You are on page 1of 12

Doc. Code AYR.HSE.PR.

04
HSE EXCAVTION Publish Date 09.04.2022
BAC
PROCEDURE Revision No
Revision Date
00
-

1. REVISION DEFINITIONS

Rev. Date Title Description

01

02

03

04

05

2-Purpose
The purpose of this procedure is to define the safety actions that are required to control civil works involving
excavation activities during the Project which be prepared in advance for a building or insulation pipe and To
protect the employees, people who may work, live in or adjacent to an excavation or trench from any risk.

3-DEFINITION AND ABBREVIATIONS

3.1 ABBREVIATIONS

HIA Health Impact Assessment


HSE MS Health, Safety and Environmental Management System.
SOP Standard Management Operation.
OHSAS Occupational Health and Safety Assessment Series.
WHSA Work Health and Safety Act.
EER Evacuation, Escape and Rescue.
MOM Mints of Meeting

1. REFERENCE DOCUMENTATION

4.1. Project Documents:

Document No Title
252100DFPA00004 Project Approved HSE Plan
Appendix E - HSE Requirements Health & Hygiene Plan
25210DFPA0002 HSE Training Producer
Doc. Code AYR.XXX.FR.00
Publish Date -
BAC EXCAVATION PROCEDURE Revision No 00
Revision Date -

1.3.0.06 The company emergency response plan


The company emergency Preparedness and
1.3.2.8
response.
1.3.2.11 The company Development health program.

4.2 International Standards

OHSAS 29 CFR part 1910.332 & 1915.508.


OHSAS 18001:2007.Health and safety management systems.

2. RESPONSIBILITIES

2.1 Construction Manager

 The Construction Manager (CM) and the HSE Manager are responsible for implementing the
Excavation Safety procedure.

 The CM will report any issues pertaining to the difficulty of implementing this procedure directly to the
PM.

2.2 HSE Manager

 HSE Manager or his HSE staff shall prepare the Mom for HSE issues discussed at site and it shall be
approved by the HSE Manager and sent to the CM and PM for review and further actions to complete
the Work safely at site.

 HSE Manager shall ensure that the HSE Staff is implementing all requirements to keep the site and
employee safe per Minimum Safety Standard on Excavation in Construction standard.

 HSE Manager and his staff shall be responsible for training all employees working in the excavation
activities as per Company approved HSE training procedure Minimum Safety Standard on Excavation in
Construction standard. The training shall include the basic requirements of the Excavations per Safety
standard

o Permit to Work application, requirement and its limitation.


o Excavation Hazards and Assessment.
o Shoring and Sloping system.
o Removal, Storage and Placement of spoil, materials, tools and equipment.
o Access, Ingress and Egress.
o Barrier and Stop Block.
o Lighting.
This document is property of Shakir Naje
It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.
_________________________________________________________________________________________
Doc. Code AYR.XXX.FR.00
Publish Date -
BAC EXCAVATION PROCEDURE Revision No 00
Revision Date -

o Ventilation and Atmospheric Monitoring.


o Emergency and Rescue.

 HSEQ Manager shall be responsible for displaying IGC Quality Policy (also requirements of ISO system)
displayed in the IGC President’s Policy Statement at clear locations at the site offices for the site staff to
read and abide by.
 HSE staff shall ensure that all drivers working in excavation shall be with valid driving licenses.

2.3 Subcontractors

 Shall be responsible for the following:


 Briefing personnel doing the work on the safe working practices required. Application of any work
permits that are provided.
 Provision of equipment that is capable of carrying out the work safely, has been maintained and is
certified for use on the project.
 Provision of adequate barriers, flashing lights and signs for the work.
 Programmed the work to ensure that any trenches that go across roads are done so in a manner that
maintains access.
 Notify the contractor supervisor of any unmarked utilities found.

2.4 Subcontractor HSE manager

The Sub Contractor shall ensure the respect of this procedure as described above. Each Work Permit shall be
accompanied by a dedicated JSA.

2.5 Competent Person

 Shall ensure that excavation permit is secured before start of the excavation.
 Ensure that safe excavation practices are followed during the execution of the Works.
 Ensure that the Minimum Safety Standard on Excavation in Construction standard is implemented at
site and follow the instructions of HSE and CM instructions to implement it.

 Ensure that the Minimum Safety Standard on Confined Space Entry standard is implemented at site
and follow the instructions of HSE and CM instructions to implement it.

2.6 Soil Testing

The Competent Person shall classify the soil type in accordance with the definitions section and on the basis of
at least one visual and one manual analysis, or as per prior company classification of soil type. These tests are
designed to determine stability based on a number of criteria: cohesiveness, whether or not it is fissured, the
presence and amount of water, the unconfined compressive strength, the presence of layering, prior
excavation and vibration.
An examination of the job site will determine sources of vibration or evidence of prior excavation, such as existing
underground utilities. Observation of the excavation will determine the presence and amount of moisture as well
as layering, faulting and fracturing.
This document is property of Shakir Naje
It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.
_________________________________________________________________________________________
Doc. Code AYR.XXX.FR.00
Publish Date -
BAC EXCAVATION PROCEDURE Revision No 00
Revision Date -

The unconfined compressive strength will type a sample. There are several methods of testing for it. The thumb
penetration test is useful and easy to perform. If the sample can be dented, but penetrated only with great effort, it
is type A. If it can be penetrated several inches and molded by light pressure, it is Type C. Type B can be penetrated
with little effort and molded.
Note: Field tests are to be performed on “freshly excavated” samples
The Competent Person shall perform multiple checks at each 4 foot (1.2m) level of the excavation to generate
consistent, corroborating data along its depth and length. The soil type is likely to change many times along a right
of way and the moisture content will vary with the weather and job conditions. All these factors must be taken into
consideration during the course of the work. It is the responsibility of the competent person to be sure of the soil
type at all times and that the protective measures are also sufficient at all times

2.7 Ground Conditions

As applied by Company, the following definitions shall apply to ground condition identification and suitable
control measures shall be adopted to ensure the safety of an excavation and, the personnel who enter:
Stable Rock

 Type A
 Type B
 Type C

Note: Stability is greatest in stable rock and decreases through Type A and B or Type C, which is the least
stable. Contractor shall implement the ground condition procedure as shall be applicable to its scope of work.
To this effect, where Company classification exists for Contractor location, Contractor shall request for such
classification and apply them.

3. PROCEDURE
6.1 Permits

 Excavation permit shall be secured as per procedure outlined in the Minimum Safety Standard on
Excavation in Construction standard.
 Night time permit shall be taken ahead of time for any excavation that will take place after sunset.
If there is any night activity should or must have PTW prior started to work.

6.2 Safety

 Physical barriers must be erected around all excavation by a Competent Person.


 Warning signs and adequate physical barricades or protective covers must be provided for all trenches,
wells, pits and shafts by a Competent Person.
 The HSE Manager will implement additional safety measures if requested by the
 Company as per Contract requirements and approved by the PM.
 All workers at site shall be wearing their PPE per HSE procedure.
 Barricaded and/ or identified area shall be designated for excavated material (Top Soil, Soft Rock, Hard
Rocks, etc.) kept at site to be use as per instructions.
 All vehicles working on site for transporting, moving and excavating the material shall be inspected,
with valid documentation and follow Contractor’s HSE procedures.
This document is property of Shakir Naje
It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.
_________________________________________________________________________________________
Doc. Code AYR.XXX.FR.00
Publish Date -
BAC EXCAVATION PROCEDURE Revision No 00
Revision Date -

 The use of explosives is forbidden.


 Smoking inside the excavating area is forbidden.
 All the excavated area should have 2 proper way to in one for excite and another for entrance
 Not with handmade ladder and should be proved with safety waring sign and barricaded.
 The barricaded depend on the depth of the excavated area like if its less than 1M it should be
barricaded with light barricading if its more than 2 M should be barricaded with scaffolding barricading
and the scaffolding producer must be implanted.

6.3 Access and Egress

 A stairway, ladder, ramp or other safe means of access or egress shall be provided in all trenches that
are 4 feet (1.2.m) or more in depth and shall be positioned at adequate intervals of lateral travel for
employees, and as constructed by contractor. In addition, two access and egress points should be
established if possible.
 Standard guardrails shall be provided on all walkways, ramps or bridges where employees are required
or permitted to cross over excavation or trenches.

6.4 Trench Excavations

 Employees shall not work in Trench Excavations in which water is accumulating, unless adequate
precautions have been taken to protect employees against the hazards posed by water accumulation.
 If water is controlled or prevented from accumulating by the use of water de-pumping equipment, the
water removal equipment and operations shall be monitored by an attendant and competent person
to ensure proper operation.
 Excavations that exceed 1.2m or 4 ft. in depth and require personnel to enter or perform works must
implement the confined space entry procedure.

6.5 Excavation Hazards

 HSE Manager and the CM shall prepare a Job Safety Analysis for the excavation activity for each type of
excavation before the start of the excavation in order to ensure that the safety measures are taken for
workers.
 Minimum Safety Standard on Excavation in Construction safety measure for the types of hazard
mentioned in the standard shall be evaluated if these types of hazards exist.

 For example, Benching shall be used as a Protective Method against cave in.
 Underground Cables & Buried Services, existing or newly installed, are a major concern during
excavation work. CM shall ensure that As Built Drawings are checked to ensure proper coordination
between different types of excavations.

6.6 Trench Crossing


 Minimum Safety Standard on Excavation in Construction shall be followed.
 Trenches will be crossed only where safe crossings have been provided.

This document is property of Shakir Naje


It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.
_________________________________________________________________________________________
Doc. Code AYR.XXX.FR.00
Publish Date -
BAC EXCAVATION PROCEDURE Revision No 00
Revision Date -

 Where walkways or bridges are provided across excavated areas, they shall have the safety
requirements to complete the Works.
 Access to, from and over excavation area should be adequately considered and provided for the
following types of vehicles:
 Excavated soil removal vehicle.
 Material transportation vehicle (Mobile Cranes, Lorries and Forklift).
 Normal passenger vehicle.

6.7 Protective Systems

 Employee shall be protected by Protective Systems, from excavated or other materials, or equipment
that could fall or roll into the excavation by placing and storing such material or equipment a minimum
distance of 4 feet (1.2m) from the edge of the excavation. Employees shall be trained regularly with
the EER Plans in order to ensure correct behavior shall be followed in case of emergency.
 Each employee in an excavation shall be protected from cave-ins by an adequate Protective System.

6.8 Inspections

 Prior to the start of work, the competent person shall make daily inspections of excavations, trenches,
adjacent areas, and protective systems and as required throughout the shift. Inspections shall be made
after every rainstorm, or unusual work activities e.g. excess heavy equipment travel or vibration.
 Employees will not be permitted to work in excavations or trenches if the Competent Person finds
evidence of a situation that could result in a possible cave-in, failure of a protective system, hazardous
atmosphere or other hazardous condition.
 Inspections will be properly documented. This record should be maintained on file in the HSE
supervisor until the excavation is back-filled and shall be available for review upon request.

6.9 General Rules

 The following points from the Project’s General Specification for Excavation shall be followed:
 The use of explosives is forbidden.
 Drainage of water from excavations, if required, must be carried out using suitable equipment such as,
for example, motor driven suction pumps, submersible pumps, or well-point systems.
 The drainage operations shall continue until the Works are completed, unless otherwise agreed upon.
 Dumped materials resulting from excavations shall not be prejudicial to the works, to the free drainage
of surface water, or to existing structures.
 Roots, shrubs, debris, plants, etc. from topsoil removal must always be transported to dump areas.
 Smoking inside the excavating area is forbidden.

4. Design of Sloping and Benching Systems


 The slopes and configuration of sloping and benching system for excavation 5 feet (1.5m) to 20 feet
(6.0m) in depth and hire shall be selected by IGC and shall be in accordance with the geotechnical
report recommendations requirements.

This document is property of Shakir Naje


It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.
_________________________________________________________________________________________
Doc. Code AYR.XXX.FR.00
Publish Date -
BAC EXCAVATION PROCEDURE Revision No 00
Revision Date -

5. Support systems, Shield Systems, Other Protective Systems


 Minimum Safety Standard on Excavation in Construction shall be followed at site.
 Design of support systems, shield systems, and other protective systems shall be selected and
constructed by IGC.
 Timber or aluminum hydraulic shoring in trenches shall be determined in accordance with the
conditions of soil classification
 Design of support systems, shield systems or other protective systems, that are drawn from
manufacturer’s tabulated data shall be in accordance with all specifications, recommendations and
limitations issued or made by the manufacturer (for example: hydraulic shores). This information must
be maintained on file on site.

6. Materials and Equipment


 Materials and equipment used for protective systems shall be free from damage or defects that might
impair their proper function.
 Manufactured materials and equipment used for protective systems shall be used and maintained in a
manner that is consistent with the recommendations of the manufacturer, and in a manner that will
prevent employee exposure to hazards.
 Warning signs shall be used at all time.

7. Installation and Removal of Support Systems

 Minimum Safety Standard on Excavation in Construction shall be followed at site.


 Members of support systems shall be securely connected together to prevent sliding falling, kick-outs,
or other predictable failure.
 Support systems shall be installed and removed in a manner that protects employees from cave-ins,
structural collapses, or from being struck by members of the support system.
 Individual members of support systems shall not be subjected to loads exceeding which the members
were designed to withstand.

 Before temporary removal of individual support members begins, additional precautions shall be taken
to ensure the safety of employees, such as installing other structural members to carry the loads
imposed on the support system.
 Removal shall begin at, and progress from, the bottom of the excavation. Support members shall be
released slowly so as to note any indication of possible failure of the remaining members of the
structure or possible cave-in of the sides of the excavation.
 Back-filling shall progress together with the removal of support systems from excavations.

8. Condition Change Monitoring


 Ground and environmentally conditions shall be continuously monitored for change, the Competent
Person (erg Civil Engineer) as per Minimum Safety Standard on Excavation in Construction standard.
 Excavated areas and trenches shall be inspected by the competent person after severe weather
conditions to ensure that implemented safety conditions still exist.
This document is property of Shakir Naje
It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.
_________________________________________________________________________________________
Doc. Code AYR.XXX.FR.00
Publish Date -
BAC EXCAVATION PROCEDURE Revision No 00
Revision Date -

9. Backfill
Backfill operations shall be carried out in accordance with the following guidelines:
Backstops will be provided for vehicles dumping material to prevent them over running the edge.
Consideration will be given to the specification for compaction qualities, need for tile markers and tiles and
other protection measures necessary for the protection of equipment.
Redundant spoil not backfilled will be removed to an area identified in advance.
A safe system of work will be identified and implemented for the removal of timber supports, steel sheeting
and piles. Consideration will include provision of lifting appliances suitable to take the load of embedded
sheet piles without damage.

10. Records
The Contractor Superintendent will ensure that new facilities are clearly reflected in the as-built drawings.
Every subcontractor will record all the information included in the Excavations Record in Attachment
Weekly the record will be checked and reviewed by the competent Contractor Superintendent and the
Contractor Field HSE Manager/HSE Coordinator.
The Excavations Record will include the results of the daily pre-work check and of all the check following
particular events that could compromise the stability and the health of the workers.
All the machinery that leave the site work should be inform the site Eng. and the site safety supervisor and to
be mention in the recorded time with the driver name and machine number.

11. Training
All employees who are to be engaged in excavation works which consists of excavations that are to be greater
than 1.2 meters deep shall be instructed by a competent person from the Subcontractor on safe methods of
working.
Instruction will cover as a minimum the following subjects:
 Requirements for excavation permit. Shoring, benching sloping.
 Removal of spoil.
 Exclusion zones for machines & equipment alongside excavations. Unstable soil.
 Leaching of water through excavation walls.
 Access and egress.
 Placement of material into excavation by cranes or other machinery.

11.1 Safety topic Trenching and Excavation

To prevent cave-ins:

 SLOPE or bench trench walls


 SHORE trench walls with supports, or
 SHIELD trench walls with trench boxes

This document is property of Shakir Naje


It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.
_________________________________________________________________________________________
Doc. Code AYR.XXX.FR.00
Publish Date -
BAC EXCAVATION PROCEDURE Revision No 00
Revision Date -

Employers should also ensure there is a safe way to enter and exit the trench. Keep materials away from the
edge of the trench. Look for standing water or atmospheric hazards. Never enter a trench unless it has been
properly inspected.

This document is property of Shakir Naje


It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.
_________________________________________________________________________________________
AYR.XXX.FR.0
Doc. Code
4
BAC EXCAVATION PROCEDURE Publish Date
Revision No
-
00
Revision Date -

12. ATTACHMENT
15.1 Safety check list.

15.2 The Company Org. Chart.

15.3 The HSE Org. Chart.


15.1 Safety check list.

Company/Area:

Date of
Inspection Location:
Inspection:
Name of Inspector: Position:
Inspection Record Inspection
Approved By: Reference:

S./No CHECKLIST YES NO


Sub-Contractor to ensure that the area of excavation is physically
1. Inspected for all other common activities. Risk reduction measures
selected for the excavation work (Check PTW)
Excavations, adjacent areas, and protective systems inspected by a
2. Competent person daily before the start of work.

Personnel protected from loose rock or soil that could pose a hazard
3. By falling or rolling into the excavation.

Excavation clearance certificate signed by all Mechanical, Electrical,


4. Piping, Instrument Department.

Soils, materials, and equipment are located a minimum of 2 m from


5. Edges of excavation.

Protection Barriers (hard Barricades ) provided at all remote


6. excavations, wells, pits, shafts, etc.

Walkways and bridges over excavations 1.5 m or more in depth are


7. Equipped with standard guardrails and toe boards.

Examination and inspection made after each rainstorm or heavy


8. Rain.

Atmosphere tested when there is a possibility of oxygen deficiency


9. Or build-up of hazardous gases.

Support systems provided in ensure stability of adjacent structures,


10. Buildings, roadways, sidewalks, walls, etc.

In lieu of a shoring system, the sides or walls of an excavation or


11. Trench to be sloped, providing equivalent protection is afforded.

Note

Eng. Signature Safety Supervisor signature

This document is property of Shakir Naje


It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.
_________________________________________________________________________________________
The HSE Org. Chart.

This document is property of Shakir Naje


It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.
_________________________________________________________________________________________

You might also like