‫شــــــــــركة القــــــــبـة الهندســــــــــــــية‬

Al-Qubba Engineering Co.

LIFTING PLAN METHOD & RISK ASSESSMENT


Project SIB-UC-SF-0046 Date 22-Jan-2023
Site/location SIBA-Iraq-CPF Client Kuwait energy (KEIL)

Document Ref. SGFCPF-QULLC-01 Rev 0 Issued by Al-Qubba engineering Co.


Appointed Person carrying out
Hazim Alsudani Date of Assessment: 22-Jan-2023
the Assessment:
Contact: Hazim Mohammed Kanosh Phone: 07833301221 Fax: 619212
Site contact: Mustafa Kamal Phone: 07711910236 Fax: 619212

Description of lift: Loading Concrete foundation inside CPF


NB 50% reduction in load capability if man basket is used.

Details of Loads Load Position 1 Load Position 2 Load Position 3


Weight: 600 Kg
Dimensions: 2.5Mx0.5Mx0.2m
directly over the
Position of C of G:
centre of the load
Height of lift (worst case only): 1.5m
Max. radius (worst case only): 6m
Date of lift: 23/01/2023
Time of lift: 10:00 AM
Monetary value of load: 250$

Details of Cranes 1st 2nd 3rd


Make & model: HANGIL 2009
Capacity: 8ton
Jib length: 7.7m
Outrigger spread: 1.5m
Outrigger load: 9ton
Max. ground bearing capacity: 100-200 KN/M²
Counterweight: N/A
Weight of crane: 10 Ton

Ground Conditions (Visual assessment)


Access/Egress for crane & Clear
transport:
Lifting position: COG position checked

Lifting Accessories
Slings (wire rope): 11mm dia. WSC non spin Slings (webbing): N/A
Slings (chains): 8 T, KOREA, S#871632 Shackles: N/A
Other Accessories: N/A
‫شــــــــــركة القــــــــبـة الهندســــــــــــــية‬
Al-Qubba Engineering Co.

Identification of Hazards

Proximity Hazard Present? Proximity Hazard (cont.) Present?


Overhead power lines No Other hazards identified No
Other overhead obstacles No
Underground services No
Excavations No Load Hazard Present?
Unstable/ Soft ground No Slinging difficulties No
Hazardous chemicals/materials No Top heavy No
Confined working area No Sharp edges No
Restricted access - width No Other hazards identified No
Restricted access - height No
Other vehicles No

Assessment of Risk
Hazard Present Risk Action to Avoid or Reduce Risk
 Defective/inappropriate  Personal injury  All involved in lifting operation shall
Lifting Appliances and  Lifting failure complete KEIL lifting awareness training
lifting gears  Fall of object and  Follow KEIL PTW
 Inadequate training for asset damage  Use competent and approved operators
operators  Environmental impact  Use trained banks man
 Uneven ground surface  Unsafe work  Barricade the lifting area
 Inadequate area for methods  Ensure proper lifting plan/procedure is
operation  Tilting/toppling of available for the planned lift and follow
 Overload equipment strictly.
 Heavy wind and bad  Electrocution  Ensure that all relevant, valid test
weather conditions certificates are available with
 Presence of power line in equipment/operator
the area of operation  Assess the weight of the load to be lifted
 Check the center of gravity and ensure
load is balanced
 Ensure that there is a clear path from the
lifting are to the landing area
 Landing site shall be strong enough to
withstand the load
 Ensure that any nearby existing facility/
plant/equipment is not be affected by lifting
operation
 Use tag line to control load

Operational Requirements:

Site Provisions: Sajjad Wesam Kadhim

Notes
*lay down / landing area(s) adequate in both size and load bearing capacity
*the outriggers evenly /adequately extended
*the lighting condition adequate to perform the operations safely
*The barriers positioned to prevent access to unauthorised personnel
*the weather conditions within limits to avoid their effects on the safety of the lifting operation
IF ALL CONTROLS ARE NOT IN PLACE, THE OPERATION SHALL NOT START!
‫شــــــــــركة القــــــــبـة الهندســــــــــــــية‬
Al-Qubba Engineering Co.

Method Statement

Responsibilities
Company Name will undertake the responsibilities for the management of this lifting operation as defined in
the British Standard 7121 for the lifting and movement of goods involving crane operation.

Personnel
Company Name will provide the following personnel complete with relevant personal protective equipment.
The duties of these people will be as defined in British Standard 7121

Title Name Title Name


Appointed Fawaz Ahmed Ketab Slinger(s) Ali Husain
Person
Crane Ali Jasim Mohammed Signaller(s) Haider Jamil
Supervisor
Crane Driver(s) Ali Jasim Mohammed Crane Erectors Ali Jasim Mohammed

Note: The appointed person may decide that one person can carry out more than one duty. This does
not however, include the crane driver who must concentrate on operating the crane.

Lifting Accessories
The lifting accessories, as detailed previously, will be provided by Al-Qubba engineering, complete with all
statutory documentation.

Weather Conditions
The Appointed Person or, in his absence, the Crane Supervisor, will ensure that the lifting operation only
takes place if the weather conditions are within the limits recommended by the crane manufacturer. 3-day
weather forecast.

Ground Conditions`

Have assurances been obtained that the ground can withstand the load? Yes
‫شــــــــــركة القــــــــبـة الهندســــــــــــــية‬
Al-Qubba Engineering Co.

ASSESSMENT OF THE LIFTING OPERATION

Has the lifting operation being performed before? Yes No


1

2 Are you experience with this type of load and lifting equipment to be used? 

3 Has the load being checked and made ready for lifting (e.g. seafasting or lashing removed)? 

4 Is the weight and the CoG clearly known/identified and taken from a reliable source? 

5
Is the operation clear from risk of SIMOPS or inteference with other activities? 

6
Is the load involving only one lifting appliance? 

7 Does the lifting operation require basic slinging practices (including certified lifting points)? 

8 Is the crane operator visibility and communication with banksman ensured at all times? 

9 Is the equipment to be used certified, appropriate for intended use and correctly colour-coded? 

10

Is the lifting operation taking place over non-sensitive areas and easy to reach?

11 Is the route clear from any overhead powerlines?



Is the operation to be performed under favourable weather conditions (e.g.wind, wave,
12 current)?

Appointed Person’s Acceptance of Responsibilities


I confirm that the lifts have been planned and will be carried out in
accordance with current legislation and British Standard 7121 and
that I accept responsibility for the preparation of this Risk Assessment Signed: Date:22/01/2023
and Method Statement.

Crane Supervisor’s Acceptance of Duties


I confirm that I have been fully briefed on the contents of this Risk
Assessment and Method Statement and that I accept the duty of
ensuring that the lift(s) will be carried out in accordance with the Signed: Date:
method and procedures set out in this document.
‫شــــــــــركة القــــــــبـة الهندســــــــــــــية‬
Al-Qubba Engineering Co.

`Sketch of the general arrangement / rigging: crane position / lifted item / obstacles and any additional details as required

Load chart to be used