TERMINAL-2 RENOVATION AND EXTENSION RPOJECT

ESTIMATED COST FOR MECHANICAL WORK

DURATION AUGUST TO DECEMBER 2022

Materials Cost Labour Cost Transporting and


S/N Particular Total Cost Remark
(Kyats) (Kyats) Handling Charges

1 Plumbing and Sanitary System


a) Sanitary Wares Installation Work (Level - 0 Plan)

b) SS-213 Soil, Waste, Vent Pipe Installation Work (Level - 0 Plan)

c) Water Supply Installation Work (Level - 0 Plan) 273,164,890.63 61,163,334.38 100,298,467.50 434,626,692.50
d) Main Sewage Pipe Line Installation Work (Level - 0 Plan)

e) Rain Water Down Take Pipe Installation Work

2 Fire Fighting System (Level - 0 Plan)


a) Fire Hydrant HDPE Pipe Line Laying Installation Work
b) Ø250mm GI Fire Pipe Line Diversion for Column and Beam
46,905,423.75 5814130.00 15815866.13 68,535,419.88
Installation Work
c) Dry Riser HDPE Pipe Line Laying Installation Work

3 Lift and Escalator System * Waiting for Quotation *


a) Reinstallation of Existing Escalator (2 Nos)

Total Amount (Kyats) 320,070,314.38 66,977,464.38 116,114,333.63 503,162,112.38