Length (In
S.No. Project Name Details State Client Mode
KMs)
Construction of Four Lane
Elevated Road from Digha to
Deedarganj, from Dulli Ghat to
Nuruddin Ghat, from
1 Ganga Path Dharamshala Ghat to old NH-30 4.09 Bihar BSRDCL EPC
along with connectivity to Ashok
Rajpath at Kangan Ghat and
Patna Ghat with allied facilities
at Patna
NH-327 E: Galgalia-
2 Bahadurganj Section Four laning of the Highway 49 Bihar NHAI HAM
(Package 1)
NH-327 E:
3 Bahadurganj-Araria Four laning of the Highway 44.98 Bihar NHAI HAM
Section (Package 1)
NH-130A: Bilaspur -
Urga section
Four Laning of the Highway
(Lot-3/
4 from Dheka Village to Bhaisma 70.20 Chhattisgarh NHAI HAM
Chhattisgarh/Pkg-1,
Village
Raipur - Dhanbad
Economic Corridor)
Vadodara Mumbai Construction of Eight Lane
5 Expressway (Phase 1 Access-Control Expressway 36.93 Gujarat NHAI HAM
Package 6) from Ena to Kim section
NH - 709AD: Shamli to
Uttar
10 Muzaffarnagar - Upgradation of the Highway 42.87 NHAI EPC
Pradesh
Package 2
1
G R INFRAPROJECTS LIMITED
Highways & Bridges Projects – Yet to Commence
Length
S.No. Project Name Details State Client Mode
(In KMs)
Development of 6 Lane
Greenfield Varanasi-Ranchi-
1 Varanasi-Ranchi-Kokata Kolkata highway from 33.50 Bihar NAHI HAM
Anarbansalea village to
Sagrampur village