RACC

Grease trap cleaning


Description Qty Unit Unit cost Amount
Labor
Foreman 1 man-day 900.00 900.00
Driver 2 man-day 750.00 750.00
Crew (6) 6 man-day 700.00 4,200.00
Equipment
Materials/handtools 1 unit/day 11,899.79 11,899.79
Hauling/Disposal 1 ls 9,375.00 9,375.00
Direct Cost Php 27,124.79
Profit 15% 4,068.72
vat 12% 3,743.22
TOTAL COST Php 34,936.73
COST / DAY 32,470.00

Submitted:

RAY S. ABALOS
R. ABALOS CONSTRUCTION
UPA

DESCRIPTION QTY UOM UNIT COST TOTAL AMT


Supplies, tools, equipment , ppe
Tools & Equipment
deodorizer 12 container/yr 5,000.00 60,000.00
Drum 80 pc/yr 2,000.00 160,000.00
Duct Tape 100 pc/yr 350.00 35,000.00
Aerotape 20 pc/yr 650.00 13,000.00
Push Brush 12 pc/yr 680.00 8,160.00
mop 12 pc/yr 1,600.00 19,200.00
aluminum ladder (max. 4m) 1 pc/yr 5,500.00 5,500.00
pulley and rope 6 pc/yr 2,500.00 15,000.00
shovel 12 pc/yr 900.00 10,800.00
rake 12 pc/yr 900.00 10,800.00
Scoop 12 pc/yr 1,200.00 14,400.00
Flashlight 4 pc/yr 1,500.00 6,000.00
Service Truck 192 eq/yr 2,500.00 480,000.00
Pressure Pump 96 eq/yr 500.00 48,000.00
Generator 96 eq/yr 600.00 57,600.00
Wheelbarrow 2 pc/yr 5,500.00 11,000.00
Lighting Fixtures 192 eq/yr 300.00 57,600.00

PPE Safety helmet 12 pc 160.00 1,920.00


rubber palm protective sewer gloves 144 pair 60.00 8,640.00
safety goggles 12 pair 400.00 4,800.00
full body harness and lanyard 2 pc 980.00 1,960.00
safety shoes 6 pair 1,600.00 9,600.00
safety boots 6 pair 350.00 2,100.00
coveralls 3 pc 2,500.00 7,500.00
Reflectorized traffic vest 12 pc 150.00 1,800.00
First Aid Kit 12 set/yr 5,000.00 60,000.00
Half mask Respirator (twin type cartridge) 4 pc 4,000.00 16,000.00
Waders 8 pc 2,000.00 16,000.00
Tools and PPE / Year 1,142,380.00
Tools and PPE / Day 11,899.79

HAULING AND DISPOSAL OF GREASE


Disposal of GREASE 12 TL/yr 75,000.00 900,000.00

Others - Disposal / Year / 1 team 900,000.00


Other - Disposal / Day / 1 team 9,375.00

SubmittedJOHN PAUL SUGASTE


R. ABALOS CONSTRUCTION