Professional Documents
Culture Documents
Ref HM/MY06PH3/HSE/FRM/015
HUASHI (MALAYSIA) SDN BHD Rev. No. 0
Issued Date 28 November 2022
EXCAVATION CHECKLIST
Page No. Page 1 of 1
MY06PH3 PROJECT BUTTERFLY
DESIGN AND BUILD CSA MAIN CONTRACT FOR THE DETAILED DESIGN, AUTHORITY SUBMISSIONS,SUPPLY, DELIVERY, INSTALLATION,
TESTING AND COMMISSIONING, OBTAIN CERTIFICATE OF COMPLETION & COMPLIANCE, SUPPORT DURING DEFECTS LIABILITY PERIOD AND
MAINTENANCE OF PROJECT BUTTERFLY 03 - A NEW 40MW IT, GREENFIELD CENTRE (PHASE 3) FOR BRIDGE DATA CENTRE MALAYSIA III
SDN BHD ON HS (D) 78142 PTD 32674
B UNDERGROUND SERVICES
C WET CONDITION
Precautions are taken to protect personnel from water accumulation through
1 continuous dewatering
Surface water or runoff is diverted / controlled to prevent accumulation in the
2 excavation.
Comments:
________________________________________________________________________________________
________________________________________________________________________________________
________________________________________________________________________________________
I have inspected the excavation and confirm it is safe for entry and is in accordance with the excavation requirements.