Professional Documents
Culture Documents
SERVING LOAD
THROUGH
TRANSMISSION NETWORK
FN PN
Problem Formulation :
The objective function, FT ,, is equal to the total cost
for supplying the indicated load.
N
Constraint equation : = 0 = Pload − P
i =1
i → NO LOSSES
Ploss is a function of Pi
LAGRANGE function :
L = FT +
The necessary conditions for an extreme value of the
objective function :
L dFi Ploss
= − (1 − )=0
Pi dPi Pi
COORDINATION EQUATIONS :
dFi Ploss
+ = N equations
dPi Pi
N
Pload + Ploss − P = = 0
i =1
i 1 constraint
Ploss is a function of Pi
EXAMPLE 3C :
No. System Input-Output Curve Output- Input- Fuel Cost
Unit Input Max Min ($/Mbtu)
(MW) (MW)
Unit 1 Coal-Fired MBtu 600 150 1.1
MBtu
MBtu
MBtu
H 1 =2 510 .0 + 7.2 P1 + 0.00142P12
Steam
H132 ===510
78..00.+0
310 + 7+ .85
7..2797
P +3P0+2.h
1P +.0
00142
0 P1 P3P2
00482
.00194 2 2
hhh
MBtu
Unit 2 Oil-Fired H2 = 310.0 + 7.85P2 + 0.00194P2 400 100 1.0
2
Steam h
Unit 3 Oil-Fired MBtu 200 50 1.0
H3 = 78.0 + 7.97 P3 + 0.00482P3
2
Steam h
P1 + P2 + P3 − 850 − Ploss = 0
NON-LINEAR EQUATIONS
Using Lambda Iteration method :
865.83 8344.55
−1
Ploss
1 −
Pi = Penalty Factor Total Loss = 15.83 MW
−1
dF Ploss
= i 1 − = 9.5282 Total Load = 850 MW
Pi
dPi
EXAMPLE 3D :
Input-output characteristics of generating plants :
H(Mbtu/h) = A + BP + CP2 + DP3 (P in MW)
A B C D
Unit 1 749.55 6.95 9.68 x 10-4 1.27 x 10-7
Unit 2 1285.0 7.051 7.375 x 10-4 6.453 x 10-8
Unit 3 1531.0 6.531 1.04 x 10-3 9.98 x 10-8
2500.0 22729.25
dFi R
= Fi'
dPi MWh
0 Pi max
Pi
Pi min
Pi0 Pi (MW )
Pi = the change in unit load
P1 = , P2 = ………… PN =
F1" F2" FN"
Total change in generation (= change in total system demand) :
PD = P1 + P2 + ......... + PN
F
1
= ''
i i
Pi ''
1 / Fi
=
PD 1
F ''
i i
EXAMPLE 3I :
hhh
MBtu
Unit 2 Oil-Fired H2 = 310.0 + 7.85P2 + 0.00194P2 400 100 1.0
2
Steam h
Unit 3 Oil-Fired MBtu 200 50 1.0
H3 = 78.0 + 7.97 P3 + 0.00482P3
2
Steam h
dF1
= 7.92 + 0.003124P1 =
dP1
dF2 = 9.148 R/MWh
= 7.85 + 0.00388P2 =
dP2
dF3 P1 = 393.2 MW
= 7.97 + 0.00964P3 = P2 = 334.6 MW
dP3
P3 = 122.2 MW
P1 + P2 + P3 = 850 MW
Optimal Economic
Solution
Calculate the dispatch for a total load of 900 MW
Similarly, we obtain :
P2 (0.00388) −1
= = 0.38
PD 681.57
P3 (0.00964) −1
= = 0.15
PD 681.57
Pi
Pnew i = Pbase i + PD for i = 1, 2, 3
PD
MW.
MW.
EXAMPLE 7.7 : SOFTWARE MATLAB
EXAMPLE 7.8 :
Fig. for this example shows the one-line diagram of a 5 bus simple
power system with generator at buses 1, 2 and 3. Bus 1, with its
voltage set at 1.06∠0º pu , is taken as the slack bus. Voltage magnitude
and real power generation at bus 2 and 3 are 1.045 pu. 40 MW, and
1.030 pu. 30 MW, respectively.
The B matrices of the loss formula for this system are given in
per unit on a 100 MVA base as follows,