Proposed Sewage Treatment Plant of Piggery Farm 50CmD (Design and Build)
Proposed Sewage Treatment Plant of Piggery Farm 50CmD (Design and Build)
Attention :
Thru :
Project : Proposed Sewage Treatment Plant of Piggery Farm 1000 Heads
Location : Batangas, Philippines
Owner :
Subject : Proposed Design and Build of Sewage Treatment Plant 50CmD
A. SCOPE OF WORKS
UNIT RATE
ITEM NO. ITEM DESCRIPTION UNIT QTY TOTAL AMOUNT
MATERIAL LABOR OTHERS TOTAL
I PRELIMINARIES
Mobilization/Demobilization 1.00 ITEM 80,000.00
Temporary Facilities 1.00 ITEM 70,000.00
Testing and Commissioning 1.00 ITEM 180,000.00
Design, As built plan Project Mngmnt. and Supervision 1.00 ITEM 250,000.00
sub-total I 580,000.00
II Electro-Mechanical Works
Bar Screen ,angle bar 1x1x6 mtr length ss 304 1.00 LOT 65,600.00 19,680.00 3,936.00 89,216.00 89,216.00
2 stage barscreen ss 304, round bar 10mm ss 304
Air Blower
Positive displacement Rotary Tri loob Blower 2.00 LOT 150,000.00 45,000.00 9,000.00 204,000.00 408,000.00
Capacity: 60 cubic meter per hour
Discharge pressure: 280 millibars
1.5 kw, 220/440V, 60Hz, 3phase
Disc Type Air Diffuser 50.00 UNIT 2,000.00 600.00 120.00 2,720.00 136,000.00
EPDM Material
Digested sludge pump 2.00 UNIT 28,000.00 8,400.00 1,680.00 38,080.00 76,160.00
Screw or vortex impeller
Capacity: 3 liter per second
TDH: 10 meters
.75 kilowatt, 220/440V, 60Hz, 3phase
Water Ozonator Generator 2.00 UNIT 350,000.00 35,000.00 7,000.00 392,000.00 784,000.00
Capacity: 50 grams per liter
with pure oxygen concentrator
TDH: 10 meters
1.4 kilowatt, 220/440V, 60Hz, 3phase
Effluent submersible pump 2.00 UNIT 28,000.00 8,400.00 1,680.00 38,080.00 76,160.00
Screw or vortex impeller
Capacity: 15 liter per second
TDH: 20 meters
.75 kilowatt, 220/440V, 60Hz, 3phase
Electrical Works 1.00 LOT 480,000.00 144,000.00 28,800.00 652,800.00 652,800.00
Motor Control Center
Electrical rough-ins
Hangers and supports
sub-total II 2,222,336.00
III Mechanical Works 1.00 LOT 761,402.00 228,420.60 45,684.12 1,035,506.72 1,035,506.72
2’’x 3/8 stainless expantion bolt
3" (75mm) Diameter x 6 mtr Length Sch .40 G.I pipe
3" (75mm) Diameter x 3 meter Length PVC Pipe
2" (50mm) Diameter x 3 meter Length PVC pipe
3/4" Diameter x 3 meter Length PVC pipe
3" (75mm) Diameter x 90 Degrees ELBOW - PVC
3" x 3" (75mm) Diameter TEE – PVC
3" x 3" (75mm) Diameter TEE - G.I
3" x 2" (75mm x 50mm) Reducer bushing G.I.
2" X 90 degree (50mm) Diameter Elbow - PVC
2" (50mm) Diameter x6 mtr length sch.40 - G.I. pipe
Proposed Sewage Treatment Plant of Piggery Farm 50CmD ( Design and Build ) Page 1 of 2 Piggery Farm (Design & Build) 3/25/2023
Date :March 25, 2023
Attention :
Thru :
Project : Proposed Sewage Treatment Plant of Piggery Farm 1000 Heads
Location : Batangas, Philippines
Owner :
Subject : Proposed Design and Build of Sewage Treatment Plant 50CmD
A. SCOPE OF WORKS
UNIT RATE
ITEM NO. ITEM DESCRIPTION UNIT QTY TOTAL AMOUNT
MATERIAL LABOR OTHERS TOTAL
Supply and Installation 1.00 LOT 1,350,502.00 405,150.60 60,772.59 1,816,425.19 1,816,425.19
Earthworks
• Excavation
• Backfill
• Layout/Site Clearing
Masonry works
• Rebar works
• ChB laying
• Plastering
• Concrete pouring
• Formworks
• Waterproofing
sub-total II 1,816,425.19
SUB-TOTAL PROJECT COST 5,654,267.91
Prepared by : Conformed:
Proposed Sewage Treatment Plant of Piggery Farm 50CmD ( Design and Build ) Page 2 of 2 Piggery Farm (Design & Build) 3/25/2023