
For S/C: Date: For CONTRACTOR Date For CONSULTANT Rep. Date: QA/QC: