GANTT CHART

PROJECT TITLE Online Aseet tracking and Service Planing COMPANY NAME Integrity (Pvt) Ltd

PROJECT MANAGER MBA 2020 A2 DATE 2/26/21

DURATION PCT OF TASK


ACTIVITY ACTIVITY TITLE Dependencies START DATE DUE DATE Feb 2021 Mar 2021 Apr 2021 May 2021 Jun 2021 Jul 2021 Aug 2021 Sep 2021 Oct 2021 Nov 2021 Dec 2021 Jan 2022 Feb 2022 Mar 2022 Apr 2022
(Weeks) COMPLETE
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10W11W12W13W14W15W16W17W18W19W20W21W22W23W24W25W26W27W28W29W30W31W32W33W34W35W36W37W38W39W40W41W42W43W44W45W46W47W48W49W50W51W52W53W54W55W56W52W53W54W55W56W52W53W54W55W56W52W53W54W55W56

Project Solution
A Specify a solution - 2/26/21 4/22/21 8.00 0%
B Hire staff - 2/26/21 3/24/21 4.00 0%
C Order tabs for riders - 2/26/21 4/29/21 9.00 0%
D Demo solutions A 4/23/21 5/14/21 3.00 0%
E Procure new systems D 5/15/21 7/25/21 10.00 0%
F Buy new PCs for staff B 3/25/21 4/23/21 4.00 0%
G Install the new system E, F, R 7/9/21 11/15/21 18.00 0%
H Train the staff to use the new system G 11/16/21 1/26/22 10.00 0%
I Train riders C 4/30/21 6/19/21 7.00 0%
J Enter all the data in to the new system H 1/27/22 3/23/22 8.00 0%
K UAT (User Acceptance Test) J, Q 3/21/22 4/12/22 3.00 0%
L Allocate zones to staff B 3/25/21 4/9/21 2.00 0%
M Prepare Manual & check L, I 6/20/21 7/18/21 4.00 0%
N Configure tabs M 7/19/21 8/10/21 3.00 0%
O System Integration K, N 4/29/21 5/27/21 4.00 0%
P Visit client sites and label assets and register them O 5/28/21 7/24/21 8.00 0%
Q Give copies for UAT M 7/19/21 7/26/21 1.00 0%
R Configure C 4/29/21 5/27/21 4.00 0%