Rainfall Calculation
Chronologically Rainfall Calculation
Year Rainfall In mm
2014 915.6
2015 859.8
2016 1180
2017 615
2018 513.24
2019 494.8
2021 865.1
2022 1105.1
Total Rainfall =6548.68
Average Rainfall 6584.68
=818.58 mm
8
Descending Order
Year Rainfall In mm
2016 1180
2022 1105.1
2014 915.6
2021 865.1 (50% Dependable)
2015 859.8
2017 615
2018 513.24
2019 494.8
50% Dependable Rainfall for Survey Number 865.1 mm
Yeild Calculation
Capacity Table
1 2 3 4 5 6 7 8 9 10
1 377.60 0.00000
2 378.00 0.000464 0.000464 0.000000 0.000155 0.400 0.000062 0.000062 0.002185
3 380.00 0.004223 0.004687 0.001400 0.002029 2.000 0.004058 0.004120 0.145489
4 381.00 0.010067 0.014290 0.006520 0.006937 1.000 0.006937 0.011056 0.390459
5 382.00 0.049447 0.059514 0.022311 0.027275 1.000 0.027275 0.038331 1.353677
6 383.00 0.116778 0.166225 0.075989 0.080738 1.000 0.080738 0.119069 4.204939
7 384.00 0.179846 0.296624 0.144921 0.147182 1.000 0.147182 0.266251 9.402657
384.40 0.223237 0.403083 0.200370 0.201151 0.400 0.080460 0.346712 12.244118 LSL
8 385.00 0.288324 0.511561 0.253702 0.255088 0.600 0.153053 0.499764 17.649169
9 386.00 0.422478 0.710802 0.349014 0.353272 1.000 0.353272 0.852910 30.124966 FTL
10 387.00 0.575030 0.997508 0.492887 0.496798 1.000 0.496798 1.349834 47.669398
387.65 0.682016 1.257046 0.626242 0.627763 0.650 0.408046 1.757880 62.079537 HFL
11 388.00 0.739624 1.421640 0.710236 0.710625 0.350 0.248719 2.006599 70.863045
12 389.50 0.931147 1.670771 0.829879 0.833550 1.500 1.250325 3.256924 115.01827 TBL
13 390.00 1.109668 2.040815 1.016496 1.019104 0.500 0.509552 3.766476 133.01309
Scale 10 x 10 Scale 1: 1000
M2 Cm2 Area in milimeter2 A X 15 X 15 Original area
464.016 4.64016 464.016 464.016 4.64016
4222.89 42.2289 4222.89 4222.89 42.2289
10067.4 100.674 10067.396 10067.4 100.674
49447.18 494.4718 49447.182 49447.18 494.4718
116777.6 1167.776 116777.621 116777.6 1167.776
179845.7 1798.457 179845.709 179845.7 1798.457
C× A
Formula = Q =
√ A+ 4
Where,
Q is maximum flood discharge in Cu. Ft./Sec
C = constant
Inglis “C’’ for 45.78 Sq. km = 6810.10 ( Refer From Capacity Table )
6810.10× 17.67
Q=
√ 17.67+4
Q = 25850.002 cu. Ft / sec
Q = 731.99 cu.m/sec
Q = 732 cu.m / sec
Maximum flood Discharge = 732 cu.m / sec
L = Q / 1.704 × H1/3
L = 732 / 1.704 × (1.5)3/2
L = 233.83 m
L = 234
C.O.F Type waste weir
1. Fixing LSL
a) Catchment Area
= 17.675 Sq km
= 0.346712 mm3
FTL = 386.00
Add1.50 in FTL = 387.50
And 0.50 for Top Hearting = 388.00
TIBL = 389.00
f) Capacity of this RL in Mc ft
= 12.1440 Mc ft
2. Storage Planning
3. Losses
Evaporation losses is to be considered as 1.2192 m over mean area of FTL and LSL for
utilization and same for storage purpose be considered as 0.9144 m over LSL and FTL.
Evaporation Losses
= RL – Area in Mm2
Area at LSL = 384.40 - 0.179846 Mm2
= 0.852910 - 0.3671
Net Storage = 0.48581 Mm3
Storage Calculation
Dead Storage
Load on silt pocket
6 Ha. m Per 100 Sq. m / Year
Controlling Level
1) NBL = 377.600 m
2) LS = 384.40 m
3) FTL = 386.00 m
4) HFL = 387.65 m
5) TBL = 389.50 m
Free
board 1.5
FSL 387.50
D/s f/wall 387.500
d1= 1.50
CBL 386.00 1.00
1.950
0.55 1.50
1 D/s MWL 385.55
2.50 1.00 0.60 1.050 D2 D/S CBL
0.3 1.00
Fou
Foun.n RL 383.50 4.05 n.n RL 383.50
8.03
2.38 1.60
DATA
Centre G L 387 M
Left side GL 388 M
Right Side GL 386.4 M
Average G.L. 387.13 M
F.T. L 386.00 M
Top of U/s Weir 386 M
Top of Wing wall 389.00 M
Maximum water
Level (M.W.L) 387.50 M
Discharge 732 cum / sec
Foundation R.L for Main Weir 383.50 M
Foundation R.L for End Weir 383.50 M
Top Width = b 1.00 M
Slope 0.55
Total Height of U/s weir 2.50 Mt (386 - 383.5)
Bottom Width =b1 2.38 M
D/S weir T.W. = 0.60 M
D/S weir B.W. = 1.60 M
D/S weir Ht. = 1.00 M
1) U/S Weir
Flood Lift = 1.50 m
Top Width of U/S Weir Tw = 1.00 m
CBL = Foundation of Main Weir + D/S Weir Height
CBL = 383.50 + 1.00 = 384.50
Height above NBL “HW’’ = 1.50 m
Foundation Depth below NBL = 3.50 m
(By 1.50 Co. f Waste Weir)
Total Height of U/S Weir Foundation Weir-Foundation RC
= (386-383.5)
Bottom Width “Bw” = 2.30
Batter = 0.55
Free Board = 1.50 m
2) D/S Weir
1. Top width of D/S Weir = 0.60 m
2. Height of D/S Weir = 1.000 m
3. Height Above Cushion Concrete.
1 ( H +d)
t= =
5( H +d ) 5
1.50+1.50
t= =0.6 mt
5
Adopt = 0.30 mt
6. Batter = 1
Length of apron = 4.05 as per MI Manual
Length of apron adopted = 4.05 m
DESIGN OF TAIL CHANNEL
FROM
RD 0 TO 30
Designed Max. flood discharge = 732 m3 / sec
234.05
11.050
0.5:1 0.5: 1
1.050
234
Formula: - Q = A × V
Were,
V = Velocity in M/Sec
Were,
N = 0.03
R=A/P
R = A/P =1.03 m
:-Q=A×V
= 798.59 M3/Sec Against 732 M3/Sec, which is More than Max. Flood Discharge
235.05
0.5:1 11.550 0.5:1
234
Formula: - Q = A × V
Were,
V = Velocity in M/Sec
Were,
N = 0.03
R = A/P =1.330 m
:-Q=A×V
= 502.182 M3/Sec Against 732 M3/Sec, which is More than Max. Flood Discharge