EIS Info3-Flow-Chart-Eia-Assessment-Approval-Process
EIS Info3-Flow-Chart-Eia-Assessment-Approval-Process
Key Notes
Tier 1 - Assessment on Referral Information Documentation is published at each stage of the assessment process
Tier 2 - Assessment by Supplementary Environmental Report (SER) Reasons for decision are also published at each decision point
Tier 3 - Assessment by Environmental Impact Statement (EIS) All timeframes are expressed as business days
TOR - Terms of Reference Public Comment - period may be extended in consultation with the proponent
SUPP - Supplement Range of 30-60 business days (determined by NT EPA) applies to public comment on draft EIS
15 days
DECISION referral
65 days
required and level
Tier 1 Tier 2 Tier 3
of assessment, and
finalise TOR or issue
SER direction (if EIS
not proceeding)
on TOR
Proponent Action - SER
15 TOR finalised
25 Public comment
115 - 145 days + Proponent time for EIS preparation + Supplement reparation
Proponent Action - EIS Proponent Action - EIS
on SER
90 days + Proponent time for SER preparation
30 Minister’s Decision
30 days