You are on page 1of 32

Emirate of Abu Dhabi

Road Safety Audit 2012


Manual
A comprehensive procedure to be followed for the preparation of Road
Safety Audit through all stages of design and implementation of Municipal
roads and Highways projects.
Emirate of Abu Dhabi Road -Safety Audit Manual-

Acknowledgements

The Manual has been prepared by the ADM road safety Unit (lead for this task) on behalf of the Road Safety Committee
for the Emirate of Abu Dhabi. The document was reviewed by the Engineering Group sub-committee and the following
members of the committee were involved in the review process:

Abu Dhabi Municipality:


Eng Sami Abdulkader Almusawi, Head of Road Design Section
Eng Rauf Iqbal, Road Safety Expert
Eng Mohamed Al Shateri, Road Safety Unit Head

Abu Dhabi Traffic Police:


Eng Abdullrazaq M. Zaytoun, Traffic Engineering Advisor
Eng Nayel Abdullah Alshamsi
Dr Gamal Gibreel, Traffic Safety Expert

Al-Ain Municipality:
Eng David George, Road Safety Specialist

Department of Transport:
Eng John Aldridge Road Safety Specialist

Western Area Municipality:


Eng Akli Ourad

Urban Planning Council:


Eng Ali Al Derai
Eng Lim Hwa, Senior Associate Planner

Our special and sincere thanks to Mr Christopher Kettell - Road Safety Specialist (Transport Research Laboratory - on
secondment to Abu Dhabi Municipality) for his authorship, efforts, coordination and dedication in developing the manual
for the Emirate of Abu Dhabi.

Additional thanks are given to Mr John Smart BSc, CEng, FCIHT, MICE, Director of Professional & Business Development
at the Chartered Institution of Highways & Transportation (UK) for peer reviewing the document.

P a g e |2
Emirate of Abu Dhabi Road -Safety Audit Manual-

Table of Contents
1 Introduction .......................................................................................................5
1.1 General 5
1.2 Scope of this Manual 5
1.3 Development of the Manual. 5
2 Definitions ..........................................................................................................6
3 Road Safety Auditors Training and Experience ...................................................9
3.1 Scope 9
3.2 The Audit Team. 9
3.3 Audit Team Leader. 9
3.4 Audit Team Member. 9
3.5 Audit Team Observer. 9
3.6 Specialist Advisors 9
4 Audit Stages .....................................................................................................10
4.1 Introduction 10
4.2 Feasibility Stage Road Safety Audits -Stage 0 10
4.3 Interim Audits (Any Stage) 11
4.4 Preliminary Design Stage Audits (Stage 1) 11
4.5 Detailed Design Stage Audit (Stage 2) 12
4.6 Opening Stage Audit (Stage 3) 12
4.7 Post Construction Monitoring (Stage 4a/b) 14
4.8 Temporary Traffic Management (work zone) Audit 14
4.9 Scope 15
4.10 Relationship between the Work Zone Traffic Management Plan and Safety Audit 15
4.11 Planning 15
4.12 Safety Audit Review Report 15
4.13 Dangerous Defects Notification / Order to Cease Works 15
5 Road Safety Audit Procedure ............................................................................16
5.1 Overview 16
5.2 Scope of the Audit 17
5.3 When & What to Audit 17
5.4 Design Changes / Audit Shelf Life 18
5.5 Appointment of the Road Safety Audit Team 18
5.6 Independence of the Road Safety Audit Team 19
5.7 Initiating the Audit 20
5.8 Approval of the Audit Team 21
5.9 Audit Management 21
5.10 The Audit brief 21
P a g e |3
Emirate of Abu Dhabi Road -Safety Audit Manual-

5.11 Assess Audit Brief (and associated information) 22


5.12 Undertaking the Site Visit 22
5.13 Compile / issue audit report 22
5.14 Compile and Issue the Exception Report 23
5.15 Approval of the Road Safety Audit and Exception Report 23
5.16 Issues outside the scope of the Audit Brief 24
5.17 Implement design changes 24
5.18 Feedback knowledge gained 24
Annex A Road Safety Audit Request Form ................................................................26
Annex B Example CV Submission for assessment ......................................................27
Annex C Example Road Safety Audit Report .............................................................28
Appendix C3 Stage 2 28
Annex D Exception Report Template ........................................................................29
Annex E Client Checklist ............................................................................................30
References 31

P a g e |4
1 Introduction 1.3 Development of the Manual.
1.3.1 This Manual is a combination of existing
1.1 General practice within Abu Dhabi Municipality and
the Department of Transport which have
1.1.1 Road Safety is of paramount importance to
previously compiled best international
the Department of Municipal Affairs, the
practice for Road Safety Audits in the United
Municipalities, Abu Dhabi Police, Department
Kingdom, Europe, Australia, New Zealand, the
of Transport and other stakeholders.
Middle East (Dubai) and North America.
1.1.2 The primary purpose of carrying out safety
1.3.2 This Manual has been prepared specifically
audits is to ensure that any changes carried
with local conditions in mind.
out on the highway do not include features, or
combination of features, that may contribute
to any type of future potential conflicts
between road users and offer advice to
minimise the likelihood of them occurring.

1.1.3 There are also many other functions taking


place on the highway, including regular like
for like maintenance works, which, whilst
not changing the highway, are nevertheless,
an opportunity to ensure that safety
considerations are taken as part of the works.

1.2 Scope of this Manual


1.2.1 This manual must be followed by all persons
who have involvement in the planning,
design or construction of changes to the
Emirate of Abu Dhabi Road Network (EADRN)
and those who are commissioned to
undertake audits and to ensure that the road
safety implications of all projects are fully
considered for all users of the road and
others affected by the project.

1.2.2 This manual shall apply to all measures


proposed on the EADRN that involve change
to the road/highway. This includes work
carried out under agreement with DMA and
DoT resulting from developments alongside
or affecting the EADRN.

1.2.3 Large or Complex construction projects


requiring temporary traffic management will
generally require a work zone safety audit.

1.2.4 Road Safety Audit (RSA) is to be conducted in


line with the procedures set out within this
manual.

1.2.5 This requirements set out in this manual are


applicable to all design and construction work
through the design and construction process
for all stages of road safety audit.

1.2.6 This manual does not include general health


and safety arrangements during construction.
Emirate of Abu Dhabi Road -Safety Audit Manual-

2 Definitions 2.1.9 Crash Investigation: The collection and


examination of historical crash data over a
2.1.1 Audit Brief: The instructions to the Audit period of time in order to identify patterns,
Team defining the scope and details of the common trends and factors which may have
Highway Improvement Scheme to be audited, contributed to the crashes.
including sufficient information for the audit
to be undertaken. 2.1.10 Crash: A rare random multifactor event in
which one or more road users fails to cope
2.1.2 Audit Report: The report produced by the with their environment. This includes
Audit Team describing the road safety related crashes resulting in casualties or in damage
problems identified by the team and the only.
recommended solutions to those problems.
2.1.11 Design Organisation: The organisation(s)
2.1.3 Audit Team Continued Professional commissioned to undertake the various
Development (CPD): A record of courses, phases of scheme preparation.
conferences, workshops and any other
training undertaken with the purpose of 2.1.12 Design Team Leader: A person within the
keeping Road Safety Auditors up to date with Design Team responsible for managing the
the latest developments in Road Safety Audit, scheme design and coordinating the input
Crash Investigation and Road Safety of the various design disciplines.
Engineering.
2.1.13 Design Team: The group within the Design
2.1.4 Audit Team Leader: A person with the Organisation undertaking the various
appropriate training, skills and experience phases of scheme preparation.
who is approved for a particular audit by the
2.1.14 Exception Report: A report which is
relevant road authority on behalf of the client
prepared where agreement cannot be
organisation. The Audit Team Leader has
reached between the design organisation
overall responsibility for carrying out the
and the audit team on road safety audit
audit, managing the Audit Team and certifying
recommendations made within the road
the report.
safety audit report. The report consists of
2.1.5 Audit Team Member: A member of the Audit the problem, recommendation and the
Team (approved by the relevant road designers response to the problem, in
authority for that particular RSA) with the addition to the audit teams response to the
appropriate training, skills and experience designer. This report is the sent to the
necessary for the audit of a specific scheme relevant highway authority and Abu Dhabi
reporting to the Audit Team Leader. Police to determine an appropriate means
of addressing the underlying safety
2.1.6 Audit Team Observer: A person with the problem(s) identified within in the road
appropriate training, skills and experience safety audit report.
accompanying the Audit Team to observe and
gain experience of the audit procedure. The 2.1.15 Highways: DoT owned and operated roads.
Audit Team Observer is encouraged to
2.1.16 Highway Improvement Schemes: All works
contribute actively to the audit process.
that involve construction of new highway or
2.1.7 Audit Team: A team that works together on all permanent change to the existing highway
aspects of the audit, independent of the layout or features. This includes changes to
Design Team and approved for a particular road layout, kerbs, signs and markings,
audit by the relevant roads authority. The lighting, signalling, drainage, landscaping
team shall comprise a minimum of two and installation of roadside equipment.
persons with appropriate levels of training,
2.1.17 Interim Road Safety Audit: The application
skills and experience in Road Safety
of Road Safety Audit to the whole or part of
Engineering work and/or Crash Investigation.
a Highway Improvement Scheme at any
2.1.8 Client: The party responsible for promoting time during the preliminary and
the project/Development. construction stages. Interim Road Safety
Audit is not mandatory or a substitute for
the formal Stage 1, 2 and 3 Safety Audits.

P a g e |6
Emirate of Abu Dhabi Road -Safety Audit Manual-

2.1.18 Department of Municipal Affairs 2.1.25 Specialist Advisor: A person approved


Roads: Municipal owned and operated by the Project Sponsor, to provide
roads. specialist independent advice to the
Audit Team should the scheme include
2.1.19 Maintaining Agent: The authority complex features outside the
responsible for maintaining the experience of the Audit Team
completed Road Project. This is Members, e.g. a complex traffic signal
typically a term contractor employed controlled junction.
on behalf of the Road Authority to
undertake this function. 2.1.26 Stage 0 - Feasibility Road Safety Audit
Feasibility Safety Audits shall only be
2.1.20 Planning Authorities: The authority undertaken on schemes where the
responsible for development control opportunity exists for safety audit to
(i.e. Abu Dhabi Urban Planning Council, assist in defining the choice of road
or Abu Dhabi/Al Ain/Western Region alignment or junction type. Where
Municipality). more than one design option exists, the
Road Safety Audit will identify the
2.1.21 Road Authority: The authority preferred option.
ultimately responsible for the
operations and maintenance of the 2.1.27 Stage 1 - Preliminary Design Road
road being audited (i.e. Department of Safety Audit shall be undertaken upon
Transport, or Abu Dhabi/Al completion of preliminary design and
Ain/Western Region Municipality). prior to any commitment to construct is
entered into, this includes the purchase
2.1.22 Road Safety Audit: The evaluation of of land, buildings etc, whereby any
Highway Schemes during planning, road safety issues which may affect the
design and at the end of construction land take required can be identified as
(preferably before the scheme is open early as possible.
to traffic) to identify potential road
safety problems that may affect any 2.1.28 Stage 2 - Detailed Design shall be
users of the highway and to suggest undertaken at the completion of
measures to eliminate or mitigate detailed design BUT before
those problems. The audit process construction commences, sufficient
includes the crash monitoring of time should be allowed for any road
Highway Improvement Schemes to safety audit issues requiring design
identify any road safety problems that changes to be incorporated into the
may occur after opening. design.

2.1.23 Road Safety Engineering: The design 2.1.29 Stage 3 - Construction Opening shall be
and implementation of physical undertaken at the substantial
changes to the road network intended completion of the project preferably
to reduce the number and severity of before the road project is opened to
crashes involving road users, based on traffic (Pre Opening Stage - 3a). Where
the results of crash investigations. it is not feasible to undertake the audit
prior to opening, it can be completed
2.1.24 Road Users: All persons located within either as a phased or complete opening
the road reserve, irrespective of the as a Stage 3b, within two weeks of
purpose of their trip or mode of opening but before handover.
transport. They include the visually and
mobility impaired (e.g. wheel chair 2.1.30 Stage 4a - 12 months monitoring can
users). be undertaken on the 12 month
anniversary of a schemes opening. This
will involve a check on the number of
resulted crashes and the locations that
they have occurred so that any
problems can be identified and
remedial works undertaken.

P a g e |7
Emirate of Abu Dhabi Road -Safety Audit Manual-

2.1.31 Stage 4b - 36 months monitoring can


be undertaken on the 36th month
anniversary of a schemes opening. This
will involve a check on the number of
resulted crashes and the locations that
they have occurred so that any
problems can be identified and
remedial works undertaken.

2.1.32 Work Zone Management: The


arrangement of temporary sign,
markings and other devices to guide all
road users safely through road works,
whilst also ensuring the protection of
works personnel.

2.1.33 Vulnerable Road User (VRU): All


persons located within the road reserve
with little or no external protection
such as pedestrians, cyclists, powered
two-wheelers and wheelchair users.

P a g e |8
Emirate of Abu Dhabi Road -Safety Audit Manual-

3 Road Safety Auditors d) A minimum of 2 days Continuing


Professional Development (CPD) in the
Training and Experience fields of Road Safety Audit, Collision
Investigation or Road Safety
3.1 Scope Engineering in the past 12 months.
3.1.1 The following chapter sets out the e) And be able to demonstrate that they
requirements for the Safety Audit Team who have a well-rounded knowledge of
Audit in the Emirate of Abu Dhabi. These are Highway Design.
the required standards for all Road Safety
Audit Teams. 3.4 Audit Team Member.
3.2 The Audit Team. 3.4.1 The Audit Team Member must be able to
demonstrate the following levels of
3.2.1 The Road Safety Audit Team shall comprise of experience:
no less than a two person team - Audit Team
Leader and Audit Team Member. a) A minimum of 2 years Collision
Investigation or Road Safety Engineering
3.2.2 There is no upper limit on the size of the Audit Experience; and
Team, if required specialist advisors may be
consulted and/or attend during the site b) Completion of at least 5 Road Safety Audits as
inspections as instructed by the relevant Audit Team Member or Observer in the past
highway authority. 24 months; and

3.2.3 The appointment of the RSA team shall be at c) Attendance of a 10-day recognised Collision
the discretion of the relevant roads authority, Investigation or Road Safety Engineering
as to the appropriateness of an individual(s) course; and
nominated to conduct the RSA for a particular
scheme. A road safety audit submitted by a d) A minimum of 2 days CPD in the fields of Road
consultant or developer where the team was Safety Audit, Collision Investigation or Road
not approved by the relevant roads authority Safety Engineering in the past 12 months.
will be rejected.
f) And be able to demonstrate that they have a
3.2.4 Road Safety Auditors who audit full time to well rounded knowledge of Highway Design.
the exclusion of other crash investigations /
road safety engineering work are 3.5 Audit Team Observer.
unacceptable.
3.5.1 The Audit Team Observer must have:
3.3 Audit Team Leader.
3.5.2 A minimum of 1 years Collision
3.3.1 The Audit Team Leader must be able to Investigation or Road Safety Engineering
demonstrate the following levels of Experience; and
experience:
3.5.3 A minimum of 2 days CPD in the fields of Road
a) A minimum of 5 years Collision Safety Audit, Collision Investigation or Road
Investigation or Road Safety Safety Engineering in the past 12 months.
Engineering experience; and
3.5.4 An interest or willingness to learn about road
b) Attendance of a 10-day recognised safety audit
Collision Investigation or Road Safety
Engineering course; and 3.6 Specialist Advisors
c) Completion of at least 5 Road Safety 3.6.1 Whilst there are no specific requirements for
Audits in the past 12 months as an the specialist advisor, it will be at the
Audit Team Leader or member; and discretion of the Design Organisation and
Audit Team if it is considered that the scheme
has a number of complex features requiring a
specialist to be included as part of the audit
team.

P a g e |9
Emirate of Abu Dhabi Road -Safety Audit Manual-

4 Audit Stages 4.1.2 An interim audit can be undertaken at any


stage in between each formal road safety
4.1 Introduction audit.

4.1.3 For smaller schemes stage 1 and stage 2 of the


4.1.1 Figure 4.1 outlines the relationship between
road safety audit process can be combined
design and road safety audit from the start of
into a single road safety audit report.
design though to the completion of
construction.
4.2 Feasibility Stage Road Safety
Audits -Stage 0
Design Starts
4.2.1 Feasibility/Conceptual Stage Road Safety
Audits should be undertaken on completion of
feasibility or conceptual design (prior to the
Master Plan / TIS
Feasibility / Stage 0 Road
completion and submission of the TIS). This is
Conceptual Safety Audit the first occasion at which land requirements
Design may be increased and it is therefore essential
to consider fully any road safety issues which
may have a bearing upon land take.

Preliminary Stage 1 Road 4.2.2 A Stage 0 Road Safety Audit MUST be


Design Safety Audit completed on any Master Plan / TIS, at
completion of the Stage 0 Road Safety Audit,
the Audit is to be submitted for approval to
the relevant highway authority and Traffic
Police.
Stage 2 Road
Detailed Design
Safety Audit
4.2.3 At this point in the project life cycle,
fundamental decisions such as route choice,
overall design and layout are being decided.
The Audit Team should therefore focus on
Construction Stage 3 Road ‘high-level’ safety aspects such as route
(Pre-opening) Safety Audit alignment, tie-in with existing road network,
and number, type, layout and location of
intersections or interchanges.
Construction
Ends
4.2.4 All Audit Team Members should examine the
site together during this Stage. It is essential to
consider fully any road safety issues which
may have a bearing upon land take, including
12 / 36 Month development-led road projects, before
Stage 4a/b Road
Scheme planning consent is granted
Safety Audit
Completion

Figure 4.1 Relationship between design and RSA

P a g e | 10
Emirate of Abu Dhabi Road -Safety Audit Manual-

4.4.5 With the route choice, overall design and


layout having been decided, the Audit
4.3 Interim Audits (Any Stage) Team can still suggest some localised
changes, such as horizontal and vertical
4.3.1 The Client will decide whether to employ alignment, consolidation of access points
Interim Road Safety Audit. Design Teams shall and location of accesses. Other issue
not contact Audit Teams without the Client’s include provision of a median, lane and
prior written authorisation. Audit Teams shoulder width, provision of cycle lanes
undertaking Interim Road Safety Audit shall and sidewalks, and channelization.
only be appointed with the approval of the Accesses provided (driveways,
relevant roads authority in accordance with intersections, interchanges) should be
section 4.10. reviewed for upstream/downstream
effects, potentially conflicting movements,
4.3.2 The Audit Team will require an Audit Brief for and sight distances.
an Interim Road Safety Audit containing as
many of the items given in paragraph 2.62 as 4.4.6 If staged implementation of the road
are available, though obviously it will not be project is to be carried out, each stage
possible to provide everything on the list in should be considered as well as the
early design stages. A full Audit Brief must still transition between each stage. If
be supplied to the Audit Team at the end of alternative design options are being
the design stage for Stage 1 or Stage 2 Audits. considered they should be reviewed
separately by the Audit Team.
4.4 Preliminary Design Stage
Audits (Stage 1) 4.4.7 The Stage 1 Audit should include a review
of the issues raised in the Feasibility Stage
4.4.1 The Preliminary design stage Road Safety Audit Audit. Any issues that have not been
must be undertaken on completion of satisfactorily resolved from the Feasibility
preliminary design. This stage occurs before Stage 0 Audit should be reiterated in the
the land acquisition process commences and is Stage 1 Audit report.
therefore the last opportunity at which land
requirements may be increased.

4.4.2 Drawings may only show general details such


as route alignment, profile of the road and
typical cross sections (typically 1:1000 scale).

4.4.3 Intersections and interchanges are generally


shown at a larger scale (for example 1:500
scale).

4.4.4 Although the Audit Team will be unable to see


the full details of the design as it will appear in
the detail design stage, a site visit must still be
undertaken to assess how the road project will
tie in to the existing road network and how
consistent the design will be from the
perspective of different road users (by
examining the adjacent road network). All
members of the Audit Team must visit the site
together to consider the prevailing climatic
conditions, surrounding vegetation and
topography and the local driver’s behaviour.

P a g e | 11
Emirate of Abu Dhabi Road -Safety Audit Manual-

4.5 Detailed Design Stage Audit 4.5.4 The Audit Team will need to consider
how these aspects of the design will
(Stage 2) affect the operation of the road project
4.5.1 The Detailed Design Stage Audit should be for all the different road user groups
conducted before completion of the final likely to use it. The base map will show
design drawings for the construction of a road significant detail of vertical contours,
project. This stage of audit provides the last existing roads, structures, vegetation
opportunity to change the design before and property boundaries at an even
actual construction of the road commences. larger scale than for the preliminary
Land acquisition may have been finalized by design drawings. Intersections and
this stage and this will prevent the Audit Team interchanges will also be shown at a
from making any recommendations involving larger scale (typically 1:500, 1:200 or
significant changes to road alignment or road larger).
footprint. The Stage 2 Audit is concerned with
4.5.5 The Stage 2 Audit should include a
the more detailed aspects of the road project.
review of the issues raised in the Stage
4.5.2 All Audit Team Members must examine the 1 Audit report. Any issues that have not
site together during the Detailed Design Stage. been satisfactorily resolved from the
Stage 1 Audit should be reiterated in
4.5.3 Drawings at the Detailed Design Stage will the Stage 2 Audit report.
show significant detail, as follows:
4.6 Opening Stage Audit
 Horizontal and vertical alignment: (Stage 3)
drawings showing the alignment and
vertical profile 4.6.1 The Opening Stage Audit should be
undertaken when the road project is
 Cross section: number and width of substantially complete and preferably
lanes, shoulders, drainage, curbs and before the road project is opened to
gutters, boulevards, medians, traffic (i.e. Pre-Opening Stage or Stage
sidewalks, clear zone, roadside 3). This is to minimise potential risk to
barriers, significant roadside road users and the difficulty that would
structures, and potential roadside be experienced by Audit Teams in
hazards traversing the site when open to traffic.
However when a pre-opening site visit
 Intersection layout: including all
is carried out a post-opening visit will
traffic control devices, signs,
also be required so that the road safety
pavement markings, number of lanes
audit team can observe actual human
on each approach, medians, and
behaviour on the new scheme.
channelization
4.6.2 Where a pre-opening RSA is not
 Interchange layout: including advance feasible, this may result in the audit
and exit direction signs, length and being carried out a short time after
width of acceleration/deceleration opening or in phases where a project is
lanes, delineation, gore area subject to phased completion and
treatments, and roadside barriers opening.
 Other details: driveway accesses,
landscaping and traffic calming
devices, illumination, signs, marking,
and delineation

P a g e | 12
Emirate of Abu Dhabi Road -Safety Audit Manual-

4.6.3 Pre-Opening Stage Audits represent the  An expert with experience of


last opportunity that the Audit Team specific road user groups (for
has to identify potential safety example, a representative from a
concerns before the road project is local disability group to assess the
opened to all road users. They will have suitability of facilities, such as
an opportunity to conduct a detailed adequate provision and location
inspection of the new road and tie-ins of dropped kerbs and ramps at an
with the existing road network. The intersection).
Audit Team will want to conduct the
site visit by driving through it and 4.6.6 The Audit Team may be under a time
walking along key stretches by foot to constraint and may need to provide a
see the entire site first hand, both in quick response to the Client and Design
daylight and in darkness. The site visits Team. To expedite the process, the
will be a critical component of the Audit Team may undertake their site
Audit Team's evaluation. visit and then meet with the Client and
design team immediately afterwards
4.6.4 All Audit Team Members must examine while still on-site to show them first
the site together during daylight at hand any identified safety issues and
Stage 3. They must also examine the suggested improvements. This will
site together during the hours of allow the Client and Design Team to
darkness so that hazards particular to address the identified safety issues
night operation can be identified (such immediately, minimizing any delay to
as inadequate lighting, misleading the opening of the road facility.
delineation, and hidden roadside
hazards). The Audit Team should also 4.6.7 The Audit Team may then follow up
consider the effects of various weather with their audit report, and the Client
conditions that may not be present at and Design Team may complete the
the time of inspection (such as fog or corresponding exemption report after
sand storms). the opening of the road project.

4.6.5 In addition to inviting the Police, at the 4.6.8 Since the road will have been built in its
Stage 3 Road Safety Audit consideration entirety, it is unlikely to be feasible for
should be given to inviting the the Client or Design Team to implement
following to both the day time and recommendations identified by the
night time site visits: Audit Team which concern physical
changes to the cross section, layout, or
 A representative from the alignment of the roadway.
relevant road authority who is Nevertheless, all identified problems
familiar with traffic control should be reported in the road safety
devices – they may be aware of audit report.
maintenance issues that
restrict/prevent the 4.6.9 It is however likely that the Audit Team
implementation of safety will tend to identify problems and make
measures the auditors may wish proportional and viable
to recommend (for example the recommendations which will focus on
need to retain access for service factors such as changes to illumination,
vehicles within an intersection). signage, delineation, pavement
Alternatively, the representative markings, roadside barriers, removal of
may need to be made aware of fixed object hazards, or on minor
any issue that needs continued structural changes (i.e. addition of a
attention to prevent it becoming wheelchair ramp).
a safety issue (for example,
vegetation close to or within the 4.6.10 Issues raised in the Stage 2 Audit report
visibility splay of an access). should also be reviewed at the Stage 3
Road Safety Audit. Any issues that have
not been satisfactorily resolved from
the Stage 2 Audit should be reiterated
in the Stage 3 Audit report.

P a g e | 13
Emirate of Abu Dhabi Road -Safety Audit Manual-

4.7 Post Construction 4.7.4 The analysis of data should include


identification of changes in the number of
Monitoring (Stage 4a/b) incidents. The crash data should be analysed
4.7.1 During the first year (12 months) a to identify the influence of problems and
Highway Scheme is open to traffic, a recommendations identified at previous audit
check can be kept on the number of stages, and any approved Exception Reports.
personal injury crashes that occur, so
4.7.5 If crash records are not sufficiently
that any problems can be identified and
comprehensive for detailed analysis, Abu
remedial work arranged quickly.
Dhabi Police should be contacted to ascertain
4.7.2 Stage 4 crash monitoring reports the availability of incident data, which could
should be prepared using 12 months aid the 12 and 36-month data analysis.
(Stage 4a) and 36 months (Stage 4b) of
4.7.6 The stage 4 12/36 month monitoring reports
crash data from the time the Highway
should identify any road safety problems
Scheme became operational and shall
indicated by the data analysis and
be submitted to the relevant highway
observations during any site visits undertaken.
authority and Abu Dhabi Police.
4.7.7 The reports should make recommendations
4.7.3 The crash records shall be analysed in
for remedial action.
detail to identify:
 locations at which personal injury 4.8 Temporary Traffic Management
crashes have occurred; (work zone) Audit
 personal injury crashes that appear
to arise from similar causes or 4.8.1 Issues to focus on during traffic management
show common factors. (work zones) audits include:

• Adequacy of advance warning;

• Proposed speed limits;

• Appropriateness of the selected standard


layout;

• Conflicts between permanent and temporary


features;

• Any aspects of layout or devices that could


be misread by drivers (for example traffic
signs, lane markings and delineation);

• Likelihood of mud or dust obscuring devices;

• Appropriateness of crash barriers and the


correct installation;

• Adequate provision for pedestrians,


particularly the mobility impaired;

• Adequate protection of works personnel;


and

• Conflict points between works traffic and the


general public.

• Temporary Traffic Management (Work Zone)


Audit.

P a g e | 14
Emirate of Abu Dhabi Road -Safety Audit Manual-

4.11 Planning
4.9 Scope 4.11.1 The road safety audit of temporary
traffic management is not intended to
4.9.1 Road Safety Audit of traffic management be a technical check of the proposed
projects (road works) should be undertaken on work zone traffic management
large or exceptionally complex traffic (however from time to time it will be
management projects that involve temporary necessary to touch upon a technical or
changes to the layout and operation of design element to fully explain a
junctions, or realignment of roads that will problem) nor to replace any approvals
affect the network for considerable periods of process in place at the relevant
time, i.e. 6 months or more. Examples of such highway authority. It asks the question
projects include installation of a temporary "is it safe"?
roundabout junction or a diversion using a
length of temporary carriageway to allow 4.11.2 The audit will consider the following
major excavation on a main carriageway. elements, but is not limited to:

4.9.2 The Road Safety Audit of traffic management a) Layout in relation to the highway
projects should involve an assessment of the b) Driver and advanced warning
proposed drawings for each different c) Delineation devices (including
configuration or staging of traffic, before they barrier, road markings etc)
are implemented. If necessary, the site should d) Signing
be inspected, taking note of any existing e) Miscellaneous devices
features that will need to be covered or
removed (e.g. traffic signs and lane markings, 4.12 Safety Audit Review
and reflective road studs) or shielded (e.g. Report
roadside hazards that will be close to traffic).
4.12.1 The report will follow the same format
4.9.3 The Road Safety Audit of temporary traffic of a stage 3 road safety audit and
management does not absolve the contractor contain the information as set out
or consultant of any responsibility for safe within Para 5.14 (Compile / issue audit
working arrangements. report).

4.10 Relationship between the Work 4.13 Dangerous Defects


Zone Traffic Management Plan Notification / Order to
and Safety Audit Cease Works
4.10.1 The objective of traffic management for 4.13.1 During the construction, periodic
construction work zones is to guide all road inspections of the traffic management
users past the work zone in a safe and efficient will be undertaken, if at any time
manner whilst protecting the operatives in the elements, even if temporary are
zone itself. identified to be unacceptable or
dangerous, an immediate notification
4.10.2 The design and approvals process of TTM of dangerous defect will be raised and
should be a part of the overall design in more serious cases an order by the
submission including the TTM Road Safety relevant highway authority to cease
Audit. Sufficient time should be given in the works will be raised.
preparation of traffic management and the
TTM safety audit.

P a g e | 15
Emirate of Abu Dhabi Road -Safety Audit Manual-

5 Road Safety Audit Procedure


5.1 Overview
5.1.1 These procedures are based largely on the
UK’s Highways Agency’s (2003) procedures for
carrying out Road Safety Audits on Trunk
Roads and Motorways as documented in HD
Determine Road
19 of the Design Manual for Roads and
Safety Audit
Bridges, this is supplemented with Stage 0 is Requirements
from the Australian Austroads road safety
audit guidance.
Instruct design team of
5.1.2 There are four main parties involved in the road safety audit
Road Safety Audit process, namely: the Client requirements through
design brief
(Relevant Highway Authority), Abu Dhabi
Police, the Design Organisation and the Audit
Team. Abu Dhabi Police is one of the
stakeholders responsible for Road Safety Audit
Prepare and issue
as a shared responsibility with the relevant the Road Safety
road authorities. Audit brief

• The Client is the organisation or party


Submit Road
responsible for commissioning the design Safety Team CVs
and the Road Safety Audit. and Experience
for approval to the
• The Design Organisation is the relevant highway
authority.
organisation or party responsible for
designing the road project.
Appoint the Road
• The Road Safety Audit Team is the Safety Audit Team
independent group of experts assembled
to review the safety of the road design.

5.1.3 The Client’s role depends on the type of road


project: Complete site visit
and prepare audit
• Highway projects: road authority (i.e. report
Department of Transport)
• Municipal Roads: road authority (i.e.
the Municipalities)
Arrange meeting to
• Private Developments: Developers handover report to
Design Team and Client
5.1.4 The Client’s interests will generally be
represented by a Project Manager.

Submit to Client
Relevant Road and Design Team
Authority

Road Safety Audit Team


Figure 5.1 - Road Safety Audit Process

Design Team

Key to process

P a g e | 16
Emirate of Abu Dhabi Road -Safety Audit Manual-

5.2 Scope of the Audit 5.3.3 Similarly, where a road project is of an


even smaller scale that no
5.2.1 Road Safety Audit should only consider road feasibility/conceptual or preliminary
safety matters. Road Safety Audit is not a design has been necessary and the project
technical check to ensure that the design has progressed directly to detailed design
conforms to standards. Road Safety Audit (such as in the case of minor developments
should not consider structural safety. Health and traffic calming schemes), Audit Stages
and Safety issues are also not addressed in the 1 and 2 can be combined at Stage 2 and
Road Safety Audit. referred to as a Stage 1 / 2 Audit (and
Feasibility Stage Audit can be omitted
5.2.2 Auditors should examine all road safety again). The relevant road authority should
elements of the project. All users of the be consulted on the audit stages that shall
highway should be considered including be undertaken.
pedestrians, cyclists, motorcyclists, those
working on the highway and motor vehicle 5.3.4 For all new road projects it is mandatory to
users. Particular attention should be given to undertake the full range of audits, namely:
vulnerable road users such as the very young,
the elderly and the mobility and visually • Feasibility Stage Audit (Stage 0 Audit)
impaired. at feasibility or conceptual design
stage/planning;
5.2.3 The potential for road safety problems is often
greatest at intersections, tie-ins and • Preliminary Design Stage Audit (Stage
immediately beyond tie-ins. Where a road 1 Audit) at preliminary design stage;
improvement project joins an existing road or
• Detailed Design Stage Audit (Stage 2
intersection, inconsistency in the standard of
Audit) at detailed design stage;
provision can lead to crashes, so special
attention should be paid to these areas to • Opening Stage Audit (Stage 3 Audit)
ensure a safe transition is achieved. This at construction stage and opening of
applies particularly to online improvements road to traffic; and
where variations in the standard of provision
between new and existing sections may not be • Monitoring (Stage 4 a/b) on the 12
obvious to the road user. and 36 month of the schemes opening.

5.3 When & What to Audit 5.3.5 Each of these audit stages above are
discussed in depth in Chapter 5.
5.3.1 All road projects must be audited at all stages
of design and construction. If an audit is not 5.3.6 See Chapter 6 for further information
undertaken at all stages, approval must be about Road Safety Auditing of Temporary
sought from the relevant roads authority (DoT Traffic Management projects.
or Municipality).
5.3.7 With Design and Build road projects, design
5.3.2 For example, where a road project is of such a work is an ongoing process throughout the
small scale that no feasibility or conceptual period of the project and completion of the
design has been necessary and the project has works is often staged. As a result it is often
progressed directly to preliminary design (such not possible to undertake audits at discrete
as in the case of minor new roads and points during the design and construction of
major/minor rehabilitation retrofit schemes), the project. The Feasibility Stage Audit is
the audit process can progress immediately to generally undertaken on the conceptual
Audit Stage 1 (i.e. Feasibility Stage Audit can design (for the whole project in one go) prior
be omitted), at the discretion of the relevant to tender, with the Stage 2 Road Safety Audit
road authority. undertaken on final design by the incumbent
consultant/contractor (i.e. post-tender) as the
design stages are completed.

P a g e | 17
Emirate of Abu Dhabi Road -Safety Audit Manual-

5.4 Design Changes / Audit Shelf 5.5.4 The relevant roads authority should be
satisfied as to the independence and
Life competence of the team to undertake the
5.4.1 Stage 1, combined Stage 1/2 and Stage 2 audit. Members of the Road Safety Audit
Audits shall be repeated if the scheme design Team should demonstrate their
materially changes or if the previous audit for competence by means of Curriculum Vitae
the relevant stage is more than 2 years old. and Continuing Professional Development
record.
5.4.2 In the case of minor changes to a Highway
Improvement Scheme then the re-audit 5.5.5 Approvals are project and stage specific
should only be concerned with the elements and the use of personnel or organisations
of the scheme that have been changed. on previous Road Safety Audit work does
not guarantee their suitability to audit
5.4.3 If the design of the Highway Improvement other Projects.
Scheme is changed during the construction
period, then the elements of the scheme that 5.5.6 Experience should be relevant to the type
have been redesigned shall be resubmitted for and complexity of Project being audited
a Stage 2 Road Safety Audit prior to and be inline with the requirements as set
construction. out within Chapter 3 of this manual.

5.5.7 In proposing a Road Safety Audit Team a


5.5 Appointment of the Road Safety CV for the team leader, team member, any
Audit Team specialist advisors and observers is to be
provided in the format shown in Annex B -
5.5.1 A Road Safety Audit Team must comprise at CV Format.
least two members: the Audit Team Leader
and Audit Team Member. This enables 5.5.8 The relevant roads authority will not
discussion between the auditors of the accept a team if it lacks the necessary
problems and recommendations and training, skills and experience or where its
maximises the potential to identify problems independence from the design team is in
(i.e. reduces the risk that road safety issues doubt. In such cases, an alternative team
are missed). The most competent auditor is shall be proposed.
generally designated as Audit Team Leader.
5.5.9 It is not necessary for the same Audit Team
5.5.2 Audit Team Observers may also join the team to undertake all audit stages of a project,
to gain experience in carrying out Road Safety however, any changes to an Audit Team
Audit, however the number of Observers and its individual members will require
should normally be limited to a maximum of further approval from the relevant roads
two. authority.

5.5.3 The Client and the Audit Team should


consider if there are any particular
features of the project, such as complex
signal controlled intersections, highway
design, traffic management or
maintenance issues that warrant the
appointment of Specialist Advisors (See
section 3.6.1) to advise the Audit Team.
Appointment of Specialist Advisors is
subject to the approval of the Client who
would separately instruct them on their
role. A Specialist Advisor is not a member
of the Audit Team but advises the team on
matters relating to their specialism.

P a g e | 18
Emirate of Abu Dhabi Road -Safety Audit Manual-

5.6 Independence of the Road 1. Audit. The teams are permitted to meet if
considered necessary to enable the Design
Safety Audit Team Team to explain their designs and the Audit
5.6.1 It is central to the auditing procedures that no Team to explain any identified problems and
member of the Audit Team has had any recommendations. This meeting should be
connection with the design of the measures chaired by the Client;
being audited and should maintain this
2. Audit Teams shall report in the format
independence throughout the audit process.
illustrated in the report in Annex C;
5.6.2 The requirement for Audit Team
3. Audit Teams shall limit their reports to
independence does not preclude direct
matters within the scope of this Standard;
contact between the Audit Team and Design
Team. 4. Minutes of meetings shall be recorded
5.6.3 There may be times where there is clear 5. All communications between the teams
benefit in allowing this to happen, for example including design submissions, interim audit
in clarifying the Audit Brief. Alternatively, reports and minutes of meetings must be
direct contact may be unavoidable if the Client submitted to the Client and copies recorded
Organisation and Design Organisation are one on an Interim Road Safety Audit File.
and the same. It is of paramount importance,
however, that the Audit Team maintains its 6. The Audit Team is responsible for
independence. The Design Team should not in maintaining the file and delivering it to the
any way influence the outcome of the audit by Client at the completion of the preliminary
discussing any design considerations or issues or detailed design;
with the Audit Team.
7. Road Safety Audits at Stages 0, 1, 2, 3 and 4
5.6.4 Generally the Audit Team should not go shall still be carried out and reported.
beyond making recommendations in broad
terms.

5.6.5 The Audit Report will be reviewed by safety


team of the relevant roads authority and
issued to the relevant client officer as final.
Any issues within the Audit Report that the
Client disagrees with, are considered to be
outside the terms of reference, or irrelevant to
the Road Safety Audit should be addressed
through the Safety Audit Response/Exception
Report.

5.6.6 Neither the Client Organisation nor the Design


Organisation should petition the Audit Team
to change the content of the Audit Report.

5.6.7 All contact between the Design Organisation


and Audit Team must be recorded. The Audit
Team will keep a record of contact with the
Design Team on the audit file.

5.6.8 Subject to the Client’s prior agreement, at


any time during the preliminary and detailed
design stages, designers may submit or be
instructed to submit interim designs of the
whole or parts of schemes to the Audit Team
for completion of an Interim Road Safety

5.6.9 This is subject to certain conditions being


met:

P a g e | 19
Emirate of Abu Dhabi Road -Safety Audit Manual-

5.7 Initiating the Audit


5.7.1 The Client initiates the Road Safety
Audit process at the appropriate stages
of a project’s development ensuring
that sufficient time is available to
complete the full procedure. (See
Figure 5.1) This shall include an time
allowance for the incorporation of
changes into the design that may arise
from the Road Safety Audit.

5.7.2 The Client ensures that the road safety


audit organisation team is given due
notice of when the proposals will be
ready for the RSA and agrees with the
Road Safety Audit team leader the date
by which the Safety Audit Report will
be issued.

5.7.3 For guidance, Client should anticipate


allowing between two and three
working weeks between undertaking
the audit for the delivery of audit
report, depending on the complexity of
the project, from issue of a complete
audit brief. Complex projects may take
considerably longer than this.

5.7.4 The Client is to liaise with the Design


Team to prepare the Audit Brief
utilising the audit brief checklist.

5.7.5 The Audit Brief is forwarded to the


nominated Audit Team Leader for
consideration. The Audit Team Leader
may direct any requests for clarification
of the Brief to the Client, who will liaise
as appropriate with the Design Team.

5.7.6 Where the Client considers it


unnecessary for a Road Safety Audit to
be carried out, he must seek approval
from the relevant road authority. His
request must clearly state why an audit
is not considered necessary.

P a g e | 20
Emirate of Abu Dhabi Road -Safety Audit Manual-

5.8 Approval of the Audit Team f) traffic signal and phasing diagrams;
g) any known departures from standard;
5.8.1 One of the relevant road authorities first tasks
is to approve an independent Audit Team h) confirmation of construction dates;
(also refer to Chapter 3). In practice the
i) all previous Road Safety Audit Reports
Design Organisation is asked to propose an
Audit Team for the relevant roads authorities relating to the project, approval from
approval.
Abu Dhabi Police and the relevant
5.9 Audit Management roads authority relating to the project;
j) all previous response reports,
5.9.1 The Client and Design Team should liaise and
ensure that the audit process is initiated at exception reports, approval from Abu
the appropriate stages, allowing sufficient
Dhabi Police and the relevant roads
programme time to complete the full audit
procedure. This should include an allowance authority relating to the project;
for the incorporation of design changes,
k) appropriate sized plans of the project
should any arise from the audit report.
for the Audit Team to mark up and
5.9.2 The Design Team should ensure that the Audit
Team is given sufficient notice of when the include in the Audit Report (either A4
scheme will be ready for audit and the date by or A3 sized sheets);
which the report will be required.
l) traffic / pedestrian flow data (where
5.9.3 Adequate time must be given for the available);
preparation of the audit report.
m) where the proposal contains new or
5.9.4 The Audit Team Leader may also, with the
modified traffic signals and detailed
approval of the Client, invite representatives
of the police and the relevant highway designs have already been prepared
authority to advise on audits at Stages 1 and
and had a design/safety check
2 where the Audit Team Leader considers that
their participation will benefit the audit. undertaken by the Traffic Signals design
and checklist must also be forwarded to
5.10 The Audit brief
the Audit Team;
5.10.1 The Audit Brief is essential to the safety audit
procedure. It defines the scope of the audit n) details of other notable events that
and contains all the information necessary to have occurred since construction
give the Audit Team a full understanding of
the project. (stage 4 audits only); and
o) any other information relating to
5.10.2 The Audit Brief is prepared utilising the audit
brief checklist which is likely to include, if existing features, that in the opinion of
appropriate and available : the Client Officer, will be required by an
a) an instruction to carry out the Audit as per Audit Team that has no prior
this manual knowledge of the proposals or existing
b) Project title; conditions.
c) a description of the section of carriageway or
junction to be audited;
d) a description of the purpose and key
elements of the project;
e) A full set of drawings appropriate to the
stage of audit being undertaken.

P a g e | 21
Emirate of Abu Dhabi Road -Safety Audit Manual-

5.10.3 The Audit Team can request further 5.13.1 On return from the site visit(s) and
information from the design following a review of the Audit Brief
organization where the road safety and associated information, the Audit
audit brief which is considered Team needs to compile the Road Safety
inadequate Audit report.

5.11 Assess Audit Brief (and 5.13.2 At all Stages the Audit Team shall
prepare a written report which will be
associated information) in the format show in Annex C. The
5.11.1 This step is normally undertaken by the Stage 0, 1, 2 and 3 Audit Reports shall
Audit Team in parallel with the site include:
visit. The Audit Team will initially assess a) A brief description of the proposed
all the information provided within the scheme;
Audit Brief before undertaking the site
visit to flag up potential safety b) Identification of the audit stage and
problems that may be identified on team membership as well as the names
site. It may also give the Audit Team an of others contributing;
indication of when it is best to
undertake the site visit (time of day or c) Details of who was present at the site
day of week). For example, crash data visit, when it was undertaken and what
may indicate high occurrence of the site conditions were on the day of
crashes during the afternoon peak. On the visit (weather, traffic congestion,
return from the site visit, the Audit etc.);
Team will review all the information
again, with the new insight gained from d) The specific road safety problems
the visit. identified, supported with the
background reasoning;
5.12 Undertaking the Site Visit
e) A3 or A4 location map, marked up and
5.12.1 The Audit Team must undertake at referenced to problems and, if
least a daytime site visit for all stages of available, photographs of the problems
audit. A night time site visit must be identified;
undertaken at Pre- and Post-Opening
Stages (at stage 3). A night time site f) A statement, signed by the Audit Team
visit may be required at stage 4 if the Leader in the format given at Annex C;
crash data shows a problem during the and
hours of darkness.
g) A list of documents and drawings
5.12.2 All members of the Audit Team must
considered for the audit.
visit the site together and at the same
time.
h) The report shall contain a separate
5.12.3 It is the Audit Team Leader’s statement for each identified problem
responsibility to invite representatives describing the location and nature of
of the police and the relevant highway the problem and the type of crashes
authority to accompany the Audit considered likely to occur as a result of
Team to offer their views for the Stage the problem.
3 Audit at least 10 working days before
the site visit date i) Each problem shall be followed by an
associated recommendation. The Audit
5.12.4 The Audit Team Leader should notify Team should aim to provide
the Client of the date proposed for the proportionate and viable
site visit. recommendations to eliminate or
mitigate the identified problems.
5.13 Compile / issue audit report Recommendations to “consider” should
be avoided. Recommendations to
“monitor” should only be made where
a need to supplement the scheduled

P a g e | 22
Emirate of Abu Dhabi Road -Safety Audit Manual-

Stage 4 monitoring is specifically 5.14.3 The Client should provide copies of the
identified in terms of frequency and final exception report to the Design
incidence of particular vehicle Organisation and Audit Team Leader
manoeuvres or crash causation factors, for action and information respectively.
and the monitoring task can be
specifically allocated. 5.14.4 The Client is ultimately responsible for
initiating prompt action on all
j) Items such as correspondence with the recommendations in the audit report,
Overseeing Organisation or copies of and the exception report.
marked up checklists shall not be
included. 5.14.5 Until such time that an exception
report has been completed, where
5.13.3 The Audit Team Leader should send the required, the audit will be considered
audit report directly to the Client and as being incomplete.
not via the Design Organisation.
5.15 Approval of the Road
5.13.4 All drawings and the road safety audit Safety Audit and Exception
report should be copied into all
relevant parties, including the Police.
Report
5.15.1 The Police and the relevant road
5.13.5 The relevant highway authority and the
authority are to be sent the final Road
Police are to be sent a draft copy of the
Safety Audit report and exception or
Road Safety Audit report for each stage
client response report (including
for comment and will be asked to
designers response) for each stage of
provide their comments within 7
the audit and will be asked to provide
working days to the Audit Team leader.
their approval within 7 working days to
The comments received from the above
the Client so that any issues may be
mentioned authorities must be taken
considered.
into consideration..
5.15.2 Abu Dhabi Police and the relevant
roads authority reserves the right to
5.14 Compile and Issue the reject any road safety audit report or
Exception Report exception report where road safety is
likely to be compromised.
5.14.1 Once the audit report is issued to the
Client, they have to set about reviewing
each problem and recommendation
from the report in consultation with
the Design Organisation, and decide
whether to accept or reject them.

5.14.2 It is the Client’s responsibility to ensure


that all problems raised by the Audit
Team are given due consideration. The
Client should consult the Design
Organisation at this stage. The
response to each problem and
recommendation is formally
incorporated into an exception report
should any of the road safety audit
recommendations be rejected. This
should include: reasons why any
recommendation cannot be
implemented; alternatives considered;
and the difficulties involved in
implementing them.

P a g e | 23
Emirate of Abu Dhabi Road -Safety Audit Manual-

Instruct Design Team to


prepare response to
Road Safety Audit

Client Project Manager

Design Team

Design Team Road Safety Audit Team


prepares response Relevant Highway Authority and
ADP

All Key to process


recommendations
accepted ?
5.16 Issues outside the scope of the
NO YES
Audit Brief
5.16.1 The Audit Team Leader shall send any
Exception report comments on matters that are not covered by
prepared and Response to Road
issued to Project Safety Audit Team the Audit Brief to the Client in a separate
Sponsor letter. Maintenance defects noted during site
visits shall be immediately reported direct to
the relevant Maintenance Authority and the
Client shall also be informed.
Road safety report, design
team response and exception 5.17 Implement design changes
report (if required) to be
approved as a package by 5.17.1 Once the exception report has been
Relevant Highway Authority authorized (signed) by both the Design
and ADP Organisation, Abu Dhabi Police and the
relevant roads authority, the Design
Organisation can implement the design
changes accordingly. Please refer to Fig 5.2

Scheme Design
YES
Changes 5.18 Feedback knowledge gained
Revised Required ?
5.18.1 There is a risk that unless the knowledge
gained from audits are fed back into the
NO design process, the same mistakes will be
repeated in future. Road Safety Auditing
Scheme proceeds should therefore be seen as an opportunity to
to next stage of
design
provide constructive feedback to the Design
Organisation and Client.
Exception report recommendations prepared and 5.18.2 This can be done simply by circulating the
issued
audit reports and exception reports through
the Design Organisation, or by undertaking a
review periodically of the most common
Figure 5.2- Exception Report
problems identified by auditors for projects
designed by different design teams.

P a g e | 24
Emirate of Abu Dhabi Road -Safety Audit Manual-

5.18.3 There may also be an opportunity or


mechanism whereby this knowledge can be
fed into, and ultimately incorporated into,
design standards to improve them, as there
may be a design element that is inherently
unsafe or an aspect of a current standard that
is ambiguous or vague and which can be
misinterpreted by the designers.

5.18.4 There may also be opportunities for


knowledge to be transferred from the Design
Organisation to the Audit Team through the
issuing of exception reports to the Audit Team
for information. The knowledge exchange is
therefore essentially a two-way process.

P a g e | 25
Annex A Road Safety Audit Request Form
Emirate of Abu Dhabi Road -Safety Audit Manual-

Annex B Example CV Submission for assessment

P a g e | 27
Emirate of Abu Dhabi Road -Safety Audit Manual-

Annex C Example Road Safety Audit Report


Appendix C3 Stage 3

P a g e | 28
Emirate of Abu Dhabi Road -Safety Audit Manual-

Annex D Exception Report Template

P a g e | 29
Emirate of Abu Dhabi Road -Safety Audit Manual-

Annex E Client Checklist

P a g e | 30
Emirate of Abu Dhabi Road -Safety Audit Manual-

References

Austroads (1994). Road Safety Audit


(Publication No. AP-30/94). Sydney,
Australia: Austroads.
GHD (2009). Route E30 Truck Road (Abu
Austroads (2009). Guide to road safety - part Dhabi to Al Ain). Road Safety Audit,
6: Road Safety Audit (Publication No. Department of Transport, Abu Dhabi.
AGRS06/09). Sydney, Australia: Austroads.
Highways Agency (2003). HD 19/03 Road
Department of Transport – Road safety audit Safety Audit, (Design Manual for Roads and
Guidelines. Bridges, Volume 5: Assessment and
Preparation of Road Schemes, Section 2:
Dubai RTA - .
Preparation and Implementation, Part 2).
Abu Dhabi Municipality Road Safety Audit Dorking, UK: The Highway Agency
Procedures
IHT (2008). Road Safety Audit. London, UK:
EU Directive 2008/96/EC of the European Institution of Highways and Transportation
Parliament and the Council of 19 November (http://www.ciht.org.uk/en/publications/inde
2008 on road infrastructure safety x.cfm).
management, EU, Brussels. Belgium.
National Roads Authority (NRA) (2004). Road
Federal Highway Research Institute (FHRI) Safety Audit guidelines. Dublin, Ireland:
(2008). Road Safety Audit, current practice. National Roads Authority.
Road Infrastructure Safety Protection - Core
PIARC (2003). Road safety manual. Grande
Research and Development for Road Safety in
Arche de la Defense, France: PIARC Technical
Europe; Increasing Safety and Reliability of
Committee on Road Safety.
Secondary Roads for a Sustainable Surface
Transport (RIPCORD – ISEREST project), Final Ross, A., Baguley, C., Hills, B., McDonald, M.,
Report, Federal Highway Research Institute. and Silcock, D. (1991). Towards safer roads in
developing countries – a guide for planners
FHWA (2006). FHWA Road Safety Audit
and engineers, First Edition. Transport
guidelines (Publication No. FHWA–SA-06-06),
Research Laboratory: Crowthorne, UK.
Washington DC, USA: Federal Highway
Administration, US Department of Transport for London (TfL) (2005). Road
Transportation. Safety Audit, Procedure: SMS-007, Issue: 1.
London, UK: Transport for London, Surface
Gaardbo, A. and Schelling A. (1997). Manual
Transport.
of Road Safety Audit. Denmark: Road
Directorate, Ministry of Transport.

P a g e | 31
Emirate of Abu Dhabi Road -Safety Audit Manual-

P a g e | 32

You might also like