You are on page 1of 3

Page 1/2

Building :
Form No. : TG-F-06-04.1.4
Year :
COOLING TOWER TESTING AND COMMISSIONING CHECKLIST

Site Location Brand


Equipment No. Model / Serial No.
Type of CT

INITIAL TESTING FINAL TESTING


DATA DESIGN
INITIAL REMARKS FINAL REMARKS

1. Rated Heat Rejection Capacity Ton


1.1 Range °F
1.2 Approach °F
2. Number of cell/s
3. Condenser water data
3.1 Water Flowrate gpm

3.2 Entering Water Temp °F


3.3 Leaving Water Temp °F
4. Air temperature data °F
4.1 Ambient air temp, db/wb °F
4.2 Entering air temp, db/wb °F
4.3 Leaving air temp, db/wb °F
5. Fan data
5.1 Type
5.2 Material
5.3 Air Flowrate cfm

6. Fan motor
6.1 Rated Power Kw
6.2 Ampere (FLA/Starting/Running)
L1 A
L2 A
L3 A

DATE OF INITIAL TESTING REMARKS :

Company Name Representative PRC Number Signature

Contractor
PM/Gencon QA/QC

DATE OF FINAL TESTING

Note :
Company Name Representative PRC Number Signature

Contractor
If Consultant is not present, specify name & company

PM/Gencon QA/QC

Building Design Consultants

APMC - TG Representative
TG Project Manager Start-up Engineer TG Account Officer
Page 2/2

Building :
Form No. : TG-F-06-04.1.4
Year :
COOLING TOWER TESTING AND COMMISSIONING CHECKLIST

Site Location Brand


Equipment No. Model / Serial No.
Type of CT

INITIAL TESTING FINAL TESTING


DATA DESIGN
INITIAL REMARKS FINAL REMARKS

6.3 Volts
L1 - L2 V
L2 - L3 V
L3 - L1 V

6.4 VFD functional test interlock with motor fan

6.5 Motorize valve test interlock with motor fan

6.6 Overload current tripping device test


6.9 Phase
6.10 Cycle
6.11 Drive
6.12 Enclosure

6.13 Quantity
6.14 Brand
7. Make Up Water
7.1 Water meter calibration
7.2 Water meter brand
7.3 Pipe Size mm
7.4 Water Flowrate gpm

7.5 Water level start up at catch basin mm


7.6 Actuation of make up water valve
8. Megger Test

9. Filler type/material

10. Operating weight kg

11. Corrosion protection of cooling tower frame


12. Endurance testing (48 hours continous
running)
13. With or without abnormal vibration
14. With or without abnormal noise

DATE OF INITIAL TESTING REMARKS :


Company Name Representative PRC Number Signature

Contractor
PM/Gencon QA/QC

DATE OF FINAL TESTING

Company Name Representative PRC Number Signature


Note :

Contractor
If Consultant is not present, specify name & company

PM/Gencon QA/QC

Building Design Consultants

APMC - TG Representative
TG Project Manager Start-up Engineer TG Account Officer
Rev. 06

You might also like