Uttar Pradesh/Bihar

Packages Chainages Contractor Status

Junction with NH-19 and Varanasi Ring Road near Rewasa


Land
village (Chandauli district) to junction with Chandauli-
Package-1 NKC Projects acquisition
Chainpur road near Khainti village (Kaimur district, Bihar)
underway
(0.000 km-27.000 km)

Bihar

Packages Chainages Contractor Status

Junction with Chandauli-Chainpur Road near Khainti Land


PNC Infratech
Package-2 village to junction with Bhabhua-Adhaura road near acquisition
Pvt. Ltd.
Palka village, Kaimur district (27.000 km-54.000 km) underway

Land
Junction with Bhabhua-Adhaura road in Bhairopur village PNC Infratech
Package-3 acquisition
to Konki village (Rohtas district) (54.000 km-90.000 km) Pvt. Ltd.
underway

Bidding
Package-4 TBA Pending notice process
underway

Junction with NH-119 in Malpura village to Lerua village


Bidding
(Aurangabad district), including a 4-lane spur to NH-19
Package-5 TBA process
from NH-119 (spur length-6.6 km) (105.300 km to
underway
116.000 km)

Land
Pachmon village to Anarbansalea village, Aurangabad PNC Infratech
Package-6 acquisition
district (116.000 km to 151.200 km) Pvt. Ltd.
underway

Land
Anarbansalea village to Sagrampur village (Gaya district) GR
Package-7 acquisition
(151.200 km to 184.700 km) Infraprojects
underway
Jharkhand

Packages Chainages Contractor Status

Sonepurbigha village to junction with NH- Tracks and Towers Land


Package-8 22 near Chatra, Chatra district (184.700 km to Infratech Pvt. Ltd.–Rail acquisition
222.000 km) Vikas Nigam Limited (JV) underway

Chatra to junction with NH-100 in Deoria Land


Ram Kripal Singh
Package-9 village (Hazaribagh district) (222.000 km to acquisition
Construction Pvt. Ltd.
253.000 km) underway

Land
Deoria village to Donoreshan village (Ramgarh H.G. Infra Engineering
Package-10 acquisition
district) (253.000 km to 288.600 km) Ltd.
underway

Donoreshan village to junction with NH-20 in Land


Package-11 Bongabar village, Ramgarh district (288.600 Ceigall India acquisition
km to 325.500 km) underway

Junction with NH-20 in Bongabar village to Land


Package-12 Junction with NH-320 in Lepo village (Bokaro Ceigall India acquisition
district) (325.500 km to 358.500 km) underway

Junction with NH-320 in Lepo village to Land


H.G. Infra Engineering
Package-13 Kamlapur village (Jharkhand-West Bengal acquisition
Ltd.
border) (358.500 km to 387.200 km) underway

The remaining stretch till Kolkata is under package division, land acquisition and DPR preparation.