You are on page 1of 8

Saudi Aramco 2616-ENG (3/99) 

OPERNS.

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
SAUDI ARAMCO OIL COMPANY

SECTION 07820
CERT

SKYLIGHTS
PART 01 - GENERAL
ENG’G

1.01 SECTION INCLUDES

A. Engineering of production documents, including structural calculations


of the entire skylight system.
DESCRIPTION

B. Fabrication and erection of skylight frames.

C. Final finish of metal parts.

D. Skylight related flashings.

1.02 RELATED SECTIONS


DATE JOB/EWO

A. Section 05120 Structural Steel.

B. Section 05160 Space Frames.


REV.
NO.

C. Section 05500 Metal Fabrications.


DISCIPLINE
ENGINEER

__ ________ _
D. Section 07720 Roof and Deck Insulation
 DATE: ________ 
PROJECT E. Section 07620 Sheet Metal Flashing and Trim.
ENGINEER
____________
DATE ______ F. Section 07920 Sealants and Caulking.
CERTIFIED
G. Section 08800 Glazing.
_ __________
DATE: ________
. H. Section 01352 LEED Requirements
CONSTRUCTION
AGENCY
________________
I. Section 01524 – Construction Waste Management
DATE: _________

OPERATIONS

______________ 1.03 REFERENCES


DATE:_________

A. ASTM A36 Structural Steel.


APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER
VERIFICATION
EDSD

B. ASTM A123 Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel


Products.
Date:
By:

C. ASTM B209 Aluminum and Aluminum-Alloy Sheet and Plate.


OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


THIS INDICATES THAT REV. NO.________

(DCC) NO.: __________________________

D. ASTM B221 Aluminum and Aluminum-Alloy Extruded Bar, Rod,


REVISION CERTIFICATION

Wire, Shape, and Tube.


E. ASTM E283 Rate of Air Leakage Through Exterior Windows,
SECTION 07820

CONSTRUCTION SPECIFICATIONS DWG. TYPE PLANT NO. INDEX DRAWING NO. SHT. NO. REV. NO.

KING ABDULLAH PETROLEUM DOC


K55 A VE-425113 1
AND RESEARCH CENTER OF 00
RIYADH SAUDI ARABIA JOB/EWO# BI-25-00013 8
15-May-10 
Saudi Aramco 2616-ENG (3/99) 
OPERNS.

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
SAUDI ARAMCO OIL COMPANY

Curtain Walls, Walls, and Doors.


CERT

F. ASTM E330 Structural Performance of Exterior Windows, Curtain


Walls, and Doors by Uniform Static Air Pressure
ENG’G

Difference.

G. ASTM E331 Test Method for Water Penetration of Exterior


Windows, Curtain Walls, and Doors by Uniform Static
Air Pressure Difference.
DESCRIPTION

H. FS TT-C-494 Coating Compound, Bituminous, Solvent Type, Acid


Resistant.

I . SSPC (Steel Structure Painting Council) - Paint Specification No. 15.

1.03 SYSTEM DESCRIPTION


DATE JOB/EWO

A. Design Requirements:

1. Extruded aluminum members with a system of alternate


serrations for attachment of exterior caps and glass supports.
REV.
NO.

2. Integral guttering system within skylight framing members for


DISCIPLINE
ENGINEER positive drainage of condensation.
__ ________ _
 DATE: ________ 3. Flush glazed exterior joints as indicated on the drawings. 
PROJECT
ENGINEER
1.04 SUBMITTALS
____________
DATE ______

CERTIFIED
A. Submit under provision of Saudi Aramco Contract Documents.

_ __________ B. Submit shop drawings showing plans, elevations and sections as


DATE: ________
required to fully describe the skylight construction for the SAUDI
CONSTRUCTION
AGENCY
ARAMCO approval prior to starting fabrication.
________________
DATE: _________ B. Submit structural calculations prepared in accordance with the
OPERATIONS Aluminum Association’s Specifications for Aluminum Structures (AA):
______________ SAS-301.
DATE:_________

C. Submit:
APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER
VERIFICATION
EDSD

1. Certification that adhesion of sealant to samples of metal and


glass is adequate when tested in accordance with ASTM C794.
Date:
By:

2. Certification that materials in contact with sealant are compatible


OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


THIS INDICATES THAT REV. NO.________

(DCC) NO.: __________________________

with sealant after being exposed to 2,000 - 4,000 micro watt


ultraviolet radiation for 21 days.
REVISION CERTIFICATION

SECTION 07820

CONSTRUCTION SPECIFICATIONS DWG. TYPE PLANT NO. INDEX DRAWING NO. SHT. NO. REV. NO.

KING ABDULLAH PETROLEUM DOC


K55 A VE-425113 2
AND RESEARCH CENTER OF 00
RIYADH SAUDI ARABIA JOB/EWO# BI-25-00013 8
15-May-10 
Saudi Aramco 2616-ENG (3/99) 
OPERNS.

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
SAUDI ARAMCO OIL COMPANY

3. Statement that stress on each detailed sealant joint will not


exceed design stress of sealant when exposed to specified wind
CERT

loads.
ENG’G

D. Submit two, 12” x 12” samples for glass.

E. Submit two, manufacturer’s samples of each type of sealant.


DESCRIPTION

F. Submit two, 6” long samples of extrusions with appropriate finish.

G. LEED Submittals
1. Product Data for Credit EQ 4.1: For Sealants and Adhesives
used at Project site, including printed statement of VOC content.

1.05 QUALITY ASSURANCE


DATE JOB/EWO

A. Skylight fabrication shall comply with the requirements of IBC Chapter


24 Edition 2006.

B. Work of this Section, including, engineering, fabrication, finishing, and


REV.
NO.

preparation at the job site, erection and glazing of the skylight system
shall be the responsibility of the skylight manufacturer. The
DISCIPLINE
ENGINEER manufacturer shall be regularly engaged in the preceding phases of
__ ________ _
construction of skylights and be able to demonstrate that he has
 DATE: ________ successfully performed on comparable projects over the previous five 
PROJECT years.
ENGINEER
____________
DATE ______ 1.06 WARRANTY
CERTIFIED
A. Certify that skylight frame is free of defects in design, material, and
_ __________ construction for a period of 10 days from the date of Substantial
DATE: ________
Completion.
CONSTRUCTION
AGENCY
________________
B. Warrant glass against defective materials, delamination, seal failure,
DATE: _________ deficient wrapping and defects in manufacture per the glass
OPERATIONS manufacturer’s standard warranties.
______________
DATE:_________
C. Warrant structural sealant for a period of 10 years per sealant
manufacturer’s standard warranty of merchantable quality.
APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER
VERIFICATION
EDSD

PART 02 - PRODUCTS
Date:
By:

2.01 MATERIALS
OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


THIS INDICATES THAT REV. NO.________

(DCC) NO.: __________________________

A. Framework:
REVISION CERTIFICATION

1. Principle Supporting Members shall be thermally broken 0.125


in. minimum thickness extruded aluminum, alloy 6063-T5, 6063-
SECTION 07820

CONSTRUCTION SPECIFICATIONS DWG. TYPE PLANT NO. INDEX DRAWING NO. SHT. NO. REV. NO.

KING ABDULLAH PETROLEUM DOC


K55 A VE-425113 3
AND RESEARCH CENTER OF 00
RIYADH SAUDI ARABIA JOB/EWO# BI-25-00013 8
15-May-10 
Saudi Aramco 2616-ENG (3/99) 
OPERNS.

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
SAUDI ARAMCO OIL COMPANY

T6, or 6061-T6 per ASTM B221. Sizes, shapes and profiles


similar to Zamel Skylight System PU RLIN# 23609 or approved
CERT

equal.
ENG’G

2. Snap-On Covers, Gutters, Flashing Strips and Miscellaneous


Non-supporting Trim: 0.062 in. minimum thickness extruded
aluminum, alloy 6063-T5, per ASTM B221.

3. Principle Formed Metal Member shall be thermally broken:


DESCRIPTION

0.125-in. minimum thickness aluminum, alloy (5052) or (6061-


T6), per ASTM B209. Sizes, shapes and profiles similar to
Zamil Skylight System PU RLIN # 23614 or approved equal.

B. Glazing Strips:

1. Extruded EPDM rubber designed to comply with the following


specifications.
DATE JOB/EWO

a. Hardness: ASTM D2240 Type A55 +/- 5 durometer.

b. Tensile Strength: ASTM D412 1800 psi (min.).


REV.
NO.

c. Elongation: 500% (min.)


DISCIPLINE
ENGINEER

__ ________ _
d. Color: black.
 DATE: ________ 
PROJECT 2. Compression Set: ASTM D395 Method B, 22 hours @ 212 deg.
ENGINEER
F.: 25% (max.)
____________
DATE ______

CERTIFIED 3. Heat Aging Characteristics:

_ __________ a. 70 hours @ 212 deg. F.


DATE: ________

CONSTRUCTION
AGENCY
b. ASTM D2240 Hardness Change: +5 durometer.
________________
DATE: _________ c. ASTM D412 Tensile Change: -10%.
OPERATIONS

______________ d. ASTM D412 Elongation Change: -20%.


DATE:_________

4. ASTM D1171 Weather Resistance at 1 Part Ozone per Million,


APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER
VERIFICATION

500 hours at 20% Bongation: No cracks.


EDSD

5. No visual checks, cracks or breaks after completion of tests.


Date:
By:

C. Setting Blocks:
OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


THIS INDICATES THAT REV. NO.________

(DCC) NO.: __________________________

1. Extruded Type II silicone rubber designed to permit adhesion


REVISION CERTIFICATION

and comply with the following specifications:


SECTION 07820

CONSTRUCTION SPECIFICATIONS DWG. TYPE PLANT NO. INDEX DRAWING NO. SHT. NO. REV. NO.

KING ABDULLAH PETROLEUM DOC


K55 A VE-425113 4
AND RESEARCH CENTER OF 00
RIYADH SAUDI ARABIA JOB/EWO# BI-25-00013 8
15-May-10 
Saudi Aramco 2616-ENG (3/99) 
OPERNS.

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
SAUDI ARAMCO OIL COMPANY

a. Hardness: ASTM D2240 Type A 80 +/- durometer.


CERT

b. Color: Black.
ENG’G

D. Fasteners:

1. For Exterior Cap Retrainers: ASTM A193 B8 300 series


stainless steel screws.
DESCRIPTION

2. For Framework Connections: ASTM B211 2024-T4 aluminum,


ASTM A193 B8 300 series stainless steel, and ASTM B316
aluminum rivets, as required by connection.

3. For Anchoring Skylight to Support Structure: ASTM A307 zinc


plated steel fasteners.

E. Glazing Unit Composition:


DATE JOB/EWO

1. Glass units are to be insulating glass Type I.


“Refer to Section 08800”.
REV.
NO.

F. Sealants:
DISCIPLINE
ENGINEER 1. Structural Flush Glazed Joints: High performance silicone
__ ________ _
sealant applied in accordance with manufacturer’s
 DATE: ________ recommendations. 
PROJECT
ENGINEER
2. Non-structural Flush Glazed Joints and Weather Seal Joints;
____________
DATE ______ Silicone sealants applied in accordance with manufacturer’s
CERTIFIED recommendations.

_ __________ 3. Structural silicone shall not be used to support dead weight of


DATE: ________
vertical glass or panels.
CONSTRUCTION
AGENCY
________________
Refer to Section 07920; Sealants and Caulking.
DATE: _________

OPERATIONS 4. All Adhesives and Sealants shall be compliant with Section


______________ 01352 – LEED Requirements.
DATE:_________

2.02 FABRICATION
APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER
VERIFICATION
EDSD

A. Construct skylights using thermally broken extruded aluminum


members.
Date:
By:

B. Construct skylights using a continuous thermally broken aluminum curb


OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


THIS INDICATES THAT REV. NO.________

(DCC) NO.: __________________________

with expansion joints as required.


REVISION CERTIFICATION

SECTION 07820

CONSTRUCTION SPECIFICATIONS DWG. TYPE PLANT NO. INDEX DRAWING NO. SHT. NO. REV. NO.

KING ABDULLAH PETROLEUM DOC


K55 A VE-425113 5
AND RESEARCH CENTER OF 00
RIYADH SAUDI ARABIA JOB/EWO# BI-25-00013 8
15-May-10 
Saudi Aramco 2616-ENG (3/99) 
OPERNS.

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
SAUDI ARAMCO OIL COMPANY

C. Insofar as practicable, fit and assemble work in manufacturer’s shop.


Work which cannot be permanently assembled shall be shop
CERT

assembled, marked, and disassembled before shipment to the site.


ENG’G

D. Design rafter bars for snap-in type glazing strips.

E. Attach Snap-On cap retainers using stainless steel fasteners into a


system of alternate serrations, at a maximum spacing of 12-in on
center.
DESCRIPTION

F. Design Snap-On cap retainer fasteners to provide not more than 10 lbs.
per lineal in. or compression on the glazing strips and glass edge.

G. Use Snap-On type caps to conceal Snap-On cap retainer fasteners.

H. Where applicable shop rivet or weld aluminum clips to framing members


Or field bolt at installation.
DATE JOB/EWO

I. Set glass with exterior EPDM glazing strips.

J. Use silicone setting blocks to support glass and to provide proper edge
REV.
NO.

clearances and glass bites.


DISCIPLINE
ENGINEER K. Locate weep holes in curb to positively drain condensation to exterior of
__ ________ _
skylight at each rafter connection.
 DATE: ________ 
PROJECT 2.03 FINISHES
ENGINEER
____________
DATE ______ A. All aluminum sections shall be 3-coat fluorocarbon resinous coating
CERTIFIED aluminum in 6063 Alloy T-6 temper or approved equal by SAUDI
ARAMCO, with a protective clear UV resisting overcoat manufactured
_ __________ by PPG Industries (or equivalent) and applied by an applicator
DATE: ________
approved in writing by the coating manufacturer and under the coating
CONSTRUCTION
AGENCY
manufacturer's direction. Pre-treat aluminum to obtain primer bond.
________________
Color and sheen shall be uniform with no variations detectable by the
DATE: _________ naked eye at a 1500 mm distance.
OPERATIONS

______________ B. After fabrication of metal work, prepare surfaces for finishing in


DATE:_________
accordance with recommendations of aluminum producer, finisher or
processor.
APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER
VERIFICATION
EDSD

Finish all components of each assembly simultaneously so as to attain


complete uniformity of color. Adjust and control direction of mechanical
Date:
By:

finishes (as specified) to achieve the best overall visual effect in work,
as determined in consultation with a SAUDI ARAMCO Representative.
OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


THIS INDICATES THAT REV. NO.________

(DCC) NO.: __________________________

C. Color Tolerance: The SAUDI ARAMCO Representative reserves the


REVISION CERTIFICATION

right to reject aluminum sections because of color variations which are


visually objectionable, but only where variation exceeds range of
SECTION 07820

CONSTRUCTION SPECIFICATIONS DWG. TYPE PLANT NO. INDEX DRAWING NO. SHT. NO. REV. NO.

KING ABDULLAH PETROLEUM DOC


K55 A VE-425113 6
AND RESEARCH CENTER OF 00
RIYADH SAUDI ARABIA JOB/EWO# BI-25-00013 8
15-May-10 
Saudi Aramco 2616-ENG (3/99) 
OPERNS.

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
SAUDI ARAMCO OIL COMPANY

variations established by the manufacturer prior to work, by means of


range samples which have been accepted by SAUDI ARAMCO.
CERT

2.04 ACCEPTABLE MANUFACTURERS


ENG’G

A. 1. ALUMACO
Aluminum Manufacturing Co. Ltd.
Tel: 03-859 4555
Fax: 03-857 2081
DESCRIPTION

2. Zamil Skylight Industries


Tel: 03 857 0985
Fax: 03 857 2193

B. Or approved equal.

PART 3 - EXECUTION
DATE JOB/EWO

3.01 EXAMINATION

A. Prior to installation of the skylight system, examine the structure and


REV.
NO.

substrate to determine that they are properly prepared, sized, and ready
to receive the skylight work included herein.
DISCIPLINE
ENGINEER

__ ________ _
3.02 PREPARATION
 DATE: ________ 
PROJECT A. Contact between aluminum and dissimilar metals shall receive a
ENGINEER
protective coating of asphaltic paint for the prevention of electrolytic
____________
DATE ______ action and corrosion.
CERTIFIED
3.03 INSTALLATION
_ __________
DATE: ________
A. Install skylight frame, glass and accessory items as needed in
CONSTRUCTION
AGENCY
accordance with manufacturer’s instructions.
________________
DATE: _________ B. Install skylight system under the direction of the skylight manufacturer’s
OPERATIONS own experienced mechanics.
______________
DATE:_________
C. Erect the System in proper alignment and relation to established lines
and grades as shown on approved shop drawings.
APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER
VERIFICATION
EDSD

D. Anchor skylight to structure in strict accordance with approved Shop


Drawings.
Date:
By:

E. Use high-performance silicone sealants to seal horizontal joints


OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


THIS INDICATES THAT REV. NO.________

(DCC) NO.: __________________________

between glass panels and silicone sealant to wet seal joints between
Snap-On cap retainers and glass.
REVISION CERTIFICATION

SECTION 07820

CONSTRUCTION SPECIFICATIONS DWG. TYPE PLANT NO. INDEX DRAWING NO. SHT. NO. REV. NO.

KING ABDULLAH PETROLEUM DOC


K55 A VE-425113 7
AND RESEARCH CENTER OF 00
RIYADH SAUDI ARABIA JOB/EWO# BI-25-00013 8
15-May-10 
Saudi Aramco 2616-ENG (3/99) 
OPERNS.

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT
SAUDI ARAMCO OIL COMPANY

F. Apply sealing materials in strict accordance with sealant manufacturer’s


instructions.
CERT

G. Provide mock-up samples for Saudi Aramco approval.


ENG’G

3.06 TOLERANCES
DESCRIPTION

A. Maximum Variance from Plane: 3mm/maximum or 6mm/30m,


whichever is less.

B. Alignment of Two Adjoining Members Abutting in Plane: Within 0.4mm.

3.07 CLEANING
DATE JOB/EWO

A. Remove protective material from prefinished aluminum surfaces.

B. Wash down exposed surfaces; wipe surfaces clean.


REV.
NO.

C. Remove excess sealant.


DISCIPLINE
ENGINEER 3.08 SCHEDULES
__ ________ _
 DATE: ________ A. Refer to the Architectural drawings. 
PROJECT
ENGINEER
____________
DATE ______ END OF SECTION
CERTIFIED

_ __________
DATE: ________

CONSTRUCTION
AGENCY
________________
DATE: _________

OPERATIONS

______________
DATE:_________
APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER
VERIFICATION
EDSD

Date:
By:
OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


THIS INDICATES THAT REV. NO.________

(DCC) NO.: __________________________


REVISION CERTIFICATION

SECTION 07820

CONSTRUCTION SPECIFICATIONS DWG. TYPE PLANT NO. INDEX DRAWING NO. SHT. NO. REV. NO.

KING ABDULLAH PETROLEUM DOC


K55 A VE-425113 8
AND RESEARCH CENTER OF 00
RIYADH SAUDI ARABIA JOB/EWO# BI-25-00013 8
15-May-10 