Professional Documents
Culture Documents
1. Outline
1.1 This document is request for quotation of construction work to Subcontractor.
LOW and Subcontractor shall discuss about contractual coverage.
1.2 Schedule
Construction period 2019/03/15 ~ 2019/05/30
for detail , please check attached schedule.
1.3 Description of work
1) Area
✘ Outdoor Indoor In clean room
2) Division for detail , please check attached document “Division of Work”
✘ Installation ✘ Piping Insulation Civil work
✘ Scaffolding ✘ Filing work ✘ Scrap work ✘ Help LOW commissioning work
✘ Instrumentation and power supply cable work Purchase materials , based on BQlist
✘ Site office , Rest space ,Praying room , etc. ✘ Other
3) Standard
✘ JIS ✘ ANSI ✘ DIN ✘ Other
1.6 Quotaion
1)In quotation , below point shall be described.
✘ Number of workers , it shall be divided as type of worker
✘ Crane and folklift specific , schedule(how many times you estimate )
✘ Price of each construction work ( material , installation , piping , electric , etc)
3)Submittal
✘ e-mail : devira.iswanda@lautanorganowater.com
✘ e-mail : linda.ijo@lautanorganowater.com
✘ e-mail : bagus.setiawan@lautanorganowater.com
✘ Graha Indramas 5th Floor, Jl. A.I.P.K.S.Tubun Raya No.77, Jakarta 11410-Indonesia
Tel:+62-21-29940900
FAX:+62-21-29940901/2
2. Guarantee
2.1 Guarantee item
Subcontractor shall warrant workmanship and materials(pipe , fitting , etc.) they prepare.
3. Attached document
3.1 Divisiton of work ← define each work scope , please confirm it carefully.
✘ Mechanical ✘ Electric Insulation Other
3.2 Drawing
✘ P&ID ✘ Machine Layout ✘ Piping assembly drawing
✘ BQ list ✘ Drawing of panel ✘ elementary wiring diagram
✘ Drawing of main equipment , tank , instrument ,unit ←if you need more , please request us.
✘ document in which is described about specific of pipe , gasket , fitting , bolt , nut ,etc.
✘ Doccument list
3.3 Schedule
✘ LOW progress schedule ✘
3.4 Other
✘ Safety cycle on site ✘ Procedure for each inspection required by LOW
4. Special Note
Additional works and material purchase shall not be done "without" LOW SV approval and its signature.
4.1
LOW reject Subcontractor's additionl bill without LOW SV approval and its signature.
So Subcontractor have to get LOW SV approval and its signature before they start additional work.
4.2 A : Lamella, Belt press, dissolving units, gas flare Assembly at site
B : Stage structure of Screw press indluded assembly at site
C : Piping rack included assembly at site, Manufacturing at Low workshop
4.3 Prefabricated pipe is in Subcontractor scope. But only SGP/RL is supplied by LOW.
To purchase material , not described in Bqlist , and assembly work is in Subcontractor scope.
Purchase Of This Project : PT Pembangkit Jawa Bali (PJB) Prepared by Check by Approve by
Owner Of This Project : PT Pembangkit Jawa Bali (PJB) Ade Roy Bagus S Bagus S
Name Of This Project : Waste water Treatment Plant & Water Treatment Plant Project No : 1806-HAK02 - 1807-HAK03
Date Of Issue : Rev : 0 Sheet 1 of 4
Document No : LOW - SW - M - SR - RFQ -HAK02/HAK03- 001
SC ME : Sub Contractor Mechanical Electrical Client Customer / Purchaser / End User
LOW : Lautan Organo Water VDR Vendor / Supplier under LOW
SC CVL : Sub Contractor Civil
A) INSURANCE
1 Inland Transportation Insurance O
2 Site Erection all risk Insurance O
3 Employee, Workers Insurance O O Jamsostek, BPJS or equivalent insurance
4 Construction Equipment / tool Insurance O Including Surat Ijin Operasi (SIO) from Disnaker
5 Vehicle Insurance O O
B) SITE OFFICE & WORK SHOP etc.
1 Site office for Lautan Organo Water Container 40ft O Loading & Unloading by SC
2 Site office for Subcon MP/ LOW Vendor
3 Laydown / Storage material & fabrication area including rest house for O O
workers
4 Ware house SC O
5 Ware house Lautan Organo Water 20ft O Loading & Unloading by SC
(to keep LOW purchased expensive equipment)
6 Praying room O
7 Toilet for LOW and SC ( Common Facilities) O
8 Mess hall ( Common Facilities) O
9 Car parking space ( Common Facilities) O
10 Smooking shelter ( Common Facilities) O O
C) TEMPORARY ELECTRICITY 1 Primary electric source for construction & fabrication work O O SC prepare power coble
O O electric source is coming from client, SC shall provided panel box
(FABRICATION AND UTILITY) 2 Secondary electric source LOW and SC complete with MCB / Breaker
(For shelter, office tools and pre comissioning)
D) SITE MANAGEMENT
O Project Construction Reporting, Update status material from site, Non
1 Project Management Conformance Report , etc
include Fee that might show up for NGO and other's individual person
such as hoodlum, bandit with inside or out side project location
3 Transportation, Loading & Unloading within site O
10 Site Investigation O O
11 Access Road Within Site O
12 Field Assembling Yard Area (Fabrication yard area) O
Security control for LOW , vendor's equipment (around site office , storage O
13
area , laydown area)
O O For storage area LOW will discuss with client for the location and
14 Equipment and raw materials storage at site submitt proposed location at site
Page 3 of 7 664311070.xlsx
Request For Quotation ( RFQ) of Construction Work
Purchase Of This Project : PT Pembangkit Jawa Bali (PJB) Prepared by Check by Approve by
Owner Of This Project : PT Pembangkit Jawa Bali (PJB) Ade Roy Bagus S Bagus S
Name Of This Project : Waste water Treatment Plant & Water Treatment Plant Project No : 1806-HAK02 - 1807-HAK03
Date Of Issue : Rev : 0 Sheet 1 of 4
Document No : LOW - SW - M - SR - RFQ -HAK02/HAK03- 001
SC ME : Sub Contractor Mechanical Electrical Client Customer / Purchaser / End User
LOW : Lautan Organo Water VDR Vendor / Supplier under LOW
SC CVL : Sub Contractor Civil
E) DOCUMENTATION 1 Drawing
(M&E) a. P&ID O
b. Piping and Equipment lay Out O
c. ISOMETRIC drawing O
d. Piperack & pipe support drawing O
2 Erection Manual O O
3 Progress Report
SC leader will assist LOW team during preparation of project reporting
a. Weekly construction report O O
( Including data and others information that required at site)
b. Weekly construction schedule O O
4 Method of Statement / Erection Report O O
5 QA/QC system and Manual Rule of inspection checking will conduct by LOW and LOW will give
O O guidance to QC SC
6 QC Record
a. HDPE/FRP tank leak test O O
b. Pump & Blower installation O O Format recording will conduct by LOW and LOW will assist by QC SC
c. Piperack installation O O
d. Pressure test piping O O
7 Non Conformity Report O This document will issue by LOW team
Inspection, Testing and Plan (ITP) for installation of rotating equipment,
static equipment, pipng,steel structure, etc O O
8 Site Instruction O
9 Preparation of Lifting plan for heavy equipment work: unloading, loading, LOW will prepare on this and it will discuss with SC leader to adjust as
handling, installation at site O O per actual site condition
F)
F) MATERIAL
MATERIAL SPECIFICATION
SPECIFICATION 9 Pipe, Fitting and interconnecting
1 Pipe sch 80 SMLS_A106_Galv O
2 Pipe sch 40 SMLS_A312-TP304L O
3 Pipe sch 10 SMLS_A312-TP304L O
4 Pipe sch 80 CVPC O
7 Pipe sch 40 PVC O
9 CS + RL O
10 Tubing SS316 O
Flange
1 JIS - 10K O If necessary depend on equipment connection from vendor equipment
2 ANSI O
3 Other (DIN ) O If necessary depend on equipment connection from vendor equipment
Gasket
1 EPDM O
2 EPDM + PTFE O
3 Viton O
4 PVC (soft) NA
5 Silicone rubber NA
6 non Asbestos O
7 Other ( Voltex, Spiral Wound Gasket etc)
Nut , Bolt ,Washer of Flange , U-bolt
1 Stud Bolt A193_Gr.B8M/A194_Gr.8M O
Page 4 of 7 664311070.xlsx
Request For Quotation ( RFQ) of Construction Work
Purchase Of This Project : PT Pembangkit Jawa Bali (PJB) Prepared by Check by Approve by
Owner Of This Project : PT Pembangkit Jawa Bali (PJB) Ade Roy Bagus S Bagus S
Name Of This Project : Waste water Treatment Plant & Water Treatment Plant Project No : 1806-HAK02 - 1807-HAK03
Date Of Issue : Rev : 0 Sheet 1 of 4
Document No : LOW - SW - M - SR - RFQ -HAK02/HAK03- 001
SC ME : Sub Contractor Mechanical Electrical Client Customer / Purchaser / End User
LOW : Lautan Organo Water VDR Vendor / Supplier under LOW
SC CVL : Sub Contractor Civil
2 For piping support at site and Unit from LOW Workshop (touch up) O Refer to document, MRT-DP00-P3GC-135142-Painting
Specification_R0_LOW
I) INSTALLATION 1 Electrical for erection work O electric source is coming from client, SC shall provided panel box
complete with MCB / Breaker
I.1: 2 Handling of Vendor's Supply items O
Mechanical
3 Check & Marking of Foundation for all mechanical equipment and tank and O O
Pump.
Positioning and Setting of Foundation high/Chemical anchor for all O O MMF tank, Pump, Blower, Dozing pump, MBP tank
4 mechanical
Page 5 of 7 664311070.xlsx
Request For Quotation ( RFQ) of Construction Work
Purchase Of This Project : PT Pembangkit Jawa Bali (PJB) Prepared by Check by Approve by
Owner Of This Project : PT Pembangkit Jawa Bali (PJB) Ade Roy Bagus S Bagus S
Name Of This Project : Waste water Treatment Plant & Water Treatment Plant Project No : 1806-HAK02 - 1807-HAK03
Date Of Issue : Rev : 0 Sheet 1 of 4
Document No : LOW - SW - M - SR - RFQ -HAK02/HAK03- 001
SC ME : Sub Contractor Mechanical Electrical Client Customer / Purchaser / End User
LOW : Lautan Organo Water VDR Vendor / Supplier under LOW
SC CVL : Sub Contractor Civil
10 Installation of inline instrument and valves which are installed together with O
equipment (including fixing anchor bolt, nut, washer, gasket and other
accessories for the instruments)
4 Prefabricated pipe / spool pipe with have purpose for temporary (flushing) O O
or permanent
I.3 : Electrical work All Instrumentation and power supply cable work (cable tray, conduit pipe ,
install instrument, positioning, levelling, marking, accessories, inspection…)
including pipe spool / connection that related to support instrument so it can For detail information ,
1 stand up and working with properly, Termination and test O Please check electrical document in which is described about
specific , procedure etc - Attached on bidding document
J) ASIST COMISSIONING
1 Filling media MMF, MBP O O pump for loading media by LOW
2 Install Name seal , sticker for vessel & Tank , equipment and pump Material sticker from LOW, installation will conduct by LOW
O O that will assist from SC
3 Install Name seal , sticker for piping O O Material sticker from LOW, installation will conduct by LOW
that will assist from SC
4 Install valve tag (indicate open or close) O O Installation will guide by LOW T&C team
5 Check inside part of CS tank, SUS tank, RC tank ( Opening man hole, etc) O O
10 Welding at site O
11 Touch-up of Tank, misc bracket O
12 Naming on Vessel & Tank Shell & piping ( spray or sticker) O
13 Valve Tagging (Hanging Type) O
K) COMPLETION 1 Clear Punch List O O
2 Working Tool for erection and QC work cover with certificate O
L) INSPECTION & TEST Insatallation inspection check position , verticality , height adjustment of all
1 tank and equipment O O
2 Hydrotest O
3 Piping line check inspection O O
4 Pressure test O
4 Welder Qualification Test O
5 Tool, Equipment and Consumable for installation inspection, and Hydrotest. O
This detail RFQ was understood and agreee by both party, if there is any potential issu that show up in the future but not mentioned in the document , both party agree to settle this on
discussion forum
Page 6 of 7 664311070.xlsx
Request For Quotation ( RFQ) of Construction Work
Purchase Of This Project : PT Pembangkit Jawa Bali (PJB) Prepared by Check by Approve by
Owner Of This Project : PT Pembangkit Jawa Bali (PJB) Ade Roy Bagus S Bagus S
Name Of This Project : Waste water Treatment Plant & Water Treatment Plant Project No : 1806-HAK02 - 1807-HAK03
Date Of Issue : Rev : 0 Sheet 1 of 4
Document No : LOW - SW - M - SR - RFQ -HAK02/HAK03- 001
SC ME : Sub Contractor Mechanical Electrical Client Customer / Purchaser / End User
LOW : Lautan Organo Water VDR Vendor / Supplier under LOW
SC CVL : Sub Contractor Civil
Page 7 of 7 664311070.xlsx