Professional Documents
Culture Documents
LTP-0029 (Pigging, Pig Launchers and Receivers)
LTP-0029 (Pigging, Pig Launchers and Receivers)
Documentos Relacionados
Número del
Nombre del Documento Descripción del Contenido
Documento
Forework
This revision of Local Technical Practice (LTP) LTP-0029 is the result of extensive operational
comment and consultation as well as significant lessons learned from recent pig trap failures.
The document has been restructured to bring relevant topics together while adding
information on ATEX requirements and the Global ILI Framework Agreement. The new
structure is as follows:
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Tabla de contenido
1. Scope………………………………..................................................................................................... 6
2. Normative references…………..................................................................................................... 6
3. Symbols and abbreviations......................................................................................................... 7
4. Pigging overview……………….. ................................................................................................... 8
4.1. Reasons to pig ..................................................................................................................... 8
4.2. Pig types............................................................................................................................... 9
4.3. Pig selection, design, and maintenance............................................................................ 9
4.3.1. General ........................................................................................................................................................... 9
4.3.2. Pig design requirements........................................................................................................................10
4.3.3. ATEX requirements for potentially explosive atmosphere service.........................................11
4.3.4. Maintenance and inspection of pigs.................................................................................................11
4.4. In-line inspection pigging requirements ........................................................................ 12
4.5. Pigging operational considerations ................................................................................ 12
4.5.1. General .........................................................................................................................................................12
4.5.2. Safety and risk assessment ...................................................................................................................12
4.5.3. Operating procedures.............................................................................................................................14
4.5.4. Contingency plans....................................................................................................................................15
4.6. Pig trap operations, inspection and maintenance ......................................................... 16
4.6.1. General .........................................................................................................................................................16
4.6.2. Operating procedures.............................................................................................................................16
4.6.3. Flushing and purging of pig traps .....................................................................................................17
4.6.4. Inspection and maintenance ................................................................................................................19
4.6.5. Inspection and revalidation of pig traps..........................................................................................19
5. Pipeline design for pigging ...................................................................................................... 20
5.1. General ............................................................................................................................... 20
5.2. Internal diameters of linepipe ......................................................................................... 21
5.3. Bends for pigging.............................................................................................................. 21
5.4. Valves, check valves, tees, and wyes ............................................................................... 21
5.5. Pig handling equipment ................................................................................................... 23
6. Design of pig trap installations ................................................................................................ 24
6.1. General ............................................................................................................................... 24
6.2. Service conditions and code requirements .................................................................... 28
6.3. Layout requirements......................................................................................................... 29
6.3.1. General .........................................................................................................................................................29
6.3.2. Onshore additional requirements ......................................................................................................30
6.3.3. Offshore additional requirements and vertical pig traps ..........................................................31
6.4. Structural supports and lifting lug design...................................................................... 31
6.5. Pipework and pressure and instrumentation requirements ......................................... 32
6.5.1. General .........................................................................................................................................................32
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
1. Scope
1. Pigging practice.
c. This LPT is relevant to the pipeline technical authority (TA), as well as design, installation, and
operations personnel.
2. Normative references
The following referenced documents may, to the extent specified in subsequent clauses and
normative annexes, be required for full compliance with this LPT:
EQUION
LTP-0030 Inspection and Integrity Assessment of Pipeline Systems.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
ASME Boiler and Pressure Vessel Code Section VIII - Rules for
Construction of Pressure Vessels Division 1.
ASME Boiler and Pressure Vessel Code Section VIII - Rules for
Construction of Pressure Vessels Division 2 - Alternative Rules.
ASME B16.5 Pipe Flanges and Flanged Fittings: NPS 1/2 through NPS 24.
ASME B16.9 Factory-Made Wrought Buttwelding Fittings.
ASME B31.3 Process Piping.
For the purpose of this LPT, the following symbols and abbreviations apply:
D Diameter.
ID Internal diameter.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
OD Outer diameter.
UT Ultrasonic technique.
4. Pigging overview
a. Pipeline pigging is a key part of managing the integrity of pipeline systems. Pipelines require
pigging at the start and end of life. Pipelines are normally pigged for:
1. Commissioning and decommissioning.
2. Cleaning or wax removal.
3. Inventory management (sweeping out liquids, batching products, etc.).
4. Corrosion and scale control.
5. Inspection.
6. Isolation and special operations.
b. New pipeline designs may consider permanent or temporary pig launcher and receiver
facilities.
1. Requirements shall be agreed with operations.
2. The project shall provide necessary equipment to facilitate pigging.
3. If traps are removed after commissioning, safe isolations and space for re-
instatement of pig traps should be left such that future inspection pigging
can be safely achieved.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
c. Pipelines should be pigged for operational and inspection purposes on a regular basis.
1. The timing for inspection is dependent on the corrosion risk assessment and
the effectiveness of detection.
2. Requirements on frequency of inspection are given in LPT-0030
d. Projects shall hand over new pipelines to operations that have been verified to be free of
debris, defects, and obstructions. A baseline ILI inspection should have been completed prior
to handover.
4.3.1. General
a. The selection and type of pig to be used and its optimum configuration for a
particular task in a pipeline shall be based upon several criteria, including:
1. Purpose (e.g., linefill, batching, cleaning, or inspection).
2. Type of information to be gathered (e.g., from an ILI pig run) and data
requirements.
3. Line contents (e.g., gas, oil, or water), with or without contaminants (e.g., wax)
that may need to be displaced or removed during conventional pigging
operations.
4. Required driving pressure versus available pressure.
5. Minimum and maximum internal diameter, including diameter restrictions or
changes (e.g., corrosion probes, coupons, instrument taps, valves, check valves,
barred or sphere tees). When multi-diameter pipelines are pigged, excessive
wear of components in the smaller diameter line section shall be considered.
6. Presence of tees and wyes that may require a longer pig to ensure that the
pressure driving force is maintained as the pig traverses the connection.
7. Minimum bend radius, bend angles, and position of back to back bends.
8. Distance the pig needs to travel and the internal condition of the pipe, with
regard to wear on the cups or discs. Large diameter pigs in gas pipelines may
require wheeled supporting structure.
9. Operating velocity range of the pig.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
10. Elevation profile (e.g., pig acceleration during linefill, slack line conditions for
operating oil pipelines).
11. Maximum temperature and/or fluid pressure permitted.
12. Ability to drive pig in the reverse direction (e.g., for a bidirectional pig).
13. Requirements to track or communicate with the pig.
b. Cleaning and brush/scraper pigs shall be configured to limit the amount of material
that can be removed in a single pass to the amount that can be contained in the
receiver.
c. Some pigs should be run in combination with other pigs (e.g., cleaning pig ahead of
a batch pig) to determine wax quantities and number of cleaning runs required.
d. If multiple module pigs are used, the components shall be designed to allow
removal if the toll separates into component parts.
e. If inflatable spheres are utilized the following shall apply:
1. Spheres shall be filled with a water/glycol mix and ring gaged to ensure
that they are of the correct diameter.
2. Inspected to ensure that the filling plugs do not leak and are replaced, if
necessary.
d. Bypass
By utilizing differential pressure across the pig, a fluid path is created front to back
of the pig creating turbulence in front of the pig. This assists in the cleaning process
and can be used to optimize cleaning.
e. Cleaning elements
A number of types of cleaning elements are available to suit the application if
pipeline cleaning is required. Expert advice should be sought for difficult or unusual
cleaning problems.
a. Pigs and associated equipment containing electronics shall have the correct
certification for area of operation.
1. This shall be consistent with ATEX regulations
2. Pigs used in hydrocarbon service or pigs deploying high powered lithium
batteries shall comply with Zone 1 ATEX requirements.
b. If ATEX compliant tools are not available or do not meet this classification, additional
procedures shall apply.
c. A suitable cross bonding shall be used between the pig trap and any equipment
necessary to perform the pigging operation (e.g., launch/receipt tray). To facilitate
this, the pig trap should be designed with suitable lugs onto which the bonding
cables can be attached.
d. Pigging procedures shall address potential of ILI tools being damaged during
operation, thereby exposing cables and/or components.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
4.5.1. General
a. Pigging operations shall be carried out using formally documented operating
procedures.
b. Only competent personnel who have had the necessary training, experience and
assessment shall be used in pigging operations.
c. There are specific requirements associated with the operation, maintenance, and
inspection of pigging facilities. These are addressed in 4.6.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
c. Flammability of deposits.
d. Operation and maintenance of trap end closures/doors.
e. Lighting (may be required for 24 hour operation).
f. Access and lifting.
5. Potential failure of operation requiring a contingency plan including:
a. A stuck, damaged or lost pig.
b. Pig location.
c. Removal or recovery of a stuck or damaged pig or pig components.
d. Communications.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
3. If two pigs, including a dual module pig, are run in the line at the
same time, second pig should be capable of driving first pig in the
event of seal failure of the pig.
4. Multiple pigs should only be deployed for specific reasons, such as
commissioning, line purges, and special cleaning operations.
e. Pipeline inlet and outlet pressures and flows shall be monitored and recorded
throughout the pigging operation.
f. Effects of pigging on the downstream process shall be assessed in design
process and prior to commencement of any pigging operation.
g. Pigging operations shall be formally recorded, including the quantity of
material removed from the pipeline and the condition of the pig.
h. Pigging procedures shall address what actions are to be taken in event of a
stuck pig or loss of components from the pig before pigging operations begin.
i. If the known location of the pig is required, transponders should be fitted to a
pig to aid detection. The type of transponder used should consider the length
of time required to mobilize and detect the pig.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
4.6.1. General
a. Operators shall have formal training of pig trap operation, maintenance, and door
interlock system.
b. Detailed launch or receive procedure shall be developed for each location and for
the type of pig being launched and/or received.
c. Detailed procedures shall be developed and used for each pig trap door type, pig
trap facility, and associated fittings and equipment. These shall include the relevant
manufacturer’s operating, maintenance, and inspection requirements.
d. Manufacturers’ requirements and recommendations shall be reviewed and
supplementary information shall be developed if these are vague or unclear.
e. Procedures shall be prepared to address the inspection, maintenance, and
replacement of components with recommended frequencies.
f. Elastomeric and polymeric seals shall be selected for suitability with process
conditions, including any trace media, such as methanol, glycol, and corrosion
inhibitors. Seals used in gas service shall also be selected for resistance to explosive
decompression.
g. Pig trap end closures shall comply with the requirements of 6.8.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
d. When pig traps are left offline, a path for thermal pressure relief, complete with
suitable discharge, shall be included to protect against temperature and pressure
changes.
e. Air that may have been introduced into a pig trap from loading pigs or spheres
should be removed before repressurising the pig trap. Removal can be achieved
through direct gas or liquid purging or with nitrogen.
f. Pig trap door seals shall be tested before the pig trap is left unattended.
g. Sour gas or wet gas service traps should be left purged and depressurised.
2. Competency of personnel.
d. For managing risks associated with pig trap operations, purging shall not be taken in
isolation to the other mitigation measures available. See Table 1.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Product Comment
Sour gas Purge to bring toxicity levels down.
Chemicals Product specific - purge if highly flammable or toxic.
Dry gas (sales gas - water Purging can be effective, but should be site specific, as it
and hydrocarbon liquid dry) depends on frequency of operation and introduces new
risks. Purging needs a risk evaluation.
Wet gas (hydrocarbon Limited effect depending upon pig trap design.
liquids and water present)
NGL/gas condensate Limited effect depending upon pig trap design.
Aviation fuel Purging has limited effect, as it is difficult to remove
hydrocarbons. N2 may introduce additional risks.
Multi products Purging has limited effect, as it is difficult to remove
hydrocarbons. N2 may introduce additional risks.
Live crude Light oil flush followed by water flush.
Stabilised crude Water flush.
Pyrophoric material Purge and keep wet.
Radioactive scale Flush and use containment.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
5.1. General
The following design requirements shall be considered for pigging:
a. Strategy for selecting equipment should be developed early in the project to ensure that
equipment will operate as intended (pig compatibility with wyes and tees, etc).
b. Design of pig trap facilities should include input from operations personnel.
c. Type of pigging activities required (construction, operation/inspection/maintenance,
shutdown, or repair).
d. The beginning and end of a pipeline shall have pig launchers and receivers. Intermediate
pigging station requirements should be dictated by changes in pipeline diameter, pig driver
cup wear, and the quantities of solids or liquids likely to build up in front of a pig.
e. Type of product, including any contaminants or additives.
f. Minimum and maximum design velocities for oil and gas service are driven by pressure drop,
noise, and vibration. The optimum pig speed is typically 1 m/s to 3 m/s (3 ft/s to 10 ft/s).
aRelative position and distance between valves, tees and/or laterals, type of
bends (cold, heat inducted, fabricated), and bend radii.
h. Pipelines should be designed to allow deployment of isolation pigs for safe pipeline and
facilities maintenance.
i. Proven capability of a multidiameter pig to pass through pipeline system if significant bore
changes are present in the pipeline system.
j. Potential for enhanced internal corrosion if the pipeline requires frequent use of scraper
pigs.
k. Use of temporary tankage to collect debris.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
f. Wyes shall have a demonstrated capability for passage of inspection pigs (i.e., test at
full scale before using the pig in the pipeline).
g. Barred tees
1. Barred tees shall be designed such that the barring does not cause excessive
stresses at the junction of bars and tee crotch area as the tee dilates under
pressure.
2. A minimum of two guide plates should be used to prevent the pig from
entering the branch pipe.
3. Guide plates shall be welded across the tee branch pipe and along the flow
direction to prevent pigs from becoming stuck at the junction or from being
wrongly diverted with the flow
4. Welds shall be ground to avoid stress concentrations where tee branch pipe
connects to main pipe and where guide plates are welded to and tapered
along blend radius.
5. Guide plates and weldments shall be smooth and free from sharp edges to
prevent damage to pipeline pigs.
6. Guide plate thickness and plate to plate spacing varies depending on tee
branch size. A nominal guide plate thickness of 9 mm to 19 mm (0,375 in to
0,750 in) and guide plate spacing of 64 mm to 76 mm (2,5 in to 3,0 in) are
typical.
7. Optimum guide plate spacing is equidistant from adjacent plates and tee
branch pipe walls.
8. Figure 1 provides barring design details.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
NOM. NO. OF
T H
PIPE SCRAPER
IN. (MM) IN. (MM)
SIZE BARS
6” 2 ⅜ (9.5) 1 (25.4)
8” 2 ⅜ (9.5) 1 (25.4)
NOTES:
• MAX. CLEARANCE = 6 mm (¼”) AND MIN. CLEARANCE = 0.
• SCRAPER BARS SHALL BE EQUALLY SPACED OVER THE INTERNAL
DIAMETER OF THE TEE.
• SCRAPER BAR MATERIAL SHALL BE THE SAME MATERIAL AS THE TEE.
• MATERIAL SHALL BE APPROPRIATE TO PIPELINE DESIGN CODE
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
b. Cassette and cradle pig handling equipment shall be designed and installed as an
integrated part of the trap to preserve its integrity as a pressure vessel.
6.1. General
a. Design of pig trap facilities shall include input from operations personnel and take
account of layout, access, lighting, equipment handling, cleaning, etc.
b. Typical pig launchers should be configured as shown in Figure 2 and pig receivers as
shown in Figure 3.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Horizontal Launcher
Vent
Vertical Launcher
Balance
Kicker
Line Relief
Line
Valve
Concentric Reducer
Pressurising Kicker
Line Valve Tra
p
Sump or Purge
Isol
Closed Connection
atio
Drain Tel-Tale Vent
n
Valve
Isolation Val
Valve
Bypass
Valve
Chemical Injection
ESDV
Valve
Main Line
TRAP ISOLATION VALVE
Typical Lengths
LONGEST ILI PIG
XI
TO CONFIRM
PIG ENGAGED XI
TO CONFIRM
PIG CLEARED
TRAP VALVE
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Horizontal Receiver
Bypass Valve
Balance Line
Relief
Valve
Vertical Receiver
Bypass
Line
Balance
Line
Pressurising Bypass
Line Valve
Trap Isolation
Sump or
Closed
Valve
Drain
Tell-Tale
Valve
Isolation
Valve
Bypass
Valve
Chemical
Injection
Valve
Typical Lengths
TRAP ISOLATION VALVE
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
c. In addition to the factors for pipeline design, in 5, design of pig traps should
incorporate the following:
1. Applicable design codes.
2. Service conditions.
3. Minimum temperature.
4. Physical interface with pipeline (e.g., insulation flange).
5. Types of pigs to be run.
6. Pigging schedule.
7. Materials of construction (compatibility with product, brittle fracture).
8. External loadings (from pipework, particularly subsea).
9. Operating cyclic loading and nozzle reinforcements (e.g., as a result of
repeated trap pressurisation and depressurisation).
10. Structural supports and lifting lugs.
11. Wind and seismic loadings.
12. Snow and ice loadings.
13. Blast loading, if applicable.
14. Transportation loads.
15. Pig handling systems (e.g., lifting gantry, pig trays).
16. Permanent or modular skid mounted unit.
17. Trap closure mechanism.
18. Barrel venting/draining rate.
19. Volume of debris (e.g., wax) to be removed and capable of being retained in
the trap.
6.3.1. General
a. Pig traps shall be designed to allow access to the pipeline for inspection and
maintenance.
b. Pig traps shall generally be:
1. Located based on overall site risk assessments, considering potential release
of hydrocarbons, potential for ignition, and classification of areas.
2. Adjacent to each other for ease of pigging operations.
3. Orientated with their end closures pointing away from personnel and critical
items of equipment.
c. Suitable access space should be provided beyond the end closure door for
pig handling.
d. Suitable access space should be provided for maintenance of equipment.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
e. The trap should normally be horizontal, with vertical traps used if space is a
premium.
f. The elevation of the bottom of the end closure on horizontal pig traps
should be approximately 700 mm (28 in) and not more than 1 100 mm
(43 in) above the working surface to provide sufficient room to slope the
drain lines, as well as facilitate easy handling of end closure and pigs.
g. A platform shall be provided adjacent to any equipment (e.g., valve, pig
signallers) that is:
1. More than 1 500 mm (60 in) above grade (centre of the handwheel
in the case of a valve).
2. Used during pigging operations and/or for maintenance.
h. Consideration shall be given to the requirements for handling of
contaminated pigs and displaced solids.
i. Pig trap layout should be such that operation and maintenance of
equipment, valves, and instruments shall be possible without temporary
ladders and scaffolding.
j. Access ways shall be provided to and from pig storage area.
k. Pig traps shall drain by gravity into appropriate drainage area.
l. Consideration should be given to potential blockage of permanent drains
and tanks.
m. If a drain system is not available, provision shall be made for waste to be
collected for disposal to designated disposal area.
n. Adequate lighting shall be provided for pigging operations if 24 hr
operations are required.
o. Spading is not recommended as a regular method of providing positive
isolation of the launcher/receiver vessel.
p. Protection of door and locking mechanism from the elements/weather
should be considered for traps in exposed locations and may be subjected to
sea spray or debris from drilling operations.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
e. Welded supports, if used, shall comply with applicable pipeline design codes.
f. If there would normally be a potential for corrosion occurring under clamps,
isolation material shall be used between clamp and pipe and provisions shall
be made to facilitate inspection.
g. Piping supports may be fixed if design calculations indicate that sufficient
flexibility is incorporated in pipework to compensate for axial and transverse
movements of trap.
h. Electrical isolation joints, if used, shall allow sufficient movement to avoid
stressing of joint above its design limit.
i. Supports may need to be electrically isolated if isolated joints are not used.
j. Supports should be positioned such that pig trap valves can be removed for
maintenance or replacement without removal of barrel.
k. Lifting lugs and trunnions shall comply with ASME VIII, DIV 2
l. Launchers and receivers shall be bonded into earthing (grounding) grid for
facility. Integrity of the pipeline cathodic protection system shall be
maintained.
m. Electrical surge arrestor installation should be considered for insulation joints
in launcher/receiver pipework.
6.5.1. General
a. Pipework not designed to the pipeline code should comply with ASME B31.3.
b. Closed drain systems should be designed to handle debris flushed from pig
traps.
c. Pipework connections should be flanged to allow maximum flexibility during
commissioning and future modification, if required.
d. Pipework should be a minimum of 50 mm (2 in) for robustness. Sizing of
drains, vent lines, and pressure gage tappings shall take account of trapped
volume, phase of product, and risk of blockage.
e. For pipelines above 350 mm (14 in) and any prone to waxing or other
blockage, consideration shall be given to using 100 mm (4 in) connections off
trap to first valve, even if it is reduced thereafter.
f. System interlocks
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
e. Pig traps can contain air or air/hydrocarbon mixtures, which shall be taken
into account if connecting to flare systems.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
the length of the longest pig anticipated to confirm receipt of the pig
and that the pig has cleared the valve.
4. An indicator should be provided upstream of the main pig trap
isolation valve to confirm arrival of the pig at the installation.
6.6. Valves
6.6.1. General
a. Double block and bleed isolation is required for any pigging operation.
Preference is always for two separate pig trap isolation valves, especially for
pipelines in which pigging is a frequent activity or critical to ongoing
operations and failure of a seal cannot be tolerated.
b. A strategy shall be developed to facilitate maintenance or replacement of pig
trap isolation valves.
c. Isolation of the main pig trap should be designed to facilitate maintenance
and/or future modifications to the pig trap and pig trap isolation valve
without a pipeline shutdown.
d. Appropriate valve seats shall be selected for the particular service conditions.
f. Isolating valve shall be installed on bypass line side for tight shutoff of the
pressurising line, and the throttling valve shall be installed on the balance
line side to control the flow in the pressurising line.
g. A balance valve shall be provided in the balance line such that flow can be
diverted behind the pig by closing balance valve.
h. Drain valves for receivers shall be quarter turn valves having a high degree of
abrasion resistance, such as tungsten carbide coated ball valves and
stellite/carbide coated balanced plug valves.
i. Vent valves may be globe type but shall have a tight shutoff isolation valve
(soft seated ball or balanced plug) in series.
j. For gas service, blowdown valve shall be a tight shutoff ball or balanced plug
valve with a downstream globe valve or orifice restriction.
k. A 50 mm (2 in) isolating valve and a 50 mm (2 in) check valve shall be
installed in purge connection, if applicable. The isolating valve shall be
installed on the barrel side for tight shutoff of purge connection.
l. Chemical injection connection, if required, shall include a tight shutoff valve
of minimum diameter of 50 mm (2 in). Diameter of the connection shall be at
least 50 mm (2 in).
m. For LPG service, a double valve arrangement shall be installed in each drain
and vent. Second valve in a double valve arrangement shall be placed
sufficient distance apart from the first to provide an alternative means of
closing the line.
n. Unless isolating valves are provided on each side, modified ball valves having
a side entry point that allows the insertion and removal of pigs shall not be
used on a live system.
6.7.1. General
a. Trap barrel shall be capable of launching one and receiving two standard
cleaning or batching pigs.
b. For launchers, the length of the barrel shall be sufficient to launch the
longest ILI pig anticipated (See Figure 2).
c. For receivers, the length from the taper to the main valve shall be at least as
long as longest pig. Total length of the major and minor barrel should be
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
greater than the longest pig or the cleaning pig and maximum amount of
debris (see Figure 3).
d. For receivers, the length of pipe before expanding into the barrel shall be
sufficient to ensure that the ILI tool fully passes through the receiver isolation
valve.
e. The major barrel shall be at least D plus 50 mm (2 in) for D less than or equal
to 400 mm (16 in).
f. For larger diameter, the major barrel shall be at least D plus 100 mm (4 in).
g. The trap reducer shall be:
1. Eccentric design for horizontal traps without an internal tray or basket
and for inclined launcher traps (with the bottom of the entire barrel at
the same level).
2. Concentric design for vertical traps, inclined sphere receiver traps, or
horizontal traps with an internal tray or basket.
h. Internal diameter of the minor barrel (neck pipe) shall be the same as that of
the pipeline.
i. If a trap may be used for facilitating hydrotesting or commissioning, an
additional connection with a blind flange may be added.
j. Transitions in the internal diameter due to wall thickness variations greater
than 2,4 mm (0,094 in) shall be tapered to a minimum angle of 14 degrees to
the pipe axis to allow for the smooth passage of pig.
k. For horizontal receivers, barrel should be sloped (typically 1:100) down
towards the drain at the end closure to improve draining of liquids from
barrel.
l. Horizontal launchers should be sloped (typically 1:100) down towards the
pipeline.
m. Sleeves may be required to facilitate launching in concentric vertical traps or
if multiple module tools are used.
n. Sleeves may be used to facilitate launching of separate cleaning tools to
avoid the need to open the pig trap between launches.
o. Universal pig traps may be used in some locations. These can be used to
both launch and receive pigs.
p. Sleeves and specialist launching systems may be used to facilitate multiple
launches without the need to open and close pig trap between each launch.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
q. Length of the receive pig trap needs to be able to accommodate all pigs
launched together with any products or debris that may be removed.
r. If automatic sphering is intended:
1. Major barrel length for launching and receiving shall be based on the
number of spheres to be handled.
2. Launcher barrel shall be inclined at sufficient angle to allow spheres to
roll forward for launching and launcher barrel shall include retractable
launcher pins.
3. Receiver barrel shall be inclined at sufficient angle to allow spheres to
roll away from the minor barrel/reducer.
s. Sphere release mechanisms, depending on environment location and
pigging schedule, shall be of the mechanical finger, flap, or valve type.
6.8.1. General
a. End closure of new traps shall be designed in accordance with functional and
safety requirements of the pressure vessel code.
b. New trap closures shall have a double locking mechanism to prevent
opening of closure under pressure.
c. Recommended trap closures for new construction and replacement closures
on existing launchers and receivers are one of the following:
1. GD Engineering BANDLOCK2 type, which has a duplex stainless steel
conical band fitted between the door and neck to transmit loads
uniformly to the full 360 degree circumference of the neck.
2. Pipeline Engineering (PE) (UK) ROC which is similar in design to the
GD engineering closure.
d. Guidance on end closure selection and testing requirements is given in
Tables 3 and 4.
e. Closure mechanisms involving the use of external clamp rings and threaded
screws are not preferred but specific TDW, FAI, and LTS end closures are
acceptable. Guidance on the use of external clamp type closures, including
three acceptable vendors is provided in Annex B.
f. Corrosion resistant overlays shall normally be provided on sealing surfaces.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Size and pressure ≤ size and Size and pressure above those Size and pressure > 1,2 x size
pressure made before of same made before but < 1,2 x size and pressure made before or
design. and pressure. any new design.
GD, PE, and other Review track record. Check Design verified by scaling Full design review in
internal and design calculations. Design in previous designs. Review shall accordance with ASME VIII,
approved type accordance with ASME VIII, Div 1 include detailed design, Div 2 Part 4, including full
closures or 2, and App 24 requirements. stresses, strains, clearances, FEA of all parts, checking
Supporting calculations and FEA extrusion gaps by scaling. stresses, deflections,
to be included. Satisfactory Design verified by scaling. extrusion gaps, deflections
experience without calculations is Independent design review and fits. Independent design
NOT acceptable. Independent recommended. review required.
design review optional.
External tie rod Full design review in accordance Full design review in Not permitted unless agreed
type (non- with ASME VIII, Division 1, or accordance with ASME VIII, otherwise.
preferred option) ASME VIII, Div 2 with FEA. Tie Div 2 App 4, including full FEA
rods shall have redundancy, and of all parts, checking stresses,
design parameters of App 24 deflections, extrusion gaps,
(including minimum angles) to deflections and fits. Backup
be adopted. (See design section). design in accordance with
Satisfactory experience without Div 1 App 24 also.
calculations is NOT acceptable. Independent design review
Independent design review required.
required.
Note:
Term “size and pressure” refers to product size in mm/inches and pressure in bar/psi.
d. End closure safety and operating gear shall be designed to ensure safety in
operation and comply with the following:
1. Failure of any single component of the locking and holding
mechanism shall not lead to release of closure.
2. Locking mechanism shall incorporate redundancy of critical
components.
3. At least one positively located safety bleed device shall be provided
on the door to relieve any residual pressure before the door can be
opened.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Size and pressure ≤ size and Size x pressure < 1,2 x size and Size and pressure > 1,2 x size and
pressure made before. pressure made before. pressure made before.
GD, PE, and Hydrotest in accordance Hydrotest in accordance with the Hydrotest in accordance with the
other internal with the design code design code. Check for any design code, with strain gages in
type closures followed by a leak test at a shakedown and dimensional critical stress locations. Check for
minimum of 1,1 x design changes after pressure test. Check any nonelastic behaviour during
pressure at least two cycles, dimensions for any deformation test and for any inconsistencies
using water for liquid service and clearances against design between strain gage and
traps and gas valves. After hydrotest, leak tests at theoretical stress values. Check
(nitrogen/helium) for gas 1,1 x design pressure, 5 cycles for any shakedown and
service traps. Check seals minimum, using water for liquid dimensional changes after
and all moving parts for service and gas (nitrogen/helium) pressure test. Check any
extrusion and degradation for gas service traps. Check seals deformation and clearances
after test. and moving parts for extrusion and against design valves. After
degradation after test. hydrotest, leak test at 1,1 x
design pressure, 10 cycles
minimum, using water for liquid
service and gas (nitrogen/helium)
for gas service traps. Check seals
and moving parts for extrusion
and degradation after test.
External tie Hydrotest in accordance Hydrotest in accordance with the Not permitted.
rod type with the design code. Tie design code, with strain gages in
(nonpreferred rod(s) to be strain gaged critical stress locations including tie
option) during hydrotest, and strain rods. Note: redundancy device to
values judged against design be removed during strain gage test
values. Note: redundancy of tie rod(s). Check for any
device to be removed during nonelastic behaviour during test
strain gage test of tie rod. and for any inconsistencies
After hydrotest, leak test at a between strain gage and
minimum of 1,1 x design theoretical stress values. Check for
pressure at least 5 cycles, any shakedown and dimensional
using water followed by changes after pressure test. Check
5 cycles on gas any deformation and clearances
(nitrogen/helium) for gas against design valves. After
service traps. Redundancy hydrotest, leak test at a minimum
device removed for water of 1,1 x design pressure at least
tests, and installed for gas 10 cycles, using water followed by
tests. Check seals and all 10 cycles on gas (nitrogen/helium)
moving parts for extrusion for gas service traps. Redundancy
and degradation after each device removed for water tests and
cycle. installed for gas tests. Check seals
and moving parts for extrusion and
degradation after each cycle.
Note:
Term “size and pressure” refers to product size in inches/mm and pressure in psi/bar.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
6.9.2. Fabrication
a. Fabrication shall comply with applicable pipeline code.
b. Fabrication shall take into account tolerances required for door closure,
timing of any required heat treatment, and machined finish.
c. The inside of the trap shall be free from obstructions that could prevent the
free rolling of spheres or travel of pigs or carriers.
d. External nonmachined surfaces shall be coated.
e. Machined surfaces shall be suitably coated to prevent corrosion and shall be
protected against damage during transport, storage, and installation.
f. If the end closure is manufactured by a different vendor than the pig trap
fabricator, the end closure shall be fully inspected in accordance with
manufacturer recommendations to ensure that the end closure functions
correctly and has not been damaged.
6.9.3. Marking
a. A stainless steel plate shall be fitted to end closure with permanent marking
stating that the operator shall refer to the manufacturer instructions for the
safe operation of the closure.
Each pig trap shall have a nameplate with the following
information:
1. Name of the pipeline in which the trap is installed.
2. Vendor name.
3. Order number and date.
4. Year of manufacture.
5. Design pressure.
6. Maximum and minimum design temperatures.
7. Test pressure.
8. Weight empty.
9. Class of flange connections.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
b. Parent material for the main barrel, reducer, and neck shall be subject to
100% visual inspection.
c. Radiographic examination should be by X-ray.
d. Ultrasonic examination shall be used for pig traps intended for onerous
service and for wall thickness over 30 mm (1,2 in).
e. Surface examination shall be by wet magnetic particle.
f. End closure, mating clamp and flange machined surfaces, door hinges, hinge
attachments, and locking mechanisms shall be subject to magnetic particle
inspection (or dye penetrant inspection if fabricated from nonmagnetic
materials).
g. Hydrotest shall be performed with clean fresh water at a temperature not
lower than that permitted by the code.
h. Duration of the test shall comply with applicable code and be at least 1 hr.
i. Any gaskets to be supplied with the pig trap shall be replaced with new ones
following the hydrotest.
j. Closures intended for gas service shall be subject to a gas leak test of 1,1
times design pressure as part of the factory acceptance test and following
the hydrotest.
k. Leakage rates shall be assessed using helium trace and acceptance criteria
shall be 0,14 m3/yr (5 scf/yr).
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
7. Special applications
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Annex A
(Informative)
Recommended pig trap closures
Table A.1 and Table A.2 are current recommended pig trap end closures and their
potential operation range based on information provided by vendors.
a. Cells marked with “” indicate that a design is available with supporting
design documentation and test verification data.
b. Cells marked with “?” indicate that a design is available, but further
verification and testing is required.
c. Cells marked with “X” indicate that no design is currently available.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Annex B
(Informative)
Tie rod type design pig trap closures
B.1.1 Introduction
a. There have been isolated failures of pig trap doors on Equion Energy Limited
assets. Most of the failures have been with closures that have external tie
rods securing the doors. While they are not the preferred type, it is likely they
will remain in service as such issues with potential enclosure failure need to
be noted and addressed. This Annex summarises the findings.
b. The tie rod type closure can work reliably, including applications on high
pressure and large diameters, as verified by the reliable operation of several
1 m, 34 MPa (42 in, 5 000 psi) rated closures.
c. The closure designs manufactured by Fauske & Associates, Inc. (FAI), Ledcor
Technical Services (LTS), and T.D. Williamson (TDW) are used in a number of
Equion Energy Limited facilities. A detailed design review was conducted to
clearly understand the designs, potential limitations, and compliance with
this LPT.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
e. If nonlisted materials are used, the designer generally uses the methods in
ASME for derivation of allowable stress, even though the materials are not
listed.
f. ASME only permits use of listed materials. This means that closures made
from nonlisted materials cannot be “U” stamped. The LTS closure on Thunder
Horse is designed this way (i.e., using nonlisted materials but deriving stress
intensity values from the methods used in ASME Boiler and Pressure Vessel
Code, Section II).
g. A review of accident reports indicated that none of the tie rod type closures
that failed have had redundancy devices fitted.
h. Failures have been the same common to one another: improper makeup of
the clamp and/or wear. If the clamp is not made up properly, the door
separates from the barrel under pressure. The change of door position loads
the clamps further and often changes the contact angle between hubs and
clamp, which in turn increases the tie rod load. If the tie rod then stretches,
the clamp opens further, leading to failure and eventual door opening (see
sketches in B.1.6.2).
i. If Equion Energy Limited stipulates that redundancy is required, most
vendors can offer some device, but design of these may be crude and/or not
fully developed.
j. A carefully designed redundancy device could incorporate a system that
ensures proper assembly of the tie rod components. Device should be
designed such that, if the tie rods and parts are not correctly positioned, the
redundancy device would not engage.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
a. Again, there are two design concepts: designs that have preloaded tie rods
and those that have low or zero preload. The need for preload depends
heavily on the nature of the design of the clamp and the type of seal used.
b. If pressure is applied to the closure, generally, two things occur, the closure
opens slightly and tie rod becomes loaded by the pressure. The degree of
loading in the tie rod due to pressure depends greatly on the angle of the
clamp faces, and these vary from design to design.
c. Clamp angles
1. The greater the clamp angle, the greater the tie rod load due to pressure, with
theoretically zero load if the angle is zero.
2. The clamp angles are acting as a gear, with small angles providing high load
and small movement, with minimum risk of back driving while large angles
give bigger movement, lower loading, and higher risk of back driving.
3. At an angle of zero, there is no risk of back driving, but there is no
compression applied to the faces by the clamp.
d. Metal seals seem to require a larger angle that provides a compressive load
over a longer movement such that the gasket compresses adequately as the
joint is assembled.
e. Ratio of clamp movement to door movement is approximately 2:1 on a
15 degree angle and approximately 10:1 on a 3 degree angle.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
f. Designs that have small angles, like the FAI design, only require sufficient
preload to ensure that the joint stays closed by the action of pressure. This
will be a fairly small angle, and the joint does not require any significant
movement to close, only the small compression of the O-ring.
g. The TDW design has no requirement for any preload. The joint is mounted
on a radial spigot, so even if the joint separates, the O-ring should still
function.
B.1.6.1 General
a. The clamp angle dictates the type of loading on the door and tie rod. The larger the
angle, the higher geared is the translation from tie rod load to joint load.
b. At zero degrees, there is no translation from tie rod load to joint face. See the
following table.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
If angles are large, there is a greater risk of back loading of the tie rod from pressure.
This means that LTS design inherently has a greater requirement for the redundancy
device than FAI and or TDW designs.
a. Tie rod designs are susceptible to the same basic problem, although the detail of
the problem varies from design to design.
b. If the joint is worn, damaged, too weak, or not made up correctly, there is a very
real risk that the design contact angles are changed. In most, if not all cases, the
contact angles increase significantly as pressure is applied, and the tie rod load
increases as a result.
c. Typical examples are as follows:
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Clamp in contact with outside of hubs, on radius, Misalignment causing localised deformation: increasing
increasing angle (topping out). angle.
Clamp in contact with inside of hubs, on radius, increasing Deformation increasing angles: weak design.
angle (bottoming out).
d. From these four load cases, it can be seen that there is usually a tendency for the
contact angle to increase above the design value.
e. In each load case, if pressure increases the tie rod load, the joint could separate
further.
f. As the joint separates, the angle may increase, further loading the tie rod, opening
the joint further until eventual release of the closure.
B.1.6.5. Materials
a. The use of the ASME Boiler and Pressure Vessel Code, Section VIII design method in
combination with nonlisted materials is fairly commonplace for high strength
materials, particularly on pipeline components.
b. The approach taken by LTS is reasonable (i.e., using a stress intensity of the lesser of
UTS/3 and 2/3 times yield stress). Additional safeguards should be taken on the
material, such as ductility and elongation.
c. In localised areas and under certain load conditions, ASME Boiler and Pressure
Vessel Code, Section VIII, Div 2, permits 1,5 and 3 times the stress intensity value
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
(see Figure 4, 130.1). The material needs to have sufficient ductility and elongation
to locally allow shakedown and plastic deformation without failure.
d. As a minimum Charpy values should form part of the material specification, as
should a minimum elongation value, suggested to be greater than 20%.
Recommended Charpy values (in Joules) are yield strength (in N/mm2)/10.
e. In some cases, vendors take a pseudo material approach to design. They use high
strength materials, typically F60, which is not listed, but for the purpose of the
calculations, use the allowable stresses of a near equivalent material, such as
ASTM A350 LF2.
f. As many of the ASTM materials have no maximum values to strength, it is possible
to recertify a F60 type material to LF2 requirements as permitted in UG10. This
permits closure to be “U” stamped. The FEA then may be assessed using the actual
material properties.
a. Ideally, use “listed” materials for the clamp, or use the pseudo materials described
in B.1.6.5.
b. Ensure that material specifications have ductility and elongation requirements,
particularly if non listed materials are used.
c. Include the redundancy device on tie rod designs. The risk of the joint failing
incrementally would be greatly reduced if an additional constraint is provided.
d. Use the ASME Boiler and Pressure Vessel Code, Section VIII, Division 1, Mandatory
Appendix 24, design method. There is a minimum design angle requirement in this
design, even if the clamp angle is zero. This provides some safeguard against tie
rods being loaded by localised deformations.
e. Conduct FEA on the design to check for deformation on the joint and to see
whether angle of contact changes significantly as the joint deforms (i.e., check for
weak clamp as described previously).
f. Ensure clamps that require a preload have a suitable preloading device fitted which
can provide adequate preload but without overstressing.
g. Provide a strain gage on the tie rod(s) during hydrotest/function test to show that
actual strain values are similar or less than design/predicted values. For preloaded
designs, the strain should not change significantly if pressure is applied, so it may
be necessary to measure strain in relaxed, preloaded, and pressurised conditions.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
h. Use realistic coefficients of friction in the design and use realistic lubricants during
test. In general, the lower the coefficient of friction between clamp and hub, the
greater the load in the tie rod(s).
i. For minimising the load transferred from clamp to tie rod, it is preferable not to use
grease or lubricant. Some designs with metal seals, such as the LTS design,
probably need lubricant to ensure that adequate gasket compression is achieved as
the tie rod is preloaded.
j. Provide some arrangement that precludes the incorrect assembly of the clamp and
hubs. Ideally, this should be included in the redundancy device and/or the safety
interlock system such that the assembly cannot be pressurised until correct
assembly is ensured.
k. Check for incorrect machining, wear, and any other mechanism that could cause the
clamp to bottom or top out on the hubs. In factory test, consideration should be
given to “blueing” the surfaces of the clamp and hub to check for even contact.
ClampTec™
D2000
Annex C
(Informative)
Onshore gas terminal incident at 16 in sphere receiver
C.1. Incident
a. While unloading spheres from a 400 mm (16 in) receiver on 25 October 1983, an
operator fell from the access platform as two spheres were ejected by captive gas
pressure.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
b. Fortunately, the operator was not hit by the receiver door or the spheres, the latter
causing structural damage to steelwork and piping before coming to rest 15 m and
50 m (50 ft and 160 ft) away, respectively.
c. The operator did sustain minor injuries as a result of his fall from the access
structure.
a. The terminal receives gas from offshore gas production platforms through 400 mm
(16 in) and 600 mm (24 in) pipelines. As the gas contains a high proportion of liquid
hydrocarbon condensate, it is necessary to pass spheres through the pipelines at
frequent intervals to prevent undue buildup of liquid in the pipelines. The hollow
spheres are pressurised with a water/glycol mixture up to 830 kPag (120 psig) to
obtain a close fit within the pipelines. The inflation valves are capped off with screw
plugs and O-ring seals.
b. Insertion of spheres into the pipelines is performed at the production platforms,
using purpose built launchers designed to contain a number of spheres held under
pipeline pressure (approximately 4 800 kPag [700 psig]) that can then be launched
individually to meet production requirements. Sphere receivers are installed at the
shore (terminal) end to collect the spheres. These are designed to be isolated and
vented down and the spheres are removed to atmosphere without affecting the
main pipeline operation.
c. At the time of the incident, two spheres had passed into the 400 mm (16 in)
receiver, and attempts were made to isolate the receiver from the main pipeline.
d. After several attempts, isolation was apparently achieved, and the receiver was
vented to atmospheric pressure at its downstream end. Depressuring was
confirmed by operating a bleed screw on the receiver door, and the operator
proceeded to open the door. The spheres were then ejected in the manner
described.
e. Subsequent investigation indicated that gas had entered the spheres from the
pipeline through leaking plug seals, causing them to expand in the enlarged
diameter of the receiver as it was depressured, maintaining a tight fit.
f. Gas had also continued to pass into the receiver through the shut isolation valve,
thus maintaining pipeline pressure in the section of receiver upstream of the
spheres. Unfortunately, this pressure was sufficient to dislodge the spheres just as
the door was opened.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
g. The successful insertion, passage, and collection of spheres had been performed in
the 400 mm (16 in) line between gas production platforms and the terminal for
nearly 20 yr.
h. Pressurisation of the spheres in this case is thought to be a combination of slight
leakage of the plug seals on the spheres themselves and the fact that the spheres
had been held in a fully pressurised sphere launcher for about a month.
i. It is noteworthy that the operator followed the established procedure for
depressuring and venting the receiver before opening the door.
C.3. Recommendations
C.4. Comment
a. This incident highlights the necessity to take particular care if breaking containment
at sphere or pig receivers and launchers.
b. Fortunately only a minor injury occurred as a result of this incident.
c. Two operators were killed in the U.S. when attempting to open a sphere launcher
door before ensuring that the launcher had been correctly depressured.
d. Theoretically, once the spheres are full of glycol/water mixture there should be no
possibility of gas ingress into the sphere from the outside. The external pressure
applied to the sphere acts through the flexible wall onto an incompressible sphere
of liquid. The design is such that it is impossible to hydraulically fill the sphere, and
a compressible vapour space is always present that is capable of being pressured
up from the outside should the plug seal leak. If the external pressure is released,
any increased internal pressure becomes trapped, resulting in a larger sphere
diameter. It is important, therefore, that spheres are not left in pressurised
launchers for excessive lengths of time to preclude the potential for gas entering
the spheres in the manner described. In addition to modifying their procedures in
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
this respect, the terminal management are also pursuing the matter with sphere
manufacturers with a view to achieving an engineering solution to this problem.
e. Sphere launchers and receivers that are permanently installed in a pipeline system
need to be designed to withstand the maximum operating pressure of the system.
Since launchers and receivers have to be opened while the pipeline is in service,
they should always be installed in conjunction with twin high integrity isolation
block valves and have suitable valved connections to allow the flow to be directed
into or out of the launcher/receiver and to allow the launcher/receiver to be
drained. Two vents to atmosphere are essential (one at each end of the
launcher/receiver) and, as an additional safeguard, there should be some form of
device that prevents the door from being opened until the pressure has been fully
relieved. It also needs to be possible to prime the launcher/receiver under
controlled conditions.
f. An incident also occurred in which an instrument mechanic attempted to release a
stuck sphere from a receiver using compressed air. The sphere was eventually
ejected and travelled a distance of 230 m (750 ft), hitting various obstacles in its
path. The report of that incident discusses the dangers of incorrect operation of
sphere launchers/receivers.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011
Bibliography
EQUION
[1] LTP-0038, Valves for Pipelines.
Pigging, Pig Launchers, and Receivers (Rev:01) Fecha de Impresión: Noviembre 30/2011