Process Calculation

817.122-PEE-910-P001-00
Sludge Storage Thickener

Revision:Rev 02 Name of File: 817.122 PEE 910 P 001 02 / SST Date: 14-Nov-18

WWTP: Buriej Project-Number: 817.122 Page: 75


Empl.: CMWU Option: According to Employers Requirements Programed: kl

20. Sludge Storage Thickener

20.1 Kind and Quality of Sludge

Kind and Origin of Sludge:


Phase 1 Phase 1 Phase 1
Load Case Phase 2
Stage 1 Stage 2 Stage 3
Digested Sludge: DiS
Digested Sludge Quantity, calculated mS,aDi kg TS/d 31374.4 39669.9 53270.9 73613.8
Digested Sludge Quantity, selected kg TS/d 31374.4 39669.9 53270.9 73613.8
Dry Solid Content of DiS before Thickening DSS,aDi kg/m³ 28.6 27.9 27.9 28.9
Flow of DiS before Thickening QS,aDi m³/d 1095.39 1421.56 1906.67 2551.36

Total Sludge Inlet:


Total Dry Solids Inlet kg/d 31374 39670 53271 73614
Total Sludge Quantity m³/d 1095.4 1421.6 1906.7 2551.4
Average Dry Solids Content kg/m³ 28.6 27.9 27.9 28.9

Operation Days dx/Wo 7 7 7 7


Dry Solid Content per Operation Day kg/dx 31374.4 39669.9 53270.9 73613.8
Sludge Quantity per Operation Day m³/dx 1095.39 1421.56 1906.67 2551.36
expected mean thickened sludge production rate per day % 100 100 100 100
expected mean thickened sludge production per day m³/dx average 1095 1422 1907 2551