Indicative Environmental Impact Assessment and Approval Timelines
Indicative Environmental Impact Assessment and Approval Timelines
Notes
Key Documentation is published at each stage of the assessment process.
Method 1 - Assessment on Referral Information Reasons for decision are also published at each decision point.
Method 2 - Assessment by Supplementary Environmental Report (SER) All timeframes are expressed as business days.
Method 3 - Assessment by Environmental Impact Statement (EIS) Public Comment - period may be extended in consultation with the proponent.
TOR - Terms of Reference Range of 30-60 business days (determined by NT EPA) applies to public comment on draft EIS.
SUPP - Supplement Additional time for other consultations or processes may apply. For example, additional time
for proponent and statutory decision-maker comments on draft environmental approvals.
Proponents will be advised at the appropriate time.
15 days
DECISION referral
65 days
No required and
assessment Method 1 Method 2 Method 3 method of
required assessment, and
finalise TOR or
issue SER direction
(if EIS not
40 Draft TOR prepared proceeding)
30 25 Proponent directed
about matters to be
DECISION
included in SER 15 Public comment
185 - 215 days + Proponent time for EIS preparation + Supplement preparation
on TOR
Proponent Action - SER
15 TOR finalised
25 Public comment
115 - 145 days + Proponent time for EIS preparation + Supplement preparation
Proponent Action - EIS Proponent Action - EIS
on SER
90 days + Proponent time for SER preparation
30 Minister’s Decision
30 days