You are on page 1of 2

Date :March 25, 2023

Attention :
Thru :
Project : Proposed Sewage Treatment Plant of Piggery Farm 1000 Heads
Location : Batangas, Philippines
Owner :
Subject : Proposed Design and Build of Sewage Treatment Plant 50CmD

A. SCOPE OF WORKS
UNIT RATE
ITEM NO. ITEM DESCRIPTION UNIT QTY TOTAL AMOUNT
MATERIAL LABOR OTHERS TOTAL
I PRELIMINARIES
Mobilization/Demobilization 1.00 ITEM 80,000.00
Temporary Facilities 1.00 ITEM 70,000.00
Testing and Commissioning 1.00 ITEM 180,000.00
Design, As built plan Project Mngmnt. and Supervision 1.00 ITEM 250,000.00
sub-total I 580,000.00
II Electro-Mechanical Works
Bar Screen ,angle bar 1x1x6 mtr length ss 304 1.00 LOT 65,600.00 19,680.00 3,936.00 89,216.00 89,216.00
2 stage barscreen ss 304, round bar 10mm ss 304

Air Blower
Positive displacement Rotary Tri loob Blower 2.00 LOT 150,000.00 45,000.00 9,000.00 204,000.00 408,000.00
Capacity: 60 cubic meter per hour
Discharge pressure: 280 millibars
1.5 kw, 220/440V, 60Hz, 3phase

Disc Type Air Diffuser 50.00 UNIT 2,000.00 600.00 120.00 2,720.00 136,000.00

EPDM Material
Digested sludge pump 2.00 UNIT 28,000.00 8,400.00 1,680.00 38,080.00 76,160.00
Screw or vortex impeller
Capacity: 3 liter per second
TDH: 10 meters
.75 kilowatt, 220/440V, 60Hz, 3phase
Water Ozonator Generator 2.00 UNIT 350,000.00 35,000.00 7,000.00 392,000.00 784,000.00
Capacity: 50 grams per liter
with pure oxygen concentrator
TDH: 10 meters
1.4 kilowatt, 220/440V, 60Hz, 3phase
Effluent submersible pump 2.00 UNIT 28,000.00 8,400.00 1,680.00 38,080.00 76,160.00
Screw or vortex impeller
Capacity: 15 liter per second
TDH: 20 meters
.75 kilowatt, 220/440V, 60Hz, 3phase
Electrical Works 1.00 LOT 480,000.00 144,000.00 28,800.00 652,800.00 652,800.00
Motor Control Center
Electrical rough-ins
Hangers and supports
sub-total II 2,222,336.00
III Mechanical Works 1.00 LOT 761,402.00 228,420.60 45,684.12 1,035,506.72 1,035,506.72
2’’x 3/8 stainless expantion bolt
3" (75mm) Diameter x 6 mtr Length Sch .40 G.I pipe
3" (75mm) Diameter x 3 meter Length PVC Pipe
2" (50mm) Diameter x 3 meter Length PVC pipe
3/4" Diameter x 3 meter Length PVC pipe
3" (75mm) Diameter x 90 Degrees ELBOW - PVC
3" x 3" (75mm) Diameter TEE – PVC
3" x 3" (75mm) Diameter TEE - G.I
3" x 2" (75mm x 50mm) Reducer bushing G.I.
2" X 90 degree (50mm) Diameter Elbow - PVC
2" (50mm) Diameter x6 mtr length sch.40 - G.I. pipe

2" (50mm) Diameter x6 mtr length sch.40 - G.I. pipe


3" (75mm) Diameter CHECK VALVE
3" (75mm) Diameter x 8’’ Length short nipple
3"x2’’(75mm x 50mm)Diameter PVCTee reducer
2’’x ¾’’(50mm x 32mm Diameter PVC Tee reducer
3’’(75mm Diameter G.I union patente
2" (50mm) Diameter BALL VALVE
2’’(50mm) ) Diameter Male adapter
2’’(50mm) ) Diameter Union patente
3" 7(5mm) Diameter x 4’’ Length short nipple
1/2" Diameter Stainless Chain
2’’x2’’(50mm x 50mm) diameter x 6 mtr length angle
bar

Proposed Sewage Treatment Plant of Piggery Farm 50CmD ( Design and Build ) Page 1 of 2 Piggery Farm (Design & Build) 3/25/2023
Date :March 25, 2023
Attention :
Thru :
Project : Proposed Sewage Treatment Plant of Piggery Farm 1000 Heads
Location : Batangas, Philippines
Owner :
Subject : Proposed Design and Build of Sewage Treatment Plant 50CmD

A. SCOPE OF WORKS
UNIT RATE
ITEM NO. ITEM DESCRIPTION UNIT QTY TOTAL AMOUNT
MATERIAL LABOR OTHERS TOTAL

5" (125mm) Diameter x 6 mtr Length Sch .40 G.I pipe

6" (150mm) Diameter x 90 Degrees Sanitary pvc elbow


6" x 6" (160mm) Diameter Sanitary PVC TEE
6" (150mm) Diameter x 3 meter Length Sanitary pvc
Pipe
sub-total III 1,035,506.72
IV Civi Works (STP Tank 4.00 x 6.00 x 4.00m)

Supply and Installation 1.00 LOT 1,350,502.00 405,150.60 60,772.59 1,816,425.19 1,816,425.19
Earthworks
• Excavation
• Backfill
• Layout/Site Clearing
Masonry works
• Rebar works
• ChB laying
• Plastering
• Concrete pouring
• Formworks
• Waterproofing

sub-total II 1,816,425.19
SUB-TOTAL PROJECT COST 5,654,267.91

GENERAL REQUIREMENTS / PRELIMENARIES (I) 580,000.00


INDIRECT COST (II-IV) 5,074,267.91
TOTAL PROJECT COST 5,654,267.91

B. TOTAL AMOUNT OF THIS OFFER: PHP 5,654,267.91


C. AMOUNT IN WORDS: Five million, six hundred fifty-four thousand, two hundred sixty-seven pesos and 91/100 only.
D. TERMS OF PAYMENT: 40% DOWN-PAYMENT , BALANCE SHALL BE PAID IN PROGRESS BILLING BASED ON ACCOMPLISHMENT.
E. WORK COMPLETION: Ninety (90) - One hundred twenty (120) calendar days.
F. VALIDITY OF QUOTATION: THIRTY (30) CALENDAR DAYS FROM THE DATE OF THIS QUOTATION
G. WARRANTY: One (1) year on mechanical equipment and workmanship against factory defects.
NOTE: If the equipment / device are mishandled, mis-used or causes human error. Unbalanced or improper power supply
the warranty will be void, Client will shoulder freight cost upon warranty claims.
G. VAT: Value Added Tax are not included in this quotation.
Note:
1 Client should provide area / facility for materials and equipment storage area.
2 Electricity and water consumption shoulder by the client.
3 The Contractor will provide Municipal Health Certificate only (if needed), For antigen/Swab test
the client will shoulder the payment.
4 Permits / Entry pass fees shoulder by the client (if needed)
5 The client will shoulder the payment of the processing / filing fee of ther discharge permit application.
6 Requesting of Official Receipt, the client shoulder the additional 12% of total project cost.

Prepared by : Conformed:

John Axl Lajom


STP Contractor/Designer

Proposed Sewage Treatment Plant of Piggery Farm 50CmD ( Design and Build ) Page 2 of 2 Piggery Farm (Design & Build) 3/25/2023