DEAR SIR THIS IS OUR QUOTATION FOR ABOVE PROJECT THOSE ITEMS WHICH ARE

NOT MENTIONED IN THIS QUOTATION WILL BE THE RESPONSIBILITY OF OWNER AND


OWNER IS BOUND TO PROVIDE.

PROJECT: VILLA (G+1) +C.W


PLOT NO: 82A/A
OWNER: ALI MOHAMED ALI MOHAMED ALSHEHI
CONSULTANT FUNOON AL AMARA ENGINEERING CONSULTANT
LOCATION: GIRATH
  G.F. 344 SQM
  F.F. 192 SQM
BUILT UP AREA: 536 SQM
SR.N
ITEM DETAILS AMOUNT
O    
A-1 EXCAVATIONL&BACK FILLING 12700
A-2 SAFTEY 10000
A-3 SUB-STRCUTURE R.C.C & PCC 137000
A-4 SUPPER STRUCTURE CONCRETE/STEEL WORK 215000
A-5 BLOCK WORK(SOLID,HOLLOW,HOURDY) 90600
A-6 PLASTERING(INNER+OUTER) 50200
A-7 PEST CONTROL 6000
A-8 BITUMINUAM 5000
A-9 PRIMER(INNER+OUTER) 55000
A-10 CERAMIC ONLY FIXING (FLOORING) 16000
A-11 CERAMIC BATH+ KITCHEN ONLY FIXING(WALL) 15000
A-12 STAIRCASE MARBEL ONLY FIXING 2000
A-13 SKIRTING ONLY FIXING 2500
A-14 WATER PROOFING 15000
A-15 ELECTRICAL WORK 70000
A-16 PLUMBING WORK 58000
A-17 BATH (FITTINGS ONLY) 17000
A-18 DRAINAGE SANITORY FITTINGS 15000
A-19 COMPUND WALL 65000
A-20 INTERLOCK (ONLY FIXING) 9500
A-21 CLEANING/HAND OVER 3500
TOTAL 870000