CIVIL WORKS

PROJECT NAME: PROPOSED DIRTY KITCHEN


OWNER : MA. NOVI V. RAAD, SAMY RAAAD & MELVI VIBA
LOCATION : PANGLAO, BOHOL

BILL OF QUANTITIES
RATES
ITEM DESCRIPTION UNIT QTY AMOUNT
MATERIALS LABOR & OTHERS UNIT RATE

DIV 00 GENERAL REQUIREMENTS, PRELIMINARIES

Sub-Total DIV 00: GENERAL REQUIREMENTS, PRELIMINARIES

DIV 01 EARTHWORKS

WAREHOUSE BUILDING

1.0 Excavation m³ 200.00 - 28.50 28.50 5,700.00

Sub-Total DIV 05: EARTHWORKS 5,700.00

DIV 02 CONCRETE REINFORCEMENTS

Supply, fabrication, Installation of Reinforcement


Steel Bars including all necessary fixing hardwares
and accessories, shoring, scaffolding, bracing, and
consumables, as shown in the plans and as
necessary to complete the works

1.0 Footing kg 954.00 12.30 11.40 23.70 22,605.10

2.0 Columns kg 682.00 12.30 11.40 23.70 16,160.04

3.0 Beam kg 445.00 12.30 11.40 23.70 10,544.31

4.0 Slab on Fill kg 85.00 12.30 11.40 23.70 2,014.08

Sub-Total DIV 04: CONCRETE REINFORCEMENTS 51,323.52

DIV 03 CONCRETING WORKS

Supply and Placing of Concrete Works including all


necessary grouting, vibrating, tampering, wetting,
sampling, protecting as shown in the plans and as
necessary to complete the system

1.0 Footing m³ 0.20 5,532.78 498.75 6,031.53 1,206.31

2.0 Columns m³ 0.40 5,532.78 498.75 6,031.53 2,412.61

3.0 Beam m³ 0.50 5,532.78 498.75 6,031.53 3,015.77

4.0 Slab on Fill m³ 4.00 5,532.78 498.75 6,031.53 24,126.13

Sub-Total DIV 05: CONCRETING WORKS 30,760.81

Page 1 PROPOSED DIRTY KITCHEN


CIVIL WORKS

DIV 04 OTHERS

BILL SUMMARY OF COST


Div 00 GENERAL REQUIREMENTS, PRELIMINARIES -

Div 01 EARTHWORKS 5,700.00

Div 02 CONCRETE REINFORCEMENTS 51,323.52

Div 03 CONCRETING WORKS 30,760.81

Div 04 OTHERS

GRAND TOTAL AMOUNT PHP 87,784.34

Submitted by :

Address :

Signature : _____________________________________________

Page 2 PROPOSED DIRTY KITCHEN