Quantities Comparison Table

Activity ID Description Unit Rate By Rayven Amount By Firass Amount Amount Difference Quantity Difference
(y) (a) (b)=(a*y) (c) (d)=(c*y) (e)=(b-d) (f)=(a-c)
Earth Works

General excavation, material other than


top soil, rock or artificial material:

E421 Depth not exceeding 0.25m m3 12.54 2,926.03 36,692.42 1,926.56 24,159.06 12,533.35 999.47
E422 Depth 0.25 -0.50m m3 12.54 2,335.43 29,286.29 3,192.37 40,032.32 (10,746.03) (856.94)
E423 Depth 0.50 -1.0m m3 12.54 6,905.48 86,594.72 6,974.37 87,458.60 (863.88) (68.89)
E424 Depth 1 -2.0m m3 12.54 15,222.86 190,894.66 15,216.65 190,816.79 77.87 6.21
E425 Depth 2 -5m m3 13.59 68,040.86 924,675.29 67,515.28 917,532.66 7,142.63 525.58
E426 Depth 5 -10m m3 15.68 254,641.08 3,992,772.13 252,885.34 3,965,242.13 27,530.00 1,755.74
E427 Depth 10 -15m m3 16.72 165,744.48 2,771,247.71 166,027.24 2,775,975.45 (4,727.75) (282.76)
E428 Depth exceeding 15m ** up to 20m m3 45.98 28,093.52 1,291,740.05 29,914.02 1,375,446.64 (83,706.59) (1,820.50)
- - - - - -
Excavation Ancillaries - - - -
E512 Trimming of excavated srufaces m3 3.14 - - - -
Haulage of excavated material to approved
E590.1 m3 16.39 543,909.74 8,914,680.64 543,651.83 8,910,453.49 4,227.14 257.91
stockpiles 0-10km from the site boundry

Commitment Value 543,909.74 18,238,583.91 543,651.83 18,287,117.15 (48,533.24) 257.91