Start Date: January 1, 2022

End Date: March 16,2022


75 Calendar Days
TIMESCALE DAYS
Activity ID Activity Name January February March
5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25
WBS1: SUBSTRUCTURE
A Excavation
B Base Course
C Footing Fabrication
D Footing Installation
E Footing Concreting
F Column Fabrication
G Column Installation
H Column Concreting
I Backfill and Compaction
WBS 2: SUPERSTRUCTURE
J Plinth Beam Fabrication
K Plinth Beam Installation
L Plinth Beam Concreting
M Soil Filling and Compaction
N Floor Slab Fabrication
O Floor Slab Installation
P Floor Slab Concreting
Q Wall Rebar Fabrication
R Wall Rebar Installation
S CHB Laying
T Wall Plastering
U Roofing Installation
V Painting
W End Activity
March
30