You are on page 1of 13

Document Name: Wi-Fi Restoration Proposal

Site: CEBU PORT AUTHORITY - PIER 1


Page: Page 1 of 13
Project Name: Structural Cabling Project

Smart Wi-Fi Restoration Plan


for
DA014_CEBU PORT AUTHORITY - PIER 1
Document Name: Wi-Fi Restoration Proposal
Site: CEBU PORT AUTHORITY - PIER 1
Page: Page 2 of 13
Project Name: Structural Cabling Project

Legends:
 Exposed FOC (SM) -  Exposed Power Cable -
 Consealed FOC (SM) -  Consealed Power Cable -
 Boring/Pokethrough -  Exposed Grounding Cable -
 Exposed UTP CAT6 -  Consealed Grounding Cable -
 Consealed UTP CAT6 -  A.P. -
 Consealed FOC (MM) -  Exposed FOC (MM) -

 FOC Drop Cable Laying from MDF going to OJB.


 Indoor FOC laying from MDF goinf to IDF1.
 UTP Laying for AP05.
 Propose new Molding for conduit.
Document Name: Wi-Fi Restoration Proposal
Site: CEBU PORT AUTHORITY - PIER 1
Page: Page 3 of 13
Project Name: Structural Cabling Project

AP05

 For AP05 installation at specified location


 FOC (Indoor & Drop Cable) and AP05 UTP Layout
 Will use Plastic Junction Box and Plastic Molding as Conduit for exposed portion. Will use PVC pipe for consealed.

 Propose FOC Drop Cable Laying going OJB will route going to Genset room.
 Will use Plastic Molding as conduit.
Document Name: Wi-Fi Restoration Proposal
Site: CEBU PORT AUTHORITY - PIER 1
Page: Page 4 of 13
Project Name: Structural Cabling Project

 FOC Drop Cable Route at Genset Room.


 Will use PVC 1” for
 Will use Pullbox on critical bendings.

 FOC Drop Cable Route at Genset Room.


 Will use PVC 1” for
 Will use Pullbox on critical bendings.
Document Name: Wi-Fi Restoration Proposal
Site: CEBU PORT AUTHORITY - PIER 1
Page: Page 5 of 13
Project Name: Structural Cabling Project

 FOC Drop Cable Route at Genset Room going outside.


 Will use PVC 1” for
 Will use Pullbox on critical bendings.

 FOC Drop Cable laying outside will route on the ground


 Will use PVC 1” as conduit.
 Junction/Pullbox for critical bendings.
 Propose Chipping/Trenching for the ground FOC laying
Document Name: Wi-Fi Restoration Proposal
Site: CEBU PORT AUTHORITY - PIER 1
Page: Page 6 of 13
Project Name: Structural Cabling Project

 FOC Drop Cable laying outside will route on the ground


 Will use PVC 1” as conduit.
 Junction/Pullbox for critical bendings.
 Propose Chipping/Trenching/Embedding for the ground FOC laying
Document Name: Wi-Fi Restoration Proposal
Site: CEBU PORT AUTHORITY - PIER 1
Page: Page 7 of 13
Project Name: Structural Cabling Project

 FOC Drop Cable laying outside will route on the ground


 Will use PVC 1” as conduit.
 Junction/Pullbox for critical bendings.
 Propose Chipping/Trenching for the ground FOC laying
Document Name: Wi-Fi Restoration Proposal
Site: CEBU PORT AUTHORITY - PIER 1
Page: Page 8 of 13
Project Name: Structural Cabling Project

 FOC Drop Cable Route outside will route on the ground


 Will use PVC 1” as conduit.
 Junction/Pullbox for critical bendings.
 Propose Chipping/Trenching/Embedding for the ground FOC laying
Document Name: Wi-Fi Restoration Proposal
Site: CEBU PORT AUTHORITY - PIER 1
Page: Page 9 of 13
Project Name: Structural Cabling Project

AP03

 Indoor FOC laying from MDF going to IDF1


 Will use PVC pipe for the consealed portion
 Propose new AP03 location.
 Will use plastic molding for the exposed portion.

AP02

 Indoor FOC laying from MDF going to IDF1


 Will use PVC pipe for the consealed portion
 Will use Junction/Pull Box on critical bendings
 Propose new AP02 location.
Document Name: Wi-Fi Restoration Proposal
Site: CEBU PORT AUTHORITY - PIER 1
Page: Page 10 of 13
Project Name: Structural Cabling Project

 Indoor FOC laying from MDF going to IDF1


 Will use PVC pipe for the consealed portion
 For mounting of IDF1 at the indicated location.
 Will use plastic molding for the exposed portion.

 Indoor FOC laying from MDF going to IDF1


 For mounting of IDF1 at the indicated location.
 Will use plastic molding for the exposed portion.
 Power Tapping at C.O.
Document Name: Wi-Fi Restoration Proposal
Site: CEBU PORT AUTHORITY - PIER 1
Page: Page 11 of 13
Project Name: Structural Cabling Project

AP01

 Indoor FOC laying from MDF going to IDF1


 Will use PVC pipe for the consealed portion
 For mounting of IDF1 at the indicated location.
 Will use plastic molding for the exposed portion.
 Power Tapping at C.O.
 Propose new AP01 location
 Propose new Grounding route going to Electrical Panel

AP01
1

 Propose new AP01 location


 Will use plastic molding for the exposed portion.
 Propose new Grounding route at Electrical Panel
Document Name: Wi-Fi Restoration Proposal
Site: CEBU PORT AUTHORITY - PIER 1
Page: Page 12 of 13
Project Name: Structural Cabling Project

 Propose Grounding tapping point at vacant slot.


 Will use plastic molding for the exposed portion.
 Propose new Grounding route at Electrical Panel
Document Name: Wi-Fi Restoration Proposal
Site: CEBU PORT AUTHORITY - PIER 1
Page: Page 13 of 13
Project Name: Structural Cabling Project

You might also like