Workshop Day 3
Workshop Instructions:
1. Submission deadline: 11:59pm 15 Apr 2023. Late submissions will not be graded.
2. All documents submitted must be in MS Office or PDF format.
3. Clearly list your Breakout Room (BOR) Number followed by your registered full name.
4. The following naming convention must be used for your submission:
“T[X] MBAP Day 3”
5. This doc is for your use only, do not circulate this in any way or form.
Team Name
Group 6
Team Members
Deston Chung Eng Kea (A0166940Y)
Leong Keng Whye (A0269738H)
Mao Yu Qi (A0172700R)
Sun Jiahui (A0091667U)
Impact Probability
Risk - Short (1 to 3, 1 is (1 to 3, 1 is Risk
Risk ID Risk Description Mitigation
Name low, 3 is low, 3 is Exposure
high) high)
RSK001 Fit with CAS cannot serve its intended 3 2 6 Conduct proper discussion with the IT
existing purpose if it cannot be integrated team to ensure the chosen solution can
architecture with SEPL’s existing systems (i.e. be integrated with all existing systems,
email, ecommerce web engine, and if possible also with foreseeable
customer history system, systems that customer data would be
inventory system) analyzed with in the future.
RSK002 Short Project Based on feasibility report, 4 1 3 3 Perform prioritization of project scope to
Timeline months to complete whole deliver MVP (with most critical features)
project is risky without any buffer within 4 months, and put 5th month as
continuous improvement
RSK003 Budget The budget is set at $500k. 1 3 3 The budget needs to be planned and
However, based on the past controlled properly and monitored
You are the Project Manager of the SEPL Customer Analytics System (CAS). The official start
date of this project is 1 Feb 2022.
You had estimated that your team could deliver an average velocity of 19 story points per
iteration. Each iteration has a duration of two (2) calendar weeks.
An additional pre-launch iteration should be included to perform system “hardening” and
launch preparation.
Table 1 is the product backlog. It can be found in Appendix A. It provides the list of the user
stories and their associated story points required to launch the CAS.
(B) Determine the Launch Date of the CAS, draw your planned burn down
chart here and show all calculations & assumptions.
The management of SEPL accepted the launch date of the CAS determined earlier by you
and your team (Question B). This launch date is final and cannot be changed.
(C) Tracking the Project Progress of the CAS, provide your justifications
here.
Average Velocity: 10
Number of Extra Iterations: 9
Total Iterations: 20 (inclusive of 3 completed iteration and pre-production iteration)
Total Iterations to be reduced: 9
Duration of Each iteration: 2 elapsed weeks (Velocity of 10 story points per iteration)
Original Planned Launched date: 5 July 2022
5. Stories to be dropped
We need to drop 90 story points. We will shortlist from the stories that have not started
development in the first 3 iterations, i.e. S/N 3.2 to 6.0.
Reasons:
Iterations
Story
S/N User Story
Points
1 2 3 … … 20