You are on page 1of 5

Main contractor : Project :

Trans Resources Corporation PROPOSED INTEGRATED MIXED-USE DEVELOPMENT (8MD3) IN PERCINT 8, PUTRAJAYA.
Sdn. Bhd.
Contract No. : MIX/COM/P8/8MD3/CONTRACTOR/2017-0088 8MD3
Check List For Cold Water Pipe Installation

Building : RIN No.:


Location: Date:
Grid Line: System / Services
Level: Drawing Ref.:

Main Contractor Client’s Consultant


Item Description Acceptable Acceptable Remarks
Yes No Yes No

1 Approved brand / material used

2 Check correct pipe fittings are used

3 Check for proper pipe joints

4 Valves size Installed as per shop drawing

5 Correct alignment & location as per shop drawing

COMMENTS :

Status Of Inspection

We have carried out all necessary inspections and verify that the above items / activities conform to the contract specifications / document.

Checked by Main-Contractor Verified By Client’s Consultant Acknowledged by ER/ERA

Signature

Name

Company

Date

Doc. Ref. : TRC / PQP / 8MD3 / MECH01 Revision: 1 Effective Date: 1st April 2019
Main contractor : Project :

Trans Resources Corporation PROPOSED INTEGRATED MIXED-USE DEVELOPMENT (8MD3) IN PERCINT 8, PUTRAJAYA.
Sdn. Bhd.
Contract No. : MIX/COM/P8/8MD3/CONTRACTOR/2017-0088 8MD3
Check List For Water Storage Tank Installation

Building : RIN No.:


Location: Date:
Grid Line: System / Services
Level: Drawing Ref.:

Client’s
Main Contractor
Consultant
Item Description Remarks
Acceptable Acceptable
Yes No Yes No
1 Approved brand / make material used

2 Tank capacity
3 Cat ladder installation

4 Access opening

5 Air vent

6 Level indicator

7 Incoming pipe, Warning pipe & Overflow pipe installation


8 Gate valves, balancing valve & float valve installation

9 Sampling pipe & balancing pipe installation

COMMENTS :

Status of Inspection

We have carried out all necessary inspections and verify that the above items / activities conform to the contract specifications / document.

Checked by Main-Contractor Verified By Client’s Consultant Acknowledged by ER/ERA

Signature

Name

Company

Date

Doc. Ref. : TRC / PQP / 8MD3 / MECH02 Revision: 1 Effective Date: 1st April 2019
Main contractor : Project :

Trans Resources PROPOSED INTEGRATED MIXED-USE DEVELOPMENT (8MD3) IN PERCINT 8, PUTRAJAYA.


Corporation Sdn.
Bhd.
Contract No. : MIX/COM/P8/8MD3/CONTRACTOR/2017-0088 8MD3
Pressure Test Checklist

Building : RIN No.:


Location: Date:
Grid Line: System / Services
Level: Drawing Ref.:

Working Pressure : Psi / Bar


Test Pressure : Psi / Bar
Specified Duration : Hrs

Main Contractor Client’s Consultant


Time Pressure Reading
Location Date Acceptable Acceptable Remarks
START END START END Yes No Yes No

COMMENTS :

Status Of Inspection
We have carried out all necessary inspections and verify that the above items / activities conform to the contract specifications / document.

Checked by Main-Contractor Verified By Client’s Consultant Acknowledged by ER/ERA

Signature
Name
Company

Date

Doc. Ref. : TRC / PQP / 8MD3 / MECH03 Revision: 1 Effective Date: 1st April 2019
Main contractor : Project :

PROPOSED INTEGRATED MIXED-USE DEVELOPMENT (8MD3) IN PERCINT 8, PUTRAJAYA.


Trans Resources
Corporation Sdn. Bhd.
Contract No. : MIX/COM/P8/8MD3/CONTRACTOR/2017-0088 8MD3
Checklist for Sanitary Plumbing Pipe Installation
Building : RIN No.:
Location: Date:
Grid Line: System / Services
Level: Drawing Ref.:

Client’s
Main Contractor
Consultant
Item Description Remarks
Acceptable Acceptable
Yes No Yes No
1 Approved brand / material used
2 Pipe sleeve installed at correct location & settings
3 Check for proper pipe joints installation
4 Correct alignment & location as per approved shop drawing
5 Pipe gradient for soil waste pipe

COMMENTS :

Status Of Inspection

We have carried out all necessary inspections and verify that the above items / activities conform to the contract specifications / document.

Checked by Main-Contractor Verified By Client’s Consultant Acknowledged by ER/ERA

Signature

Name

Company

Date

Doc. Ref. : TRC / PQP / 8MD3 / MECH05 Revision: 1 Effective Date: 1st April 2019
Main contractor : Project :

Trans Resources PROPOSED INTEGRATED MIXED-USE DEVELOPMENT (8MD3) IN PERCINT 8, PUTRAJAYA.


Corporation Sdn.
Bhd.
Contract No. : MIX/COM/P8/8MD3/CONTRACTOR/2017-0088 8MD3

Flow/Leaked Test Inspection Checklist

Building : RIN No.:


Location: Date:
Grid Line: System / Services
Level: Drawing Ref.:

Client’s
Main Contractor
Consultant
Item Test Sequence Description Visual Checked Status Remarks
Acceptable Acceptable
Yes No Yes No

1 Water to be poured from highest point

2 No leakage detected

10

11

12

13

14

15

16

COMMENTS :

Status Of Inspection

We have carried out all necessary inspections and verify that the above items / activities conform to the contract specifications / document.

Checked by Main-Contractor Verified By Client’s Consultant Acknowledged by ER/ERA

Signature

Name

Company

Date

Doc. Ref. : TRC / PQP / 8MD3 / MECH07 Revision: 1 Effective Date: 1st April 2019

You might also like