Professional Documents
Culture Documents
Submitted by:
Korea Engineering Consultants Ltd. Corp. & Kyong Dong Engineering Co. Ltd. JV
Seoul, Korea
in association with
Meh Consultants (P.) Ltd., Multi-Disciplinary Consultants (P.) Ltd. & Soil Test (P.) Ltd.
APRIL 2023
Table of Contents
1. Introduction ......................................................................................................................................... 2
7. Recommendations ............................................................................................................................... 9
Uphill side cutting as per design before the monsoon for widening the road. .................... 10
APPENDIX ................................................................................................................................................ 17
Figure 1: Location map of the Daunne area as seen on the satellite image of Google Earth.
-2-
perched water tables are formed at the sandstone-mudstone interface. Mainly, three joint sets intersect the
rock and they are almost perpendicular to each other, forming oblong to cubic sandstone blocks.
Figure 2: Geological map of the Daunne area showing the landslide site.
• In June 2021, the road settled by about 50 cm to 1 m. Subsequently the road was repaired and
restored to its original level.
-3-
• During August 2022, a major collapse occurred on the downhill slope where a house on the outer
edge was also destroyed by the landslide. But a small portion of the road towards the uphill side
remained intact.
• The landslide caused the road blockage for one day. At this place, the road became single-laned for
some time. As a result, the traffic was severely disturbed along with the massive effect on road
project causing further delay. Later, the rock on the uphill side of the road was excavated and the
road was expanded to its original width.
The landslide history can be assessed from the satellite images of the Daunne area taken at various times
(Figure 3). The images clearly show an intermittently active and shallow but long slide developed on the
soil cover or weathered rock above the resistant bedrock. The slide is shifting laterally as well as expanding
(i.e., extending towards the uphill side).
The main cause of recurrent activation of landslide at least since 2009 is due to poor water management and
addition of surcharge load of buildings at the crown of the landslide. Generally, during the monsoon season,
the ground is saturated with water and excess porewater pressure triggers earth flow and slide. Also, the
flowing water from unprotected streams and the wastewater from settlements have aggravated the situation
by eroding the slopes and increasing infiltration as well as porewater pressure.
-4-
Landslide Occurrences (Time History Study) at Ch. 67+350 to Ch. 67+450, Daunne over a period of 13 years (2009 to 2023)
-5-
5. Proposed investigation at Daunne
The following investigations are very critical to determine the soil and rock properties of the underlying
strata and also to confirm the bedrock level.
6. Geophysical survey
A preliminarily geophysical investigation was undertaken along and across the slope. The resistivity
values (Israil et al. 2022) indicate that the bedrock is very close to the surface and it lies at a depth of
less than a few metres (Figures 4, 5, 6, and 7). However, this has to be confirmed by borehole drilling.
-6-
Figure 4: Location of ERT survey lines at the Daunne landslide
-7-
Figure 6: Electrical Resistivity Tomogram of ERT – 3 shown in Figure 4
-8-
Figure 7: Electrical Resistivity Tomogram of ERT – 4 shown in Figure 4
7. Recommendations
The recommendations are based on field survey, and past history study. While the permanent downhill
retention is not achievable before this monsoon, it is suggested to take some immediate action for the uphill
cutting as well as follow certain temporary actions.
Risk Reduction
-9-
• Temporary resettlement and evacuation from the landslide prone areas
• Temporarily close one lane during the monsoon
• Uphill side cutting as per design before the monsoon for widening the road ( Immediate Action)
• Road Safety during the Monsoon: Action in plan (Temporary Traffic rules)
Uphill side cutting as per design before the monsoon for widening the road.
• During the cutting in progress, the activity has to be monitored and shall be progressive in
nature so that the minimal disturbances are caused to the top of the slope.
• The rockfall hazard safety shall be assessed before the cutting activity starts.
• Retaining structures as per design shall be constructed immediately.
• Cover the open slope and use combination of geotextile and bio-engineering to control erosion
on these slopes.
• A tension crack is identified at the uphill side. Tension crack sealing is suggested and can be
undertaken immediately.
-10-
-11-
Road Safety during the Monsoon: Action in plan
Some of the temporary traffic road safety protocols listed below can be adopted to prevent additional
loadings and minimum disturbances to the unstable road section.
Temporary Traffic Road Safety Plan against probable landslide during this monsoon
(June 2023 - July 2023)
Temporary Permissions/
Action Appropriate signs
Traffic plan Stakeholders
1 Hazards Warning ~Warning Seek permissions
Signs. signs to be and inform related
Hazard signs displayed at authorities,
must be displayed appropriate stakeholders in
on the roads. distance from advance.
Possibly make the critical
announcements via section.
newspaper and
radios.
-12-
Temporary Traffic Road Safety Plan against probable landslide during this monsoon
(June 2023 - July 2023)
Temporary Permissions/
Action Appropriate signs
Traffic plan Stakeholders
4. Speed Control Signs stating Permission from
Speed of under the speed limit the related
25km/hr for any for the affected authorities and
vehicles passing sections should stakeholders shall
this area strictly to be installed. be obtained at
be followed earliest.
especially during
this temporary
lane closure hours.
-13-
Temporary Traffic Road Safety Plan against probable landslide during this monsoon
(June 2023 - July 2023)
Temporary Permissions/
Action Appropriate signs
Traffic plan Stakeholders
affected
section.
• After the geotechnical investigation, design a retaining structure as per soil and rock conditions and
drainage on the downslope.
• Tentatively check dams targeting the local failures below the roadside at staged and benched profile
is suggested, after analysis of geotechnical investigation and water flow study results.
• Placement of drainage network to drain the saturated area, possibly horizontal drains, after
piezometer data collection and establishing flow network, after analysis of geotechnical
investigation and water flow study results.
• As per design, after analysis of geotechnical investigation.
• Since the road-side slope at Daunne section is unstable, bio-engineering may be implemented only
after stabilizing the slope and addressing any deeper-seated problems.
• The cost estimation to undertake the investigation works at this site are given in the section 8
below:
-14-
8. Cost Estimation for the Proposed Investigation
Total Amount
Description Of Work Unit Estimated Qty. Rate (NRs)
(NRs)
Mobilization
Mobilization/Demobilization of Machine to / from the site to KTM No. 2 50,000.00 100,000.00
Shifting & Setting ( manual carrying of the drilling machines from 1 location to another) No. 1 5,000.00 5,000.00
Topographical Survey (1 sqkm)
Regional Topographical Survey support shall be from contractors
~ Scale 1:10,000 surveyor and already existing
~ Contour Interval approx. 5 m. survey control points
~ Confirms project boundary.
¬ DGPS
Geological Survey and Detailed Landslide Mapping
Geological Reconnaissance / Regional Geological Survey/ Bedrock Mapping
~Scale 1:250,000 and 1:10,000
~Mapping of geological structures, geological rock types
Detailed topographic survey with geological observation points marked on the ground
~Scale 1:500
~Covering about 1 sq.km
Lump Sum Cost 350,000.00
~ About 10-20 separate spots.
Standard Landslide Mapping
~slide boundary, cracks, crown, springs,seepage zones e.t.c …..
~ Senior Geologist Expert
~ Junior Geologist
~ Reporting
Drilling
Bore hole Drilling at site
~ Tentatively 2 holes upto 30m. i.e. 40 X 2 = 80m drilling.
~ Core Logging by geologist Mtrs 95 10,000.00 950,000.00
Installation of Piezometer and concrete monument for daily recording of data for next 6 months
~ slotted PVC in two boreholes of total 40 X 2 = 80m.
~ Core Logging by geologist
~ Daily obeservation by technician and recording water level. Lump Sum Cost 200,000.00
Insitu Permeability Test No 4 2500
Conducting SPT/CPT Test 1.5 Interval No 65 500 32,500.00
Retreiving UDS Sample in cohesive Strata , possibly every metre for soft strata Nos 10 800 8,000.00
Requisite Laboratory Test(Per Borehole) 15 3,000 45,000.00
as per change in strata along the depth of the borehole set
Natural Moisture Content -
Bulk Density
Hydrometer
Specific Gravity
Direct Shear
Unconfined compression
Consolidation
Atterberg Limit etc.
Sieve Analysis
Lab Permeability (Falling head/ Constant head , as per sample type) 4 6000 24,000.00
Triaxial Test, ( if applicable / as per sample type) 2 50,000 100,000.00
Trial Pits and Soil sampling (2m X 2m X 3m)
~ Soil Sampling will be done by a geologist by following sampling protocol to meet criteria of
samples required for testings unit 3 15,000.00 45,000.00
Total 1,859,500.00
Add 13% VAT 241,735.00
Grand Total (with VAT) 2,101,235.00
~ These are estimated quantity . The actual cost will be applicable on pro-rata basis, meaning cost is applied only for the the test
undertaken and /or actual drill depth.
~ This is effective method of costing, as the exact number of test shall done as per approval from the client.
-15-
9. Recommendation for Additional Expert - Senior Geologist
It is critical to carry out detailed landslide mapping and geological survey at various such locations at
Daunne, given the criticality of the sites and its impact along the Narayanghat - Butwal road section. The
works of geologist cannot be substituted by geotechnical expserts.
Geological works are critical and has not taken place for the sites along Daunne. Maps should include
bedding and joint measurements, mapping tension cracks, soils, scarps, and other landslide features are
crucial for correct remediation of the slope protection works. The joint data should be analysed using a
stereo net by carrying out a kinematic analysis so that the overall stability analysis can be substantiated to
detect the right failure types in this section. It is critical to appoint an experienced geologist for analysis and
site visits for this Daunne road section in this Narayanghat Butwal Road Project.
References
Israil M., Ansari R. R., Zubair M., Yogeshwar P., Tezkan B., 2022. Near surface resistivity structure
estimated from time domain electromagnetic data recorded along a profile in HFT Zone in Mohand area,
Uttarakhand, India
-16-
APPENDIX
-17-
April 2023 ( Uphill - tension crack At the time of Site Assessment)
-18-
April 2023 ( Downhill - At the time of Site Assessment)
-19-