You are on page 1of 22

NUMBER P05-G01

REV. NO. 0
ENGINEERING STANDARD DATE SEP 2017
PAGE 1 OF 22

Requirement of 3D Model and Review

This document is issued by ECoE, SABIC E&PM, Jubail Industrial City, Kingdom of Saudi Arabia. The information contained in this
document is the confidential property of SABIC. It cannot be disclosed, copied or used for any purpose without approval from SABIC.
If you are not authorized to posses this document, please destroy it immediately.
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 2 OF 22

CONTENTS

1 Scope .................................................................................................................................................3
2 References .........................................................................................................................................3
3 Definitions ..........................................................................................................................................3
4 General ..............................................................................................................................................3
5 3D Model Implementation ..................................................................................................................4
5.1 General ..............................................................................................................................................4
5.2 Model Execution.................................................................................................................................4
5.3 Disciplines Breakdown of Model Contents ........................................................................................5
5.4 Deliverables .....................................................................................................................................10
6 Design Review .................................................................................................................................11
6.1 General ............................................................................................................................................11
6.2 Design Review Schedule .................................................................................................................11
6.3 30% 3D Model Review Workshop ...................................................................................................11
6.4 60% 3D Model Review Workshop ...................................................................................................11
6.5 90% 3D Model Review Workshop ...................................................................................................12
7 Execution of Design Review ............................................................................................................12
7.1 General ............................................................................................................................................12
7.2 Matrix of 3D Model Items .................................................................................................................12
7.3 Color Code .......................................................................................................................................12
7.4 Model Review Comment Tagging System .......................................................................................12
7.5 3D Model Comment Log ..................................................................................................................13
8 Review Team ...................................................................................................................................13
9 Revision Summary ...........................................................................................................................13

TABLES
Table-1 Tagging System …………………………………………………..………………………………...…13
Table-2 3D Model Review Team ……………………………………………………….……..……….…...…13

ATTACHMENTS
Attachment-1 Areas covered by modelling activities……………………………………………………...…14
Attachment-2 Matrix of 3D Model Items …………………………………………………………………...…15
Attachment-3 Color Code for Design Review …………………….………………………..……………...…19
Attachment-4 Comment Log Sheet…………………………………………………….…………………...…22
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 3 OF 22

1 Scope
1.1 This standard covers the minimum requirements for 3D model and provides an overview of the
activities involved in the 3D modelling of the plant for the PROJECT.
1.2 This standard is applicable for both new projects and De-bottlenecking (DBN) projects.
1.3 This standard provides the split of activities of the different involved disciplines and assigns
responsibilities.
1.4 This standard presents means and references for executing, checking and controlling the design
with special focus on the 3D model reviews.
1.5 This standard does not cover the requirements of software and related information for 3D modeling.
1.6 This standard covers the requirements for industrial projects and not applicable for housing
projects.

2 References
The following referenced documents are requisite for the application of this standard. The latest issues,
amendments, and supplements to these documents shall apply unless otherwise indicated.

SABIC Engineering Standards (SES)


D02-D02 Engineering Tools and Data Structure

Safety, security, health & environment management (SHEM)


SHEM-02.01 Process Safety Risk Assessment

3 Definitions
For the purpose of understanding this standard, the following definitions apply.

Design Engineering Company: Engineering Company responsible for Engineering, Procurement and
Construction of piping systems.
EPC: Engineering Procurement and construction
FEED: Front End Engineering Design/Basic Engineering Design
PMT: Project Management Team
SES: SABIC Engineering Standard
SP3D: Smart Plant 3D
Vendor: Manufacturer of Equipment
Package Vendor: Manufacturer and supplier of package type of equipment

4 General
4.1 3D model shall be developed based on the requirements specified in SES D02-D02 and this
standard.
4.2 Interference and clash check shall be performed for the complete scope, which shall include the
followings.
4.2.1 All new facilities.
4.2.2 All modified facilities (including tie-ins)
4.3 Whenever new facilities are planned as part of existing plant/facility, such new facilities shall be
modeled by covering and modeling existing facilities to such an extent so that a 3D model review
can be performed to determine that access, maintenance and operability requirements for the
scope are complied.
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 4 OF 22

4.4 3D model shall include all the interconnection piping for process, utility and off-sites from the
existing tie-ins as may be required for the new Plant.
4.5 In accordance with the requirements of SHEM 02.01, the model shall take into account of the
following aspects.
4.5.1 Interference between services are avoided
4.5.2 Safety, operational and maintenance criteria are met
4.5.3 Equipment requiring regular attention are accessible
4.5.4 Adequate escape routes and access for safety services
4.5.5 Ergonomics

5 3D Model Implementation
5.1 General

5.1.1 The scope and limits of 3D modeling shall be established and marked in the plot plan. An
example for scope and limits of 3D modeling is shown in Attachment-1 “Limits of 3D
Modelling”.
5.1.2 The objects to be modelled and the specific review steps are listed in Attachment-2 “Design
Activities inside 3D Model”.
5.1.3 Plant Break Down Structure shall be developed for each project based on the requirement
specified in SES D02-D02.
5.1.4 Modification in the existing facilities shall be updated in the existing 3D model, if 3D model
of existing plant is available.

5.2 Model Execution

3D modelling activities are split into three (3) stages. Stage 1, 2 & 3 correspond to 30%, 60% &
90% progress respectively as a milestone after completion of each stage. The modeling activities
carried out at each stage pertaining to various discipline are listed below, together with the
associated deliverables.

5.2.1 Stage 1 (30% Progress)


a. Activities
All the items required to be modeled during 30% shall be in accordance with items listed
in Attachment-2.
b. Deliverables
The deliverables after completion of 30% 3D model (including incorporation of 3D model
review comments) shall include, but not limited to, as given below.
i. Equipment Layouts issued for design
ii. Foundation Plans issued for design
iii. Piping Tie-in list
iv. Material Take-Off (MTO)
v. Issue isometrics for major lines for stress analysis.

5.2.2 Stage 2 (60% Progress)


a. Activities
All the items required to be modeled during 60% shall be in accordance with items listed
in Attachment-2.
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 5 OF 22

b. Deliverables
The deliverables after completion of 60% 3D model (including incorporation of 3D model
review comments) shall include, but not limited to, as given below.
i. Main steel and pipe rack drawings
ii. Preliminary underground piping layout
iii. Isometrics of underground piping lines issued for construction
iv. Material Take-Off (MTO) issued for construction bidding
v. Preliminary arrangement for electrical/instrument cable trays
vi. Equipment drawings with nozzle orientation
vii. Issue isometrics for major lines for stress analysis.

5.2.3 Stage 3 (90% Progress)


a. Activities
All the items required to be modeled during 90% shall be in accordance with items listed
in Attachment-2.
b. Deliverables
The deliverables after completion of 90% 3D model (including incorporation of 3D model
review comments) shall include, but not limited to, as given below.
i. Issue of remaining piping isometrics
ii. Isometrics of main process lines issued for construction
iii. Isometrics of underground piping lines issued for construction
iv. Continuous Material Take Off (MTO) update from model
v. General Arrangement of electrical/instrument cable trays

5.3 Disciplines Breakdown of Model Contents


The contents of final 3D model for each discipline shall be, but not limited to, as stipulated below.

5.3.1 Equipment Modeling


The modelling of equipment should be carried out based on P&ID, preliminary plot plan,
equipment data sheets and Vendor drawings. The following details will typically be modelled
as a minimum.

a. Detail equipment model, including nozzle orientation, nozzles sizes, lifting lugs, davits
and space reservations (Operation and Maintenance volumes/envelopes)
b. Detail equipment auxiliary model, including service platforms, ladders (including cage if
applicable) and stairs
c. Man ways, hand holes, skirts and supports
d. Rotating equipment with all nozzles including vents and drains at all interfaces, driver,
coupling, acoustic enclosure
e. Appurtenances of Vessels – major (e.g. levels)
f. Equipment insulation
g. Pipe supports and guides on equipment (Physical type)
h. Exchangers/heaters Tube bundle removal with tube withdrawal volumes/envelopes.
i. Equipment pull-outs and drop area with volumes/envelopes
j. Permanent cranes and hoist beams
k. Outline of Auxiliary Unit (e.g. Lube/Seal Oil Skids)
l. Enclosure
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 6 OF 22

m. The minimum attribute requirements for equipment are equipment number, insulation
thickness and a description. The minimum required nozzle attributes are tag number,
size, pressure rating, end preparation and pipe material class

The following items should be excluded in the model.

a. HVAC equipment
b. Portable equipment
c. Lab equipment

5.3.2 Packages Modeling

The model of package equipment shall be integrated with overall 3D model following the
same rules of overall 3D modelling. Modelling of package equipment as an outline (box
shape) is not acceptable. Packaged equipment, irrespective of whether it is designed by
Design Engineering Company or its sub-contractors shall be modeled on a basis that is
consistent with the requirements herein and to the same accuracy and content as Design
Engineering Company’s own design. Package equipment shall be modeled in sufficient
detail to facilitate the review of access to all components and instrumentation for operation,
maintenance, ergonomic design, piping, instrument and electrical connections. Deviation
from these requirements by Design Engineering Company or its sub-contractors shall require
SABIC’s prior approval. The following details will typically be modelled as a minimum

a. All piping termination points & local control panels


b. All piping hook-ups between vendor supplied skids (where applicable)
c. Outline of Auxiliary Unit (e.g. Lube/Seal Oil Skids)
d. All packages having scattered equipment shall be modelled with complete piping to
ensure clash free, layout & easy operation/ maintenance access.Packages Modeling

5.3.3 Piping Modeling

Detailed design of pipe routings should be carried out based on P&ID’s and piping classes.
Every modelled line is completed with all the relevant information, such as line identifier,
fluid, piping class, size (NPS), insulation thickness and other details. The following details
will typically be modelled as a minimum

a. All process and utility piping, vents & drains, including all piping components for sizes
NPS ½ and above as shown on the P&ID
b. Complete underground piping, Manholes and thrust blocks (if applicable)
c. Valves including hand wheels, actuators, and motor operators correct in orientation and
actual dimensions
d. Piping specialities like strainers, steam traps, expansion joints and other special piping
items
e. Jacketed piping
f. Piping insulation, maintenance and access volume/envelopes
g. Pipe supports (Physical type as per Design Engineering Company’s 3D library or Logical
type) with tag number
h. In-line instruments
i. Safety showers/eyewash stations
j. Utility stations
k. Hose racks
l. Steam and condensate manifolds
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 7 OF 22

m. Instrument manifolds
n. Roof vents (if applicable)
o. Hazardous vents
p. Low point drains & high point vents
q. Equipment working clearance
r. Sampling Points, including sample cabinets & sample coolers
s. Tie-in connection
t. Vessel trim – valving, blinds, instrumentation, etc.
u. Spectacle blinds spades and spacers – removal capability
v. Piping shall carry all attributes in the piping line list and additional attributes associated
with construction, inspection and testing requirement.

The following items should be excluded in the model.

a. Steam Tracing
b. Plumbing
c. Tubes in package

5.3.4 Civil, Structural & Architectural Modeling

The following details will typically be modelled as a minimum.

a) Structural Main Steel Model:


i. Pipe Racks
ii. Technological Structures to house equipment
iii. Shelters and pre-engineered metal buildings
iv. General equipment structure
v. Main columns, beams, girders, vertical & horizontal bracing dimensionally
accurate
vi. Monorails
vii. Miscellaneous structural supports

b) Structural Secondary Steel Model:


i. Purlins & Girths
ii. Stairs
iii. Cladding, fireproofing, floor plating/grating (including penetrations and supporting
steel)
iv. Floor plates (gratings and checkered plates)
v. Handrails on platforms and stairways
vi. Ladders (including cage if applicable)
vii. Space reservations shall be modelled for major connections details (such as;
haunches, gusset plates) to avoid clashes with piping or cable routes

c) Foundation Model:
i. Site: terrain
ii. Foundation: Outline, top and bottom level, piles and plinths and details
iii. Equipment foundations that project above & below slab
iv. Foundations for Building
v. Foundations for steel structures and concrete structures
vi. Trenches / duct foundations
vii. Road crossings
viii. Underground conduits: Outline
ix. Underground culvert and duct bank envelopes
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 8 OF 22

x. Underground Facilities
xi. Wall and Fences: Volume outline including foundations
xii. Roads: Outline, shoulders, upper and lower levels
xiii. Paving: Outline, upper and lower levels and type

d) Concrete Item and Component Model:


i. Concrete Structure: All beams, wall columns, slabs, up stands, sumps, etc., in
dimensionally accurate section, floors with penetrations
ii. Drainage and sewerage: Routing outline and level, drips, manholes, catch basin,
separators, vents and sumps
iii. All underground cable duct/cable trench: Routing, outline, top and bottom level
trenches for electrical and instrument cables and direct buried cables
iv. Stairs
v. Equipment pads
vi. Dikes
vii. Pits, basins and ponds
viii. Curbs not under walls

e) Architectural:
i. Overall dimensions of the buildings showing all the main openings (for doors,
windows, ducts, piping, cable trays, etc.) and HVAC air intakes
ii. Internal walls and partition
iii. Roof and side cladding
iv. Doors and windows
v. Roof continuous monitor

The following items should be excluded in the model.

a. Miscellaneous steel (connection plates, clip angles, etc.)


b. Framing required for wall and roof openings
c. Furniture and equipment in buildings
d. Building finishes will generally not be modelled.

5.3.5 Instrumentation items Modeling

Smart Plant 3D Modeling extent is including, but not limited to, as given below.

a. In-line instruments - including control valve topwork dimensionally accurate for actual
items, relief valves, orifice plates with flanges (including maintenance volumes), integral
orifices, pressure tappings, process isolations, vents and drains connections.
Thermowells, Thermocouple / RTD, analyzer probes withdrawal clearance volumes
b. Offline instruments including transmitters, gauges and local indicators, remote mounted
instrumentation including stands, housings and shades
c. All process connections for instrument on piping and equipment
d. Local panels: Outline and access doors, including access volumes
e. All aboveground instrument cable ducts and cable trays (150mm and larger)
f. Main instrument cable trenches
g. Conduit routing envelope on pipe rack
h. Major instrument cable routes
i. All instrument junction boxes including support frames and access volumes
j. Analyzer houses and shelters: With HVAC air intake, associated bottle racks and vent
stack. Utility connections and samplings. Control room – brief layout showing major
components like DCS, rack room, cabinets etc.
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 9 OF 22

k. Telecom equipment, F&G detectors/devices


l. Cable tray support (6”& above)
m. Air accumulators (local or remotely mounted)

The following items should be excluded in the model.

a. Conduit & Cable tray supports


b. Cable tray dividers

5.3.6 Electrical items Modeling

Smart Plant 3D Modeling extent is including, but not limited to, as given below.

a. Outline for Electrical motors


b. Lighting Fixtures and Lighting Poles
c. Panel boards & junction boxes
d. Major electrical cable routes (like trays, trenches, conduits)
e. Local control station, local panel, lighting panel
f. All transformers, transformer safety cages and access volumes, bus ducts
g. Substations
h. All aboveground electrical cable ducts and cable trays (150mm and larger)
i. Main electrical cable trenches
j. Lighting – all lighting fittings and equipment including any supporting towers and
structures, switches and lighting control equipment.
k. Power and control equipment – Switchgears, bus ducts, motor control stations,
miscellaneous panels, UPS equipment and batteries, junction boxes (including
supporting frames) and distribution panels.
l. Communication and security – telephones, CCTV, miscellaneous panels and racks,
public address speakers, beacons and sirens.
m. Convenient receptacles and switches
n. Disconnect Switches
o. Welding Receptacles

The following items should be excluded in the model.

a. Phones, speakers, etc.


b. Conduit & Cable tray supports
c. Cable tray dividers

5.3.7 Fire Protection Modeling

The following Fire Protection shall be modelled using “SP3D”.

a. Fire main headers & branches


b. Firefighting system (dry risers, fixed water monitor, hose reels, etc.)
c. Block Valves and valves boxes, post indicator valves (PIV)
d. Fire hydrants and monitors
e. Deluge valve manifolds
f. Spray systems
g. Fire alarm push buttons
h. Fire, smoke, heat and gas detectors
i. Firefighting cabinets
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 10 OF 22

j. Alarm pushbutton stations


k. Fire Extinguishers

The following items should be excluded in the model.

a. Pipe hangers
b. Auxiliary Systems
c. Panels

5.3.8 Safety and Others Modeling

All items shall be located and modelled as an “envelope” inside the 3D Model to avoid
clashes with piping, equipment and structures.
Smart Plant 3D Modeling extent is including, but not limited to, as given below.

a. Emergency Equipment
b. Safety, access and egress
i. Volumes of all emergency access and egress/escape route corridors
ii. Maintenance volumes and manways
iii. Dropout volumes.
iv. Laydown areas.
v. Radiation volumes for flares.
vi. Area classification volumes
vii. Cranes access way
viii. Restricted access roads and walkways.
ix. High noise restricted volumes
c. Main lifting equipment
d. Truck access for unloading chemicals/catalyst/additives
e. Maintenance and operability: All necessary lifting and mechanical handling requirements
for removal of loads of 25 kg and more shall be modelled

5.4 Deliverables

As a minimum requirement, the following documents shall be capable being extracted from the 3D
model and associated database.
a. Plot plans
b. Equipment layout/unit plot plan (plan and elevation drawings)
c. General arrangement drawings for piping including detailed plan and elevation
d. Underground piping layout drawings
e. Piping isometric details including bill of materials
f. Piping material take-off (MTO)
g. Structural general arrangement drawings, plan and elevation including material take-off
h. Instrument location plans
i. Electrical equipment and substation layout drawings
j. Cable/tray route and layout
k. AC duct layout and detail.
l. Interference checks (clashes) Report
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 11 OF 22

6 Design Review
6.1 General

6.1.1 The 3D Model Review Workshop shall be based on 3D model progress and usually
conducted at 30%, 60% & 90% progress.
6.1.2 The 3D Model Review Workshop during Basic Engineering phase (FEED) will be
conducted at only 30% progress. However, considering the type and size/complexity of
the project, the number of reviews may be increased to two (at 30% & 60% progress) after
the approval by SABIC.
6.1.3 The 3D Model Review Workshop during Detail Engineering phase (EPC) will be conducted
at 30%, 60% & 90% progress. However, considering the type of project such revamp or
de-bottlenecking (DBN) and size of the project, the number of review may be reduced to
two (at appropriate progress, e.g. 45% & 90%) after approval by SABIC.
6.1.4 3D Model Review shall be carried out for each line specified in the P & ID including
Package Equipment P & ID.
6.1.5 3D Model Review Sessions are broken down into Model Review Packages (MRP), i.e.
process consistent groupings of design areas, Utilities and Offsite (U&O), etc.
6.1.6 3D Model Review shall be carried out using SmartPlant Review (SPR) module of the
SmartPlant-3D (SP-3D) software.

6.2 Design Review Schedule

6.2.1 Design Engineering Company shall arrange and conduct Internal Review to validate the
accuracy of the model including interference check few days prior to the scheduled joint
review with SABIC. The results of internal review shall be communicated to SABIC.
6.2.2 The schedule of 3D Model joint review with SABIC at various stage shall be prepared
according to progress of the project as mentioned in above para. 6.1.

6.3 30% 3D Model Review Workshop

6.3.1 This review shall take place when major equipment and structures are positioned and
focuses on equipment location, structures, maintenance clearances, safety distances,
escape routes, etc.
6.3.2 Construction and commissioning comments (e.g. laydown area, drop areas, space
allocation, etc.) shall be considered at this stage of the review.
6.3.3 Ensure constructability review of the plant facilities during this workshop.
6.3.4 This review (at 30% Completion) shall include, but not be limited to, the items listed in
Attachment-2.

6.4 60% 3D Model Review Workshop

6.4.1 This review shall take place when the modelling of main process lines is complete and
follows the milestone of 60% progress of 3D Model. It focuses on process verification of
critical pipe routing, pipe flexibility, accessibility., operations, maintenance and
commissioning inputs, if any are required at this stage, shall be considered.
6.4.2 This review (at 60% Completion) shall include, but not be limited to, the items listed in
Attachment-2.
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 12 OF 22

6.5 90% 3D Model Review Workshop

6.5.1 This review shall take place when the 3D Model is at 90% of its progress and complete
the milestone of 90% progress of 3D Model. It focuses on the configuration of piping
systems that were not shown in the previous review, i.e. location of electrical and
instrumentation items (Junction Boxes and panels), safety, operability, etc.
6.5.2 This review (at 90% Completion) shall include, but not be limited to, the items listed in
Attachment-2.

7 Execution of Design Review


7.1 General

7.1.1 Design Review files shall be created and latest Smart Plant Review (SPR) file shall be
made available prior to each Model Review stages.
7.1.2 A complete set of the latest release of the following documents shall be made available
and marked “MASTER” as reference during the 3D Model Review Workshop and
distributed to the review team for reference:.
a. Plot Plan
b. Unit Plot Plan/Equipment Layout Drawings
c. P&ID
d. Line List
e. Tie-in list
f. Equipment List
g. Package GA Drawings
h. Equipment Data Sheets
i. Equipment Engineering Drawing
j. Steel Structure Drawings
k. Building and Concrete Structure Drawings
l. Underground Composite Plan
m. Conceptual layout for fire fighting
n. Cable Tray routing Drawings (Electrical & Instrument)
o. Hazardous Area Classification Plan
p. Blast Overpressure Contours Drawings
q. QRA Study Report (if applicable)

7.2 Matrix of 3D Model Items


The scope of items to be modelled for each model review stage shall be in accordance with
Attachment2 “Matrix of 3D Model Items”.

7.3 Color Code


The colour codes of the models shall be in accordance with colors specified in Attachment-3. If
existing model is adopted in case of revamp or De-bottlenecking (DBN) projects, existing color
code should be followed.

7.4 Model Review Comment Tagging System


All the comments of model reviews shall be tagged with numbering as listed in Table-1.
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 13 OF 22

Table-1, Tagging System


Sr. Review Stage Tag Number
No.
1 30% 1 ~ 1000
2 60% 1001 ~ 2000
3 90% 2001 ~ Onwards

As an example, Tag Numbering is explained below:


Each tag number shall be preceded with 30, 60 or 90 as applicable to identify the stage of model
review e.g.: 30201 means 30% model review tag item # 201.

7.5 3D Model Comment Log


As a result of the 3D Model Review Workshop, a comment log sheet shall be prepared by Design
Engineering Company and eventually reviewed by the SABIC. The content of the log sheet shall
be in accordance with Attachement-4.

8 Review Team
In accordance with the requirements of SHEM 02.01, the minimum experience of team members shall
be 5 years. The following team members listed in Table-2 should participate in the 3D Model Review
Workshop.

Table-2 3D Model Review Team

Design
Sr.
Discipline Engineering SABIC/PMT Remarks
No.
Company
1 Project Manager Need Based Need Based
2 Project Engineer Full Time Need Based
3 3D Model Facilitator Full Time Not Applicable
4 3D Model Coordinator Full Time Not Applicable
5 Lead Process Engineer Full Time Full Time
6 Lead Piping Engineer Full Time Full Time
7 Lead Civil/ Structural/Architectural Engineer Part Time Part Time
8 Lead Electrical Engineer Part Time Part Time
9 Lead Instrumentation Engineer Part Time Part Time
10 Lead Mechanical (Static) Engineer Part Time Part Time
11 Lead Mechanical (Rotating) Engineer Part Time Part Time
12 Lead Process Safety Engineer Full Time Full Time
13 Operations Representative Not Applicable Full Time
14 Maintenance Representative Not Applicable Full Time
15 Environment & Industrial Hygiene (E&IH) Not Applicable Full Time
specialist

9 Revision Summary

Revision No. 0, Sep 2017: New SES


NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 14 OF 22

Attachment-1 Areas covered by modelling activities

440 = “X1” AREA, 900 = “X2” AREA, 930 = “X3” AREA, 940 = “X4” AREA, 390 = “X5” AREA

Note: Area Code 440, 900, 930, 940 & 390 and Area Name X1, X2, X3, X4 & X5 shall be specified for specific
project.
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 15 OF 22

Attachment-2 Matrix of 3D Model Items (Note-1)

3D Model Review Stage


Sr. No. Modeling Items Remarks
30% 60% 90%
1 Static Equipment (Tower, Drum, H/Exchanger, Tank, Filter, etc.)
1.1 Equipment Outline/Location O O O
1.2 Equipment Insulation P O O
1.3 Nozzle and Manhole X O O (Note-3)
1.4 Ladder, Platform, Handrail & Stair X O O (Note-3, 4)
1.5 Maintenance space (ex. Tube Bundle Removal) O O O
1.6 Davit O O O (Note-2)
1.7 Lifting lug P O O (Note-2)
1.8 Drop Area O O O
1.9 Fire Water Rings X O O (Note-2)
1.10 Local Instrument on Equipment X O O (Note-2)
1.11 Pipe supports and guides on equipment X P O (Note-2)

2 Rotating Equipment (Pump, Compressor, Blower, etc.)


2.1 Equipment Outline/Location O O O
2.2 Equipment Insulation P O O
2.3 Nozzle P O O
2.4 Local Panels X X O (Note-2)
2.5 Outline of Auxiliary Unit (e.g. Lube/Seal Oil Skids) X X O (Note-3)
2.6 Maintenance space O O O
2.7 Enclosure X O O (Note-3)

3 Package item
3.1 Outline of Package Unit O O O
3.2 Maintenance access O O O
3.3 Piping termination point X O O (Note-2)
3.4 Outline of Auxiliary Unit (e.g. Lube/Seal Oil Skids) X X O (Note-3)

4 Piping
4.1 Nozzles orientation and position X O O (Note-3, 4)
4.2 Manhole opening direction and access way X O O (Note-3)
4.3 Drop zone P O O
4.4 Operating space/maintenance space/access way P O O
4.5 Major Piping (NPS 8 and above) O O O
4.6 Process & Utility, NPS 2 and Lager Piping X O O (Note-2)
4.7 All Process & Utility, NPS 1-1/2 and Smaller Piping X P O (Note-2)
4.8 Piping vent (Highest point) and drain (Lowest point) X P O (Note-2)
4.9 Utility Station Location O O O (Note-2)
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 16 OF 22

3D Model Review Stage


Sr. No. Modeling Items Remarks
30% 60% 90%
4.10 Eye Wash/Safety Shower Location O O O
4.11 In-line Instrument X O O (Note-3)
4.12 Instrument Manifold X X O (Note-2)
4.13 Piping Specialty X O O (Note-3)
4.14 Line Trap piping X X O (Note-2)
4.15 Manifold for Tracing (steam and condensate) X P O (Note-2)
4.16 Jacketed Piping X P O (Note-3)
4.17 Sampling point location and access way X P O (Note-2)
4.18 Tie-in point connection and location P O P
4.19 Insulation X O O (Note-3)
4.20 Pipe Supports including special pipe supports X X O (Note-2)
4.21 U/G Main Header O O O
4.22 U/G Piping all P O O
4.23 Vessel trim X P O (Note-2)
4.24 Spectacle blinds spades and spacers P O O

5 Civil
5.1 Foundation and Footing (Equipment, Structure &
O O O
Buildings)
5.2 Roads O O O
5.3 Paving P O O
5.4 Trenches, ducts and Pits X O O (Note-3)
5.5 Dike P O O
5.6 Pipe Sleeper P O O
5.7 Curb/Spill Wall P O O
5.8 Ramp and steps X O O (Note-3)
5.9 Sewer & Stormwater X O O (Note-3)

6 Steel Structure & Building


6.1 Structural Frames (Steel and Concrete) O O O
6.2 Main Bracing X O O (Note-3)
6.3 Opening Hole (For 6” and Larger Piping) X X O (Note-2)
6.4 Local Platform, Ladder, Handrail, stairs X O O (Note-2)
6.5 Floor plates (gratings and checkered plates) P O O
6.7 Permanent Crane Girder and Monorail X O O (Note-3)
6.8 Foundation for Building & Structure O O O
6.9 Equipment Support on Structure X O O (Note-3)
6.10 T-Support & Its Foundation X X O (Note-3)
6.11 Fire Proofing X O O (Note-2)
6.12 Outline of Building P O O
6.13 Outline for Process Building and Shelter O O O
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 17 OF 22

3D Model Review Stage


Sr. No. Modeling Items Remarks
30% 60% 90%
6.14 Building floor X P O (Note-3)
6.15 Building wall, door, window, roof, cladding, etc. X P O (Note-4)
6.16 Fences P O O
6.17 Shelters and pre-engineered metal buildings P O O (Note-2)
7 Instrument
7.1 In-line instruments P O O
7.1 Offline instruments P O O (Note-2)
7.3 All Cable Trays (width 300mm and larger) P O O
7.4 All Cable Trays (150mm and larger) P O O
7.5 Underground Main Cable Trench O O O
7.6 Analyzer House and Shelter X P O (Note-3)
7.7 Instrument actuator and maintenance space X O O (Note-2)
7.8 Junction Box X P O (Note-3)
7.9 Local Panel X P O (Note-2)
7.10 Air Accumulators X P O (Note-2)
7.11 Telecom equipment, F&G detectors/devices X P O (Note-4)
8 Electrical
8.1 All Cable Trays (width 300mm and larger) P O O
8.2 All Cable Trays (150mm and larger) X O O (Note-3)
8.3 Underground Main Cable Trench O O O
8.4 Local Control Stations or Panel (Outdoor) X X O (Note-2)
8.5 Lighting Fixtures and Lighting Poles X X O
8.6 Substations P O O
8.7 Transformer P O O
8.8 Emergency Diesel Generator P O O
8.9 Junction Boxes X P O (Note-3)
8.10 Major Electrical Equipment (Switchgear, MCC, Bus
duct, UPS, Distribution Panels) X P O (Note-3)
8.11 Communication and Security (PAGA, Outdoor
Telephone Equipment, CCTV) X P O (Note-2)
9 Fire Protection
9.1 Fire-fighting equipment outlines/locations P O O
9.2 Fire Water Line, Header P O O
9.3 Fire Water Line, Sub Lines X O O (Note-2)
9.4 Fire-fighting Piping for A/G X P O (Note-2)
9.5 Block Valves and valves boxes, PIVs P O O
9.6 Fire hydrants and monitors X P O (Note-3)
9.7 Deluge valve manifolds X O O (Note-3)
9.8 Firefighting cabinets and Hose Reel X P O (Note-2)
9.9 Spray systems/nozzles X P O (Note-2)
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 18 OF 22

3D Model Review Stage


Sr. No. Modeling Items Remarks
30% 60% 90%
10 Safety and Others
10.1 Emergency Equipment P O O
10.2 Safety access and egress P O O
10.3 Escape Rout (envelop) P O O
10.4 Main lifting equipment O O O
10.5 Cranes, maintenance (major) access O O O
10.6 Truck access for unloading P O O
chemicals/catalyst/additives

Legend:
Legend: O = To be Modelled, P = Partially Modelled, X = Out of Modelling

Notes:
1. For detailed modelling requirements, refer to Para. 5.3.
2. As this matrix is mainly applicable for EPC phase of the projects, these items should be excluded from
FEED phase of the projects.
3. Although it is not required to be modelled during 30% of EPC, it shall be modelled during Basic Engineering.
4. The extent of modelling shall be carried out to suite the details level of Basic Engineering to comply with
the scope requirement.
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 19 OF 22

Attachment-3 Color Code for Design Review

RAL RAL
Sr. No. Items Description Color No. Color Remarks

1 Static Equipment (Tower, Drum, H/Exchanger, Tank, Filter, etc.)


1.1 General container, tower Silver grey 7001
1.2 Heavy material tank Silver grey 7001
1.3 Reactor, Heat exchanger Silver grey 7001
1.4 Spherical Tank Signal white 9003
1.5 Loading Arms Silver grey 7001
1.6 Steel stack Silver grey 7001
1.7 Flare Silver grey 7001
1.5 Other Equipment Silver grey 7001

2 Rotating Equipment
2.1 Pump Sky blue 5015
2.2 Motor Sky blue 5015
2.3 Compressor、Centrifuge Sky blue 5015
2.4 Fan Sky blue 5015
2.5 Blower

3 Package Equipment
3.1 Industrial furnace Silver grey 7001
3.2 Boiler Silver grey 7001
3.3 Chiller Silver grey 7001

4 Piping
4.1 Ordinary material Silver grey 7001
4.2 Acids and alkalis Violet 4001
Mineral, vegetable and animal oils; combustible
4.3 liquids (petrol, kerosene, diesel, etc.) Ochre brown 8001
Gases in either gaseous or liquefied condition
4.4 (except air), chemicals Yellow-ochre 1004
4.5 Water Green 6010
4.6 waste water Black 9005
White
4.7 Steam 9006
aluminum grey
4.8 Air and Oxygen Light blue 5012
4.9 Nitrogen Zinc yellow 1018
1.10 Ammonia Signal yellow 1003
4.11 Chlorine Fern Green 6025
4.12 The combustible gas such as coal gas Zinc yellow 1018
4.13 Other liquids Black 9005
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 20 OF 22

RAL RAL
Sr. No. Items Description Color No. Color Remarks

4.14 Emergency vent pipe (nozzle) Traffic Red 3020


4.15 Instrument air piping Sky blue 5015
4.16 Pipe Support Sapphire blue 5003
4.17 Manual Valve Capri Blue 5019
4.18 Control valve Traffic Red 3020
4.19 Safety Valve & Special fitting Traffic Red 3020

5 Civil, Structural & Architectural


5.1 Wall Sapphire blue 5003
5.2 Window Traffic green 6024*
5.3 Ground Concrete grey 7023*
5.5 Stairs Signal yellow 1003
5.6 Railing Signal yellow 1003
5.7 Ramp and steps Concrete grey 7023*
5. Rain pipe Signal white 9010*
5.9 Roof maintenance ladder Signal yellow 1003
5.10 Structural beam and column Sapphire blue 5003
5.11 Floor Concrete grey 7023*
5.12 Foundation and Footing Black grey 9005*
5.13 Road Sapphire blue 5003
5.14 Fence Sapphire blue 5003
5.15 Trench Sapphire blue 5003

6 Instrument
6.1 Operating Station Blue grey 7031
6.2 Instrument panel Blue grey 7031
6.3 Junction box Blue grey 7031
6..4 Panel-mounted Instrument Blue grey 7031
6.5 local instrument Blue grey 7031
6.6 Cable Tray, Underground Cable Ways Blue grey 7031
6.7 Cable Trench Blue grey 7031
6.7 Conduit Jet black 9005
6.9 Air Accumulators Blue grey 7031
6.10 support frame Sapphire blue 5003

7 Electrical
7.1 Switch gear, Distribution Panel/Cabinet Blue grey 7031
7.2 Transformer Blue grey 7031
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 21 OF 22

RAL RAL
Sr. No. Items Description Color No. Color Remarks

7.3 Local Control Station Blue grey 7031


7.4 Distribution box Blue grey 7031
7.5 Welding Outlet Blue grey 7031
7.6 Lighting Fixture Blue grey 7031
7.7 Conduit Jet black 9005
7.8 Cable Tray, Underground Cable Ways Blue grey 7031
7.9 Cable Trench Blue grey 7031
7.10 Support frame Sapphire blue 5003

8 Fire Protection
8.1 Fire-fighting equipment Traffic red 3020
8.2 Firefighting Piping Flame Red 3000
8.3 Eye wash/safety shower Mint green 6029
8.4 Foam mixture Yellow green 6018

9 Safety and Others


Warning of danger Yellow, with 1018
9.1 black
diagonal

Notes:
1. If the color code is not available for new items envisaged in the project, Design Engineering Company may
use their own company color code after SABIC approval.
NUMBER P05-G01
Requirement of 3D Model and Review REV. NO. 0
DATE SEP 2017
PAGE 22 OF 22

Attachment-4 Comment Log Sheet

Tag: 30001
Session: 30% Model Review
Date:
Unit:
Description: Vent valve shall be added at the highest point.
Discipline Responsible: Piping
Before:

After:

Design Engineering Company Reply:


Revised as per SABIC comment.